Question

In: Accounting

Net Present Value Method, Present Value Index, and Analysis Donahue Industries Inc. wishes to evaluate three...

Net Present Value Method, Present Value Index, and Analysis

Donahue Industries Inc. wishes to evaluate three capital investment projects by using the net present value method. Relevant data related to the projects are summarized as follows:

Product Line
Expansion
Distribution
Facilities
Computer
Network
Amount to be invested $568,347 $365,363 $216,394
Annual net cash flows:
Year 1 280,000 190,000 123,000
Year 2 260,000 171,000 85,000
Year 3 238,000 152,000 62,000
Present Value of $1 at Compound Interest
Year 6% 10% 12% 15% 20%
1 0.943 0.909 0.893 0.870 0.833
2 0.890 0.826 0.797 0.756 0.694
3 0.840 0.751 0.712 0.658 0.579
4 0.792 0.683 0.636 0.572 0.482
5 0.747 0.621 0.567 0.497 0.402
6 0.705 0.564 0.507 0.432 0.335
7 0.665 0.513 0.452 0.376 0.279
8 0.627 0.467 0.404 0.327 0.233
9 0.592 0.424 0.361 0.284 0.194
10 0.558 0.386 0.322 0.247 0.162

Required:

1. Assuming that the desired rate of return is 15%, prepare a net present value analysis for each project. Use the present value of $1 table presented above in your computations. If the net present value is negative, enter a negative amount.

Product Line Expansion Distribution Facilities Computer Network
Present value of net cash flow total $ $ $
Amount to be invested
Net present value $ $ $

2. Determine a present value index for each proposal. Round your answers to two decimal places.

Present Value Index (Rounded)
Product Line Expansion
Distribution Facilities
Computer Network

Solutions

Expert Solution

Product Line Expansion Distribution Facilities Computer Network
Year Table Value Cash Flows PVCF Cash Flows PVCF Cash Flows PVCF
1 0.870 280000 243600 190000 165300 123000 107010
2 0.756 260000 196560 171000 129276 85000 64260
3 0.658 238000 156604 152000 100016 62000 40796
596764 394592 212066

NPV

Product Line Expansion Distribution Facilities Computer Network
PV of Net Cashflows 596764 394592 212066
Amount to be invested 568347 365363 216394
NPV 28417 29229 -4328
Profitability Index
PV of Net Cashflows Amount to be invested
Product Line Expansion 596764 568347                                1.05
Distribution Facilities 394592 365363                                1.08
Computer Network 212066 216394                                0.98

Related Solutions

Net Present Value Method, Present Value Index, and Analysis Donahue Industries Inc. wishes to evaluate three...
Net Present Value Method, Present Value Index, and Analysis Donahue Industries Inc. wishes to evaluate three capital investment projects by using the net present value method. Relevant data related to the projects are summarized as follows: Product Line Expansion Distribution Facilities Computer Network Amount to be invested $735,596 $447,586 $274,176 Annual net cash flows: Year 1 362,000 250,000 156,000 Year 2 337,000 225,000 108,000 Year 3 308,000 200,000 78,000 Present Value of $1 at Compound Interest Year 6% 10% 12%...
Net Present Value Method, Present Value Index, and Analysis Donahue Industries Inc. wishes to evaluate three...
Net Present Value Method, Present Value Index, and Analysis Donahue Industries Inc. wishes to evaluate three capital investment projects by using the net present value method. Relevant data related to the projects are summarized as follows: Product Line Expansion Distribution Facilities Computer Network Amount to be invested $783,240 $531,394 $308,533 Annual net cash flows: Year 1 382,000 279,000 172,000 Year 2 355,000 251,000 119,000 Year 3 325,000 223,000 86,000 Present Value of $1 at Compound Interest Year 6% 10% 12%...
Net Present Value Method, Present Value Index, and Analysis Donahue Industries Inc. wishes to evaluate three...
Net Present Value Method, Present Value Index, and Analysis Donahue Industries Inc. wishes to evaluate three capital investment projects by using the net present value method. Relevant data related to the projects are summarized as follows: Product Line Expansion Distribution Facilities Computer Network Amount to be invested $733,787 $514,437 $260,321 Annual net cash flows: Year 1 365,000 270,000 150,000 Year 2 339,000 243,000 103,000 Year 3 310,000 216,000 75,000 Present Value of $1 at Compound Interest Year 6% 10% 12%...
Net Present Value Method, Present Value Index, and Analysis United Bankshores, Inc. wishes to evaluate three...
Net Present Value Method, Present Value Index, and Analysis United Bankshores, Inc. wishes to evaluate three capital investment proposals by using the net present value method. Relevant data related to the proposals are summarized as follows: Branch Office Expansion Computer System Upgrade Install Internet Bill-Pay Amount to be invested $713,368 $471,275 $236,700 Annual net cash flows: Year 1 344,000 248,000 155,000 Year 2 320,000 223,000 107,000 Year 3 292,000 198,000 78,000 Present Value of $1 at Compound Interest Year 6%...
Net Present Value Method, Present Value Index, and Analysis United Bankshores, Inc. wishes to evaluate three...
Net Present Value Method, Present Value Index, and Analysis United Bankshores, Inc. wishes to evaluate three capital investment proposals by using the net present value method. Relevant data related to the proposals are summarized as follows: Branch Office Expansion Computer System Upgrade Install Internet Bill-Pay Amount to be invested $575,292 $377,600 $191,050 Annual net cash flows: Year 1 286,000 200,000 123,000 Year 2 266,000 180,000 85,000 Year 3 243,000 160,000 62,000 Present Value of $1 at Compound Interest Year 6%...
Net Present Value Method, Present Value Index, and Analysis United Bankshores, Inc. wishes to evaluate three...
Net Present Value Method, Present Value Index, and Analysis United Bankshores, Inc. wishes to evaluate three capital investment proposals by using the net present value method. Relevant data related to the proposals are summarized as follows: Branch Office Expansion Computer System Upgrade Install Internet Bill-Pay Amount to be invested $837,326 $465,641 $258,271 Annual net cash flows: Year 1 320,000 218,000 141,000 Year 2 298,000 196,000 97,000 Year 3 272,000 174,000 71,000 Present Value of $1 at Compound Interest Year 6%...
Donahue Industries Inc. wishes to evaluate three capital investment projects by using the net present value...
Donahue Industries Inc. wishes to evaluate three capital investment projects by using the net present value method. Relevant data related to the projects are summarized as follows: Product Line Expansion Distribution Facilities Computer Network Amount to be invested $790,052 $535,506 $310,018 Annual net cash flows: Year 1 413,000 301,000 186,000 Year 2 384,000 271,000 128,000 Year 3 351,000 241,000 93,000 Present Value of $1 at Compound Interest Year 6% 10% 12% 15% 20% 1 0.943 0.909 0.893 0.870 0.833 2...
Net Present Value Method, Present Value Index, and Analysis First United Bank Inc. is evaluating three...
Net Present Value Method, Present Value Index, and Analysis First United Bank Inc. is evaluating three capital investment projects using the net present value method. Relevant data related to the projects are summarized as follows: Branch Office Expansion Computer System Upgrade ATM Kiosk Expansion Amount to be invested $601,461 $411,359 $216,033 Annual net cash flows: Year 1 317,000 219,000 133,000 Year 2 295,000 197,000 92,000 Year 3 269,000 175,000 67,000 Present Value of $1 at Compound Interest Year 6% 10%...
Net Present Value Method and Present Value Index Diamond and Turf Inc. is considering an investment...
Net Present Value Method and Present Value Index Diamond and Turf Inc. is considering an investment in one of two machines. The sewing machine will increase productivity from sewing 150 baseballs per hour to sewing 270 per hour. The contribution margin per unit is $0.42 per baseball. Assume that any increased production of baseballs can be sold. The second machine is an automatic packing machine for the golf ball line. The packing machine will reduce packing labor cost. The labor...
Net Present Value Method and Present Value Index Diamond and Turf Inc. is considering an investment...
Net Present Value Method and Present Value Index Diamond and Turf Inc. is considering an investment in one of two machines. The sewing machine will increase productivity from sewing 180 baseballs per hour to sewing 324 per hour. The contribution margin per unit is $0.46 per baseball. Assume that any increased production of baseballs can be sold. The second machine is an automatic packing machine for the golf ball line. The packing machine will reduce packing labor cost. The labor...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT