In: Finance
The Dolphin Corporation, a firm in the 40 percent marginal tax
bracket with a 9 percent cost of capital, is considering a new
project. This project involves the introduction of a new product.
This project is expected to last 4 years and then to be terminated.
Cost of new plant and equipment is $990,000. Shipping and
installation costs are $10,000. The company needs to increase its
working capital requirement. There will be an initial inventory
requirement of $15,000 just to start the production. Out of this
amount, the company can owe money in the form of account payable.
The payable will increase by $3,000. All the investment in working
capital is paid at the termination of the project at year 4. The
company expects to sell 27,000 units per year in four years. Sales
price per unit is $25 per year. Total variable cost of productions
is $10 per unit. At the end of 4th year, the
equipment should have a market value, which equals to salvage value
because book value of the equipment is zero, of $50,000. The assets
would be depreciated under MACRS with 3- year life. Year 1
depreciation rate is 33%, year 2 is 45%, year 3 is 15%, and year 4
is 7%.
Questions:
a. Given the information, fill in the excel work sheet to estimate the net cash flows of the project.
b. Determine the NPV, IRR, and payback period of the project.
c. What is your recommendation about the project?
Total cost of equipment = purchase cost + installation cost
Net investment in working capital = investment in inventory - accounts payable
Operating cash flow (OCF) each year = income after tax + depreciation
profit on sale of equipment at end of year 4 = sale price - book value
book value is zero as the equipment is fully depreciated.
after-tax salvage value = salvage value - tax on profit on sale of equipment
NPV and IRR are calculated using NPV and IRR functions in Excel
Payback period is the time taken for the cumulative cash flows to equal zero
Payback period = 2 + (cash flow required in year 3 for cumulative cash flows to equal zero / year 3 cash flow) = 2 + ($214,000 / $303,000) = 2.71 years
NPV is $143,776
IRR is 15.62%
It is recommended to accept the project as the NPV is positive and the IRR is higher than the cost of capital