In: Accounting
The following data are average times per order over the last month for Groot Corp.
|
days |
|
|
Move time |
1 |
|
Inspection time |
41 |
|
Queue time |
3 |
|
Wait time to start production |
2 |
|
Process time |
5 |
(Q): What is Manufacturing Cycle Efficiency (MCE)? Use two decimal places in the answer (for example, if the answer is 25%, key in "0.25").
| The answer is | ||||
| MCE = 0.10 | ||||
| Manufacturing Cycle Efficiency = | Value-Added Time | = | Process Time | |
| Throughput Time | Total Cycle Time | |||
| Total Cycle Time = | Process Time + Inspection Time + Queue Time + Move Time | |||
| Process Time | 5 | |||
| Inspection Time | 41 | |||
| Queue Time | 3 | |||
| Move Time | 1 | |||
| Total Cycle Time | 50 | |||
| Manufacturing Cycle Efficiency = | 5 | = | 0.10 | |
| 50 |
Note : Wait Time is not to be included in Total cycle time.