Question

In: Accounting

Question 1 The following information is for Obaapa Ltd's July production:  Standards: Material: 3.0 feet per unit...

Question 1

The following information is for Obaapa Ltd's July production:  Standards: Material: 3.0 feet per unit @ GH¢4.20 per foot, Labour: 2.5 hours per unit @ GH¢7.50 per hour. Actual: Production: 2,750 units produced during the month, Material: 8,700 feet used; 9,000 feet purchased @ GH¢4.50 per foot, Labor: 7,000 direct labour hours @ GH¢7.90 per hour.  Determine the total material cost and total labour cost variance, separating them into their corresponding price and quantity variances. show all workings clearly

Question 2

Akyede Groups of Companies uses a standard cost system for its production process and applies overhead based on direct labour hours. The following information is available for May when Akyede produced 4,500 units: Standard: Direct labour hour per unit - 2.50, Variable overhead per direct labour hour - GH¢1.75, the fixed overhead per direct labour hour - GH¢3.10, Budgeted variable overhead - GH¢21,875, Budgeted fixed overhead - GH¢38,750. Actual: Direct labour hours - 10,000, Variable overhead- GH¢26,250, Fixed overhead- GH¢38,000. Calculate the total variable overhead cost and total fixed overhead cost variance, indicating the respective spending or expenditure variance and efficiency (volume) variance.

Solutions

Expert Solution

Answer :

Question no -1

Material Cost variance = Standard cost - Actual cost

= 2750* 3*4.2 - 8700*4.5

= 4500 Unfavorable

Material Price variance = (SP - AP)AQ used

= (4.2 - 4.5)*8700

= 2610 Unfavorable

Material price variance can be also calculated at the time of purchase.

Material price variance = (SP - AP)AQ Purchased

= (4.2 - 4.5 )*9000

= 2700 Unfavorable

Material Quantity Varince = (SQ - AQ )* SP

= (2750*3 - 8700 )*4.2

= 1890 Unfavorable

Labor cost Variance = Standard cost - Actual cost

= 2750*2.5*7.5 - 7000*7.9

= 3737.5 Unfavorable

Labor rate / price variance = (SR - AR )*AH

= (7.5- 7.9 )*7000

= 2800 Unfavorable

Labor Efficiency variance / Quantity Variance = (SH- AH )*SR

= (2750*2.5 - 7000)*7.5

= 937.5 Unfavorable

Question no -2

Variable OH cost variance = Standard cost - Actual cost

= 4500* 2.5*1.75 - 26250

= 6562.5 Unfavorable

Variable oh Spending variance = (SR- AR )*AH

= SR *AH - AR*AH

= 1.75* 10000- 26250

= 8750 Unfavorable

Variable oh Efficiency variance = (SH -AH )*SR

= (4500*2.5 - 10000)*1.75

= 2187.5 Favorable

Fixed oh cost variance = Absorbed Fixed oh - Actual fixed oh

= 4500*2.5*3.1 - 38000

= 3125 Unfavorable

Fixed oh Expenditure variance = Budgeted fixed oh - Actual fixed oh

= 38750- 38000 = 750 Favorable

Fixed oh Volume variance = Absorbed fixed oh - Budgeted fixed oh

= 4500*2.5*3.1 - 38750

= 3875 Unfavorable


Related Solutions

QUESTION 1 The material that has the lowest stress per unit of strain diagram is: Wood...
QUESTION 1 The material that has the lowest stress per unit of strain diagram is: Wood Cast Iron Concrete High strength steel QUESTION 2 Aluminum Metals subjected to loads: Do not exhibit a clearly defined yield point compared to steel. Have a greater difference between tensile and yield strengths compared to steel. Have a Modulus of elasticity one-third greater than structural steel. Have a coefficient of Thermal expansion one-half that of structural steel. QUESTION 3 An alloying element is any...
1. Costs per Equivalent Unit The following information concerns production in the Baking Department for March....
1. Costs per Equivalent Unit The following information concerns production in the Baking Department for March. All direct materials are placed in process at the beginning of production. ACCOUNT Work in Process—Baking Department ACCOUNT NO. Date Item Debit Credit Balance Debit Credit Mar. 1 Bal., 9,000 units, 4/5 completed 21,600 31 Direct materials, 162,000 units 291,600 313,200 31 Direct labor 81,750 394,950 31 Factory overhead 45,978 440,928 31 Goods finished, 164,100 units 426,300 14,628 31 Bal. ? units, 2/5 completed...
Costs per Equivalent Unit and Production Costs The following information concerns production in the Forging Department...
Costs per Equivalent Unit and Production Costs The following information concerns production in the Forging Department for November. All direct materials are placed into the process at the beginning of production, and conversion costs are incurred evenly throughout the process. The beginning inventory consists of $105,410 of direct materials. ACCOUNT Work in Process—Forging Department ACCOUNT NO. Date Item Debit Credit Balance Debit Credit Nov. 1 Bal., 8,300 units, 30% completed 114,125 30 Direct materials, 76,000 units 942,400 1,056,525 30 Direct...
Costs per Equivalent Unit and Production Costs The following information concerns production in the Forging Department...
Costs per Equivalent Unit and Production Costs The following information concerns production in the Forging Department for November. All direct materials are placed into the process at the beginning of production, and conversion costs are incurred evenly throughout the process. The beginning inventory consists of $115,200 of direct materials. ACCOUNT Work in Process—Forging Department ACCOUNT NO. Date Item Debit Credit Balance Debit Credit Nov. 1 Bal., 9,000 units, 70% completed 137,880 30 Direct materials, 82,000 units 1,033,200 1,171,080 30 Direct...
Costs per Equivalent Unit and Production Costs The following information concerns production in the Forging Department...
Costs per Equivalent Unit and Production Costs The following information concerns production in the Forging Department for September. All direct materials are placed into the process at the beginning of production, and conversion costs are incurred evenly throughout the process. The beginning inventory consists of $52,070 of direct materials. ACCOUNT Work in Process—Forging Department ACCOUNT NO. Date Item Debit Credit Balance Debit Credit Sept. 1 Bal., 4,100 units, 30% completed 54,899 30 Direct materials, 37,000 units 458,800 513,699 30 Direct...
Use the information in the table below to answer the following questions. Production per unit of...
Use the information in the table below to answer the following questions. Production per unit of Labor                         U.S.                 Argentina Wheat              100                  200 Beef                200                  400 Does either country have an absolute advantage in the production of wheat or beef? Explain. (b)        What is the opportunity cost of wheat in each country? (c)        What is the opportunity cost of beef in each country? (d)        Analyze comparative advantage and opportunities for trade between the U.S. and Argentina. Unit labor Requirements...
Ch 17#13 Costs per Equivalent Unit and Production Costs The following information concerns production in the...
Ch 17#13 Costs per Equivalent Unit and Production Costs The following information concerns production in the Forging Department for November. All direct materials are placed into the process at the beginning of production, and conversion costs are incurred evenly throughout the process. The beginning inventory consists of $91,800 of direct materials. ACCOUNT Work in Process—Forging Department ACCOUNT NO. Date Item Debit Credit Balance Debit Credit Nov. 1 Bal., 9,000 units, 30% completed 101,520 30 Direct materials, 82,000 units 811,800 913,320...
Costs per Equivalent Unit The following information concerns production in the Baking Department for December. All...
Costs per Equivalent Unit The following information concerns production in the Baking Department for December. All direct materials are placed in process at the beginning of production. ACCOUNT Work in Process—Baking Department ACCOUNT NO. Date Item Debit Credit Balance Debit Credit Dec. 1 Bal., 24,000 units, 3⁄4 completed 116,700   31 Direct materials, 134,000 units 234,500    351,200 31 Direct labor 150,000 501,200 31 Factory overhead 375,000    876,200 31 Goods finished, 128,000 units    760,700 115,500 31 Bal., ? units,...
Costs per Equivalent Unit The following information concerns production in the Baking Department for March. All...
Costs per Equivalent Unit The following information concerns production in the Baking Department for March. All direct materials are placed in process at the beginning of production. ACCOUNT Work in Process—Baking Department ACCOUNT NO. Date Item Debit Credit Balance Debit Credit Mar. 1 Bal., 7,800 units, 2/5 completed 17,160 31 Direct materials, 140,400 units 266,760 283,920 31 Direct labor 72,440 356,360 31 Factory overhead 40,744 397,104 31 Goods finished, 142,200 units 383,784 13,320 31 Bal. ? units, 2/5 completed 13,320...
Costs per Equivalent Unit The following information concerns production in the Baking Department for May. All...
Costs per Equivalent Unit The following information concerns production in the Baking Department for May. All direct materials are placed in process at the beginning of production. ACCOUNT Work in Process—Baking Department ACCOUNT NO. Date Item Debit Credit Balance Debit Credit May. 1 Bal., 8,400 units, 1/3 completed 20,020 31 Direct materials, 151,200 units 317,520 337,540 31 Direct labor 89,590 427,130 31 Factory overhead 50,396 477,526 31 Goods finished, 153,300 units 459,760 17,766 31 Bal. ? units, 4/5 completed 17,766...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT