In: Accounting
Answer:
Correct answer is: A) $96,000, $64,000 and $32,000
Explanation:
Cost to be capitalized = Lump sum price paid + Appraisal cost
= $180,000 + $12,000
= $192,000
Total appraised values = Land value + Building Value + Equipment value
= $120,000 + $80,000 + $40,000
=$240,000
Cost assigned to an asset = (Appraised value of the asset / Total appraised value of all assets) * Total cost to be assigned
Hence,
Cost assigned to Land = ($120,000 / $240,000) * $192,000 = $96,000
Cost assigned to Building = ($80,000 / $240,000) * $192,000 = $64,000
Cost assigned to Equipment = ($40,000 / $240,000) * $192,000 = $32,000
Hence option A) $96,000, $64,000 and $32,000 is correct.
In Option B, the assigned values are same as appraised values and are incorrect.
In Option C, the values assigned do not factor in appraisal cost and are incorrect.
In Option D, values are assigned equally, which cannot be the basis of assignment and are incorrect.