Question

In: Accounting

After the introduction of a new information system, a post implementation review is usually carried out....

After the introduction of a new information system, a post implementation review is usually carried out.

1. List and describe three reasons for this review?

2. Describe three assessment/evaluation criteria that may be used in this review?

3. List and describe three factors that the post implementation review considers?

Solutions

Expert Solution

1. Reasons of Post implementation review are as follows:

  1. It helps in ascertaining how succesful the project is. the main objective of PIR is to see if the project has met its objectives and delivered the expected benefits. It also helps in identifying whether the specific requirements if any have been met.
  2. It helps in identifying if furthere improvements or alterations are requied in order to achieve the desired results. It examines the efficacy of all the working business solution elements.
  3. It heps in identifying the lessons learned from the project which can be used further by the other members of the team or other project members or by the otganisation to ensure better decision making in future

2. Evaluation criteria that may be used in this review

  1. Review existing documents : Project outcomes and their performance measuresNote may have already been defined in project documents such as business case report, project brief and funding paper. Therefore, the fi rst step is to examine various project documents to see if suitable and adequate performance measures are already in place
  2. Develop performance measures : The performance measures must be developed by keeping in mind the requirements of end users, conseidering success ratios of similar projects, strategies followed by them, etc
  3. Design data collection approach : Data on performance measures may be located in readily available sources, e.g. performance reports, or need to be collected from other sources.

3. factors that the post implementation review considers are:

  1. Determine the satisfaction of stakeholders. whether all the requirements of end users have been met and the sponsors are satisfied with the results.
  2. Determine the project's costs and benefits: For a project to be succesful it is very important that the benfits exceeds the costs for which is is extremely important to consider a cost benefit analysis.
  3. Identify areas for further development: Another factor that needs to be considered is if there are any scope of further improvements and whether more training of staff is required and planning the future of the project thereafter

Related Solutions

A. A review engagement is carried out in accordance with the International Standard for Review Engagements...
A. A review engagement is carried out in accordance with the International Standard for Review Engagements (ISRE) 2400. During review engagement, the auditor should apply the same materiality considerations as would be applied if an audit opinion on the financial statements were being given. Although there is a greater risk that misstatements will not be detected in a review than in an audit, the judgment as to what is material is made by reference to the information on which the...
When the Accounting Standards Board issues new standards, the implementation date is usually 12 months after...
When the Accounting Standards Board issues new standards, the implementation date is usually 12 months after the issue date, but early implementation is encouraged. As the Controller for Wheelz Manuafacturing your are discussing their financial statements with Wheelz' vice-president the need for early implementation of a standard that would result in a fairer presentation of the company's financial condition and earnings. When the vice-president determines that early implementatino of the standard will lower the reported net income for the year,...
Implementation of a Payroll Management System Introduction Payroll management system project in C++ is a console...
Implementation of a Payroll Management System Introduction Payroll management system project in C++ is a console application with the use of Object Oriented Programming with graphics. The project has multiple classes and sub-classes with many features within them. Basic operations: users can perform via this program project that are based on file handling are adding new employee record, modifying employee record and deleting record, displaying one or all employee’s record. Besides these, payroll management also allows users to print the...
The FASB issues new standards on accounting. The implementation date is usually a year from the...
The FASB issues new standards on accounting. The implementation date is usually a year from the date of issuance with early implementation encouraged. Jane Durham, chief accountant is discussing implementing this new standard as soon as possible. The CFO however realizes that an early implementation will have a negative effect on the firm's net income for the year. The CFO discourages the chief Accountant from implementing the standard until the required date. Is the CFO's action proper? Why or why...
After the Introduction of a new product, the percent of the public that is aware of...
After the Introduction of a new product, the percent of the public that is aware of the product is approximated by A(t)= 10t22-t where t is time in months. (a). Calculate A'(t). (b). Find the rate of change of the percent of the public that is aware of the product after 2 months and after 4 months and include units. (c). In part (b), one of your answers should have been positive while the other should have been negative. what...
An experiment was carried out to determine the electrical properties of a new conducting material. A...
An experiment was carried out to determine the electrical properties of a new conducting material. A bar was made out of the material,
A medIV. A medical trial into the effectiveness of a new medication was carried out. 120...
A medIV. A medical trial into the effectiveness of a new medication was carried out. 120 females and 90 males took part in the trial. Out of those people, 50 females and 30 males responded positively to the medication. Given below is a contingency table with the given information filled in. Female Male Total Positive 50 30 Negative 70 60 Total a. What is the probability that a randomly selected person from the sample is a female? b. What is...
An analysis carried out during and shortly after the project life cycle that attempts to capture...
An analysis carried out during and shortly after the project life cycle that attempts to capture positive and negative learning is represented in which of the following? Performance evaluation Lessons learned Scenario analysis Strategic objectives Variance analyses
Brief introduction of new trends in post-war international trade development
Brief introduction of new trends in post-war international trade development
Brief introduction of new trends in post-war international trade development
Brief introduction of new trends in post-war international trade development
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT