Question

In: Finance

An investment project has the following cash flows: CF0 = -1,200,000; C01 – C05 = 300,000...

An investment project has the following cash flows: CF0 = -1,200,000; C01 – C05 = 300,000 each

If the required rate of return is 12%, calculate IRR= (   )%.

Solutions

Expert Solution

Computation of IRR using trial and error method:

Let’s compute NPV at discount rate of 7 %

Year

Cash Flow (C)

Computation of PV Factor

PV Factor @ 7 % (F)

PV (C x F)

0

-$1,200,000

1/ (1+0.07)0

1

-$1,200,000

1

300,000

1/ (1+0.07)1

0.9345794392523

280,373.831776

2

300,000

1/ (1+0.07)2

0.8734387282732

262,031.618482

3

300,000

1/ (1+0.07)3

0.8162978768909

244,889.363067

4

300,000

1/ (1+0.07)4

0.7628952120475

228,868.563614

5

300,000

1/ (1+0.07)5

0.7129861794837

213,895.853845

NPV1

$30,059.230784

As NPV is positive, let’s compute NPV at discount rate of 8 %

Year

Cash Flow (C)

Computation of PV Factor

PV Factor @ 8 % (F)

PV (C x F)

0

-$1,200,000

1/ (1+0.08)0

1

-$1,200,000

1

300,000

1/ (1+0.08)1

0.9259259259259

277,777.777778

2

300,000

1/ (1+0.08)2

0.8573388203018

257,201.646091

3

300,000

1/ (1+0.08)3

0.7938322410202

238,149.672306

4

300,000

1/ (1+0.08)4

0.7350298527965

220,508.955839

5

300,000

1/ (1+0.08)5

0.6805831970338

204,174.959110

NPV2

-$2,186.988877

IRR = R1 + [NPV1 x (R2 – R1)/ (NPV1 – NPV2)]

= 7 % + [$ 30,059.230784 x (8 % - 7%)/ ($ 30,059.230784– (-$ 2,186.988877))]

= 7 % + [($ 30,059.230784 x 1 %)/ ($ 30,059.230784 + $ 2,186.988877)]

= 7 % + ($ 300.59230784/ $ 32246.219661)

= 7 % + 0.009321784

= 7 % + 0.93 % = 7.93 %

IRR of the project is 7.93 %


Related Solutions

An investment project has the following cash flows: CF0 = -1,000,000; CF1 – CF8 = 200,000...
An investment project has the following cash flows: CF0 = -1,000,000; CF1 – CF8 = 200,000 each. If the required rate of return is 12%: a.       What decision should be made using NPV? (5%) b.      How would the IRR decision rule be used for this project? What decision would be reached? (10%)              c.       How are the above two decisions related? (10%)
Project A has the following Cash Flows: Cost = $1,200,000; Cash flows the following years as...
Project A has the following Cash Flows: Cost = $1,200,000; Cash flows the following years as follows: Year 1 = $274,600; Year 2 = $298,000; Year 3 = $303,950; Year 4 = $312,875; and Year 5 = $374,600. Calculate the Traditional Payback. Assume cash flows are even throughout the year. Calculate the Net Present Value using the WACC = 8.28%.
There is a project with the following cash flows: CF0 = -850; CF1 = 300; CF2...
There is a project with the following cash flows: CF0 = -850; CF1 = 300; CF2 =320; CF3 = 340; CF4 = 360. If the appropriate discount rate is 10%, what is the project's MIRR? (Assume the same reinvestment rate) 14.08% 15.65% 17.21% 18.29% 19.15%
A potential CB project has the following cash flows: CF0 = -$500, CF1 = $300, CF2...
A potential CB project has the following cash flows: CF0 = -$500, CF1 = $300, CF2 = $200, CF3 = $150. WACC = 6%. Compute the following: A. Payback Period B. NPV C. IRR
You have the chance to participate in a project that produces the following cash flows. CF0=?...
You have the chance to participate in a project that produces the following cash flows. CF0=? CF1=$0 CF2=$11,000 The NPV of the project is $4,090.91. If the opportunity cost of capital is 10%, a) you would accept the project, if the IRR is greater than the required return. b) you would not accept the project, as the largest cash inflow occurs at the end of the project. c) you would not be able to decide whether to accept the project,...
Calculate the IRR(s) for a 10-year project with the following cash flows: CF0 = -30, CF1...
Calculate the IRR(s) for a 10-year project with the following cash flows: CF0 = -30, CF1 = 10 = CF2 = CF3 = CF4 = CF5 = CF6 = CF7 = CF8 = CF9, and CF10 = -65. In Excel, plot the NPV against r (= discount rate), using r = 0%, 2%, 4%, 6%, 8%, 10%, 12%, 14%, 16%, 18%, 20%, 22%, 24%, 26%, 28%, and so on until you find all IRRs on the horizontal axis. Approximately, what...
Project Bhas the following cash flows: CF0 = -100, C01 = -390, C02 = 660, C03...
Project Bhas the following cash flows: CF0 = -100, C01 = -390, C02 = 660, C03 = 330, C04 = -290. What is the PV of only the costs to Project B if the cost of capital is 0.07?
Seaborn Co. has identified an investment project with the following cash flows.
Seaborn Co. has identified an investment project with the following cash flows. Year Cash Flow 1 $800            2 1,000            3 1,330            4 1,160            Required: (a) If the discount rate is 10 percent, what is the present value of these cash flows? (Click to select)  3,679.79  3,268.96  3,424.40  4,290.00  3,345.26 (b) What is the present value at 18 percent? (Click to select)  2,746.13  3,308.65  4,290.00  3,635.58  2,803.94 (c) What is the present value at 28 percent? (Click to select)  2,345.12  2,259.53  ...
Suppose that you had paid $ 300,000 for an investment that pays the following cash flows....
Suppose that you had paid $ 300,000 for an investment that pays the following cash flows. What will be your internal rate of return? a. $45,000 b. $38,000 c. $52,000 d. $320,000
What is the payback period for the investment project that has the following cash flows? Year...
What is the payback period for the investment project that has the following cash flows? Year Cash Flows 0 -65,209 1 24,853 2 27,977 3 23,774 4 25,436
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT