Question

In: Operations Management

Read the case study below and answer the accompanying questions. TELESTAR INTERNATIONAL On November 15, 1978,...

Read the case study below and answer the accompanying questions.

TELESTAR INTERNATIONAL

On November 15, 1978, the Department of Energy Resources awarded Telestar a $475,000 contract for the developing and testing of two waste treatment plants. Telestar had spent the better part of the last two years developing waste treatment technology under its own R&D activities. This new contract would give Telestar the opportunity to “break into a new field”—that of waste treatment. The contract was negotiated at a firm-fixed price. Any cost overruns would have to be incurred by Telestar. The original bid was priced out at $847,000. Telestar’s management, however, wanted to win this one. The decision was made that Telestar would “buy in” at $475,000 so that they could at least get their foot into the new marketplace. The original estimate of $847,000 was very “rough” because Telestar did not have any good man-hour standards, in the area of waste treatment, on which to base their man-hour projections. Corporate management was willing to spend up to $400,000 of their own funds in order to compensate the bid of $475,000. By February 15, 1979, costs were increasing to such a point where overrun would be occurring well ahead of schedule. Anticipated costs to completion were now $943,000. The project manager decided to stop all activities in certain functional departments, one of which was structural analysis. The manager of the structural analysis department strongly opposed the closing out of the work order prior to the testing of the first plant’s high-pressure pneumatic and electrical systems. Questions (Conversations) Structures manager: “You’re running a risk if you close out this work order. How will you know if the hardware can withstand the stresses that will be imposed during the test? After all, the test is scheduled for next month and I can probably finish the analysis by then.” Project manager: “I understand your concern, but I cannot risk a cost overrun. My boss expects me to do the work within cost. The plant design is similar to one that we have tested before, without any structural problems being detected. On this basis I consider your analysis unnecessary.” Structures manager: “Just because two plants are similar does not mean that they will be identical in performance. There can be major structural deficiencies.” Project manager: “I guess the risk is mine.” Structures manager: “Yes, but I get concerned when a failure can reflect on the integrity of my department. You know, we’re performing on schedule and within the time and money budgeted. You’re setting a bad example by cutting off our budget without any real justification.” Project manager: “I understand your concern, but we must pull out all the stops when overrun costs are inevitable.” Structures manager: “There’s no question in my mind that this analysis should be completed. However, I’m not going to complete it on my overhead budget. I’ll reassign my people tomorrow. Incidentally, you had better be careful; my people are not very happy to work for a project that can be canceled immediately. I may have trouble getting volunteers next time.” Project manager: “Well, I’m sure you’ll be able to adequately handle any future work. I’ll report to my boss that I have issued a work stoppage order to your department.” During the next month’s test, the plant exploded. Postanalysis indicated that the failure was due to a structural deficiency QUESTIONS 1. Who is at fault? 2. Should the structures manager have been dedicated enough to continue the work on his own? 3. Can a functional manager, who considers his organization as strictly support, still be dedicated to total project success

Solutions

Expert Solution

(1)

The responsibility lies with the project manager as he did not promote structural analysis, taking it out of the operations of the programs. However, it is essential to note that the initial project calculation was carried out irrationally, estimating the cost in order to win the contract. That also leaves the owner of the project and the top management responsible for the mistake. Therefore, a change management process is non-existent enabling the project manager to arbitrarily abandon a critical part of the project without the sponsor's verification and approval. Therefore the top management should be held accountable for the poor system.

(2)

The frameworks manager has the potential, in my own opinion, to remain in his role. His skill is obvious because he could foresee the calamity ahead which he told the boss. There is proof of his commitment, as he expressed his doubts and cautioned the project manager against carrying out his plan. In fact, the manager of systems has doubts about the trust of his group and company as a whole. It would have been the mechanism that helped him to escalate his problems and log them. Therefore, there was a flaw in the management generated method, removing the responsibility from the systems boss.

(3)

The functional manager assumes responsibility for the whole project along with the project manager. The project had no long chain of command through which the project manager took each decision arbitrarily. The project team will include several functional managers who have to decide jointly in such a large-scale project. Different methods , for example the RASI maps, may assess accountability. Management should incorporate these structures to ensure the comprehension of obligations between team participants and to decentralize decisions. This interventions mitigate project costs and increase productivity.

PLEASE LIKE THIS ANSWER, IF ITS USEFUL TO YOU! THANK YOU!


Related Solutions

Read the case study below and answer the accompanying questions. TELESTAR INTERNATIONAL On November 15, 1978,...
Read the case study below and answer the accompanying questions. TELESTAR INTERNATIONAL On November 15, 1978, the Department of Energy Resources awarded Telestar a $475,000 contract for the developing and testing of two waste treatment plants. Telestar had spent the better part of the last two years developing waste treatment technology under its own R&D activities. This new contract would give Telestar the opportunity to “break into a new field”—that of waste treatment. The contract was negotiated at a firm-fixed...
COST ACCOUNTING ASSIGNMENT – CASE STUDY Read the case study below and answer the questions that...
COST ACCOUNTING ASSIGNMENT – CASE STUDY Read the case study below and answer the questions that follow. Ma Baker produce a mini-kitchen called Small Cook, which is enjoying extensive popularity amongst young children. The following data is available for the month: Selling price (per unit) R116 Units in opening inventory 600 Units manufactured 2 550 Units sold 3 050 Units in closing inventory 100 Variable costs per unit: Direct materials R12,00 Direct labour R50,00 Variable manufacturing overhead R6,50 Variable selling...
Case Study- Read the case study scenario, answer the questions below, and explain the rationale for...
Case Study- Read the case study scenario, answer the questions below, and explain the rationale for your answer. Glenna, age 38, lost leg function during a motor vehicle accident at age 16. She plays basketball at the community center and teaches aerobic classes for wheelchair-bound people three times a week. She manages a medical equipment rental business since her husband died. Business is not profitable. A physician’s referral was made to the public health department for a developmental assessment. A...
Case Study- Read the case study scenario, answer the questions below, and explain the rationale for...
Case Study- Read the case study scenario, answer the questions below, and explain the rationale for your answer. Glenna, age 38, lost leg function during a motor vehicle accident at age 16. She plays basketball at the community center and teaches aerobic classes for wheelchair-bound people three times a week. She manages a medical equipment rental business since her husband died. Business is not profitable. A physician’s referral was made to the public health department for a developmental assessment. A...
Read the following case study and answer the questions.                                  &
Read the following case study and answer the questions.                                     1*6=6 RBC’s Youth Marketing Strategy As stated above, the marketing strategy consists of selecting a target market and designing the marketing mix of your product, price, place, and promotion to appeal to your competitors. RBC, Canada’s largest bank, obviously has many different target markets, which results in the key managing different marketing mixes. One key target market for the bank is university students and recent graduates. The group is particularly...
Read the case study below and answer the questions that follow: A leading construction company is...
Read the case study below and answer the questions that follow: A leading construction company is building an apartment building with five floors. Each story has four flats. Due to limited manpower availability, they want to outsource the maintenance management. Assume that you are a facility manager for that company. a. Explain how you would plan the daily maintenance activities of this building after its completion. The plan should include detailed information of the time, resource and budget requirements. The...
Case study (questions 20–21) Read this case study then answer the questions that follow. Miyuki is...
Case study (questions 20–21) Read this case study then answer the questions that follow. Miyuki is a carer for Mr Ling, a 76-year-old man who has dementia and lives at home on his own. Miyuki often finds that the most challenging part of caring for Mr Ling is balancing his rights and safety. Last week Miyuki found Mr Ling on the ground outside, where he had fallen while trying to garden. Miyuki knows that it is important for Mr Ling...
Case study (questions 6–13) Read this case study then answer the questions that follow. Lila is...
Case study (questions 6–13) Read this case study then answer the questions that follow. Lila is a support worker at a care facility. Lila provides care to people who experience memory loss. Every day at work Lila faces new challenges as she tries her best to use the most appropriate communication strategies to meet each person’s individual needs. Some of the people Lila works with have severe dementia and can become distressed when spoken to. Others she cares for are...
Case study (questions 14–19) Read this case study then answer the questions that follow. Richard is...
Case study (questions 14–19) Read this case study then answer the questions that follow. Richard is part of a team who support people with dementia. One of the most challenging aspects of Richard’s job is managing the problematic and disruptive behaviours of the people he is caring for. Richard realises that in most cases these behaviours are a way of expressing unmet needs and concerns. Unfortunately, it can be tricky to identify these needs, especially for those like Karin who...
Read the case study, then answer the questions that follow. Case study (questions 1–8) Peter is...
Read the case study, then answer the questions that follow. Case study (questions 1–8) Peter is 74 and has Parkinson’s disease. He resides in his own home in the community. When the support worker arrives, she finds that Peter has left all his washing in the basket in the laundry. When the worker asks Peter why he hasn’t hung out the washing, he tells her that he can’t lift the sheets and towels onto the clothesline because they are too...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT