Question

In: Accounting

1. In a job-order cost system, what would back up the balance in the Work in...

1. In a job-order cost system, what would back up the balance in the Work in Process account?

2. What are the differences between actual costing system and normal costing system?

Solutions

Expert Solution

Answer for 1)

In job order costing the balance in the work in process account will be transferred to Finished goods accounts for which the the costs of direct materials,direct labour and other overheads of remaining portion will be added.

Answer for 2)

1)The primary difference of actual and normal costing system is in actual costing system the actual costs of direct materials, direct labour and manufacturing Overheads is recorded as cost but when it comes to normal costing system the predetermined rates are used for mostly manufacturing overhead as it easy to determine the actual costs of material and labor which is not in the case of manufacturing overhead.

2)The second major difference is that in normal costing system the variation of overhead costs is almost negligable as it uses predetermined rate but when it comes to actual costing system the rate may vary due to price hikes and drops in the overheads used.


Related Solutions

What is a job order cost system? Describe a situation in which you would use job...
What is a job order cost system? Describe a situation in which you would use job order cost information. What type of information is useful in making your decision?
Job-Order Cost Sheets, Balance in Work in Process and Finished Goods Prull Company, a job-order costing...
Job-Order Cost Sheets, Balance in Work in Process and Finished Goods Prull Company, a job-order costing firm, worked on three jobs in July. Data are as follows: Job 86 Job 87 Job 88 Balance, July 1 $21,370 $6,280 $0 Direct materials $10,510 $12,350 $16,190 Direct labor $16,040 $12,240 $24,030 Machine hours 500 290 980 Overhead is applied to jobs at the rate of $17 per machine hour. By July 31, Jobs 86 and 88 were completed. Jobs 82 and 86...
Stine Company uses a job order cost system. On May 1, the company has a balance...
Stine Company uses a job order cost system. On May 1, the company has a balance in Work in Process Inventory of $ 3,910 and two jobs in process: Job No. 429 $ 2,460, and Job No. 430 $ 1,450. During May, a summary of source documents reveals the following. Job Number Materials Requisition Slips Labor Time Tickets 429 $ 2,900 $ 2,060 430 3,940 3,130 431 4,670 $ 11,510 7,760 $ 12,950 General use 950 1,370 $ 12,460 $...
Ivanhoe Company uses a job order cost system. On May 1, the company has a balance...
Ivanhoe Company uses a job order cost system. On May 1, the company has a balance in Work in Process Inventory of $3,940 and two jobs in process: Job No. 429 $2,160, and Job No. 430 $1,780. During May, a summary of source documents reveals the following. Job Number Materials Requisition Slips Labor Time Tickets 429 $2,770 $2,100 430 3,910 3,300 431 4,920 $11,600 8,200 $13,600 General use 940 1,460 $12,540 $15,060 Ivanhoe Company applies manufacturing overhead to jobs at...
Cullumber Company uses a job order cost system. On May 1, the company has a balance...
Cullumber Company uses a job order cost system. On May 1, the company has a balance in Work in Process Inventory of $3,770 and two jobs in process: Job No. 429 $2,430, and Job No. 430 $1,340. During May, a summary of source documents reveals the following. Job Number Materials Requisition Slips Labor Time Tickets 429 $2,940 $2,300 430 3,850 3,400 431 4,680 $11,470 8,200 $13,900 General use 940 1,570 $12,410 $15,470 Cullumber Company applies manufacturing overhead to jobs at...
Stine Company uses a job order cost system. On May 1, the company has a balance...
Stine Company uses a job order cost system. On May 1, the company has a balance in Work in Process Inventory of $3,900 and two jobs in process: Job No. 429 $2,450, and Job No. 430 $1,450. During May, a summary of source documents reveals the following. Job Number Materials Requisition Slips Labor Time Tickets 429 $3,000 $2,200 430 3,730 3,400 431 4,710 $11,440 8,200 $13,800 General use 980 1,330 $12,420 $15,130 Stine Company applies manufacturing overhead to jobs at...
Stine Company uses a job order cost system. On May 1, the company has a balance...
Stine Company uses a job order cost system. On May 1, the company has a balance in Work in Process Inventory of $3,500 and two jobs in process: Job No. 429 $2,000, and Job No. 430 $1,500. During May, a summary of source documents reveals the following. Job Number Materials Requisition Slips Labor Time Tickets 429 2,500 1,900 430 3,500 3,000 431 4,400 10,400 7,600 12,500 General use 800 1,200 11,200 13,700 Stine Company applies manufacturing overhead to jobs at...
Stine Company uses a job order cost system. On May 1, the company has a balance...
Stine Company uses a job order cost system. On May 1, the company has a balance in Work in Process Inventory of $ 4,130 and two jobs in process: Job No. 429 $ 2,370, and Job No. 430 $ 1,760. During May, a summary of source documents reveals the following. Job Number Materials Requisition Slips Labor Time Tickets 429 $ 3,090 $ 2,080 430 3,960 3,310 431 4,820 $ 11,870 8,180 $ 13,570 General use 960 1,320 $ 12,830 $...
Darden Manufacturing uses a job order cost accounting system. On April 1, the company has Work...
Darden Manufacturing uses a job order cost accounting system. On April 1, the company has Work in Process Inventory of $7,600 and two jobs in process: Job No. 221, $3,600, and Job No. 222, $4,000. During April, a summary of source documents reveals the following: For Materials Requisition Slips Labor Time Tickets Job. No. 221 $2,200 $3,600 222 1,700 3,200 223 2,400 2,900 224 2,100 2,800 General use 600 400 Totals $9,000 $12,900 Darden applies manufacturing overhead to jobs at...
Entries for Costs in a Job Order Cost System Velasco Co. uses a job order cost...
Entries for Costs in a Job Order Cost System Velasco Co. uses a job order cost system. The following data summarize the operations related to production for July: Materials purchased on account, $695,900 Materials requisitioned, $584,560, of which $75,990 was for general factory use Factory labor used, $716,780, of which $136,190 was indirect Other costs incurred on account for factory overhead, $167,020; selling expenses, $257,480; and administrative expenses, $153,100 Prepaid expenses expired for factory overhead, $32,010; for selling expenses, $27,140;...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT