In: Accounting
The following data are average times per order over the last month for Groot Corp.
days |
|
Move time |
1 |
Inspection time |
41 |
Queue time |
3 |
Wait time to start production |
2 |
Process time |
5 |
(Q): What is Manufacturing Cycle Efficiency (MCE)? Use two decimal places in the answer (for example, if the answer is 25%, key in "0.25").
The answer is | ||||
MCE = 0.10 | ||||
Manufacturing Cycle Efficiency = | Value-Added Time | = | Process Time | |
Throughput Time | Total Cycle Time | |||
Total Cycle Time = | Process Time + Inspection Time + Queue Time + Move Time | |||
Process Time | 5 | |||
Inspection Time | 41 | |||
Queue Time | 3 | |||
Move Time | 1 | |||
Total Cycle Time | 50 | |||
Manufacturing Cycle Efficiency = | 5 | = | 0.10 | |
50 |
Note : Wait Time is not to be included in Total cycle time.