Question

In: Finance

Company X has an investment project requiring a $10m investment today and that has a $1m...

  1. Company X has an investment project requiring a $10m investment today and that has a $1m net present value. The company has 1 million shares, no internal funds and, given the nature of its business, cannot get debt financing. Hence it must raise funds by issuing equity or abandon the project. While the market knows all about the investment project, it does not know whether the value of the company’s existing assets (i.e., excluding the new project) is $10m or $2m and regards both values as equally likely. Management knows the assets’ value and investors are aware of that. Therefore, management must consider investors’ (and hence the stock price’s) reaction to the announcement of an equity issue. A priori, three scenarios are possible:

    • Scenario 1: Investors would infer nothing about the assets’ value.

    • Scenario 2: Investors would infer the assets’ value is $2m.

    • Scenario 3: Investors would infer the assets’ value is $10m.

    1. For each scenario, at what price would the company be able to issue shares?

    2. For each scenario, if managers knew the value was $2m, would they go ahead

      with the equity issuance or abandon the project?

    3. For each scenario, given managers know the value is $10m, would they proceed

      with the equity issuance or abandon the project?

Solutions

Expert Solution

For Scenario 1 :

Investors do not infer anything and hence the estimate of the value of company's assets = ($2m+$10m) /2 = $6 m

So, with $10m project of $1 m NPV, the value of the company = $6m + $1m = $7 million

So, Price at which shares can be issued = $7 million/ 1 million shares = $7 per share

For Scenario 2 :

Investors infer that the value of company's assets is $2 million

So, with $10m project of $1 m NPV, the value of the company = $2m + $1m = $3 million

So, Price at which shares can be issued = $3 million/ 1 million shares = $3 per share

For Scenario 3 :

Investors infer that the value of company's assets is $10 million

So, with $10m project of $1 m NPV, the value of the company = $10m + $1m = $11 million

So, Price at which shares can be issued = $11 million/ 1 million shares = $11 per share

If the managers knew the value was $2m, and that correct issue price is $3 per share

For Scenario 1 : They would prefer to issue shares as the shares can be issued at a higher price than $3 per share

For Scenario 2 : They would prefer to issue shares as the shares can be issued at same price of $3 per share

For Scenario 3 : They would prefer to issue shares as the shares can be issued at a higher price than $3 per share

If the managers knew the value was $10m, and that correct issue price is $11 per share

For Scenario 1 : They would prefer not to issue shares as the shares can be issued at a lower price than $11 per share . And they would decide to abandon the project

For Scenario 2 : They would prefer not to issue shares as the shares can be issued at a lower price than $11 per share.And they would decide to abandon the project

For Scenario 3 : They would prefer to issue shares as the shares can be issued at the same price of $11 per share


Related Solutions

Company X has an investment project requiring a $10m investment today and that has a $1m...
Company X has an investment project requiring a $10m investment today and that has a $1m net present value. The company has 1 million shares, no internal funds and, given the nature of its business, cannot get debt financing. Hence it must raise funds by issuing equity or abandon the project. While the market knows all about the investment project, it does not know whether the value of the company’s existing assets (i.e., excluding the new project) is $10m or...
Consider an investment opportunity with an option to grow that requires a $10m investment today. In...
Consider an investment opportunity with an option to grow that requires a $10m investment today. In one year we will find out whether the project is successful or not. The probability that the project will generate $1M per year in perpetuity (starting from one year after the investment is made; that is, starting from year 1) is 50%. Otherwise, the project will generate nothing. You can double the size of the project in year 1 if the original project is...
In year 0 of project A, your company is required to make $1M investment but in...
In year 0 of project A, your company is required to make $1M investment but in year 1, 2, 3, 4, 5, and 6 the investment level is only $250K per year. Benefits are forecasted to start in year 3 and continue for the next 20 years varying by each year. Breakeven period is somewhere between year 6 and 7. There is another project alternative (call it project B) that is known but not pursued because the payback period is...
Company is evaluating a 10-year project requiring an initial investment of $50 million. The firm has...
Company is evaluating a 10-year project requiring an initial investment of $50 million. The firm has made the following projections: EBIT = $10 million Interest Expense = $2 million Tax Rate = 40% Depreciation = $5 million/year Debt/Equity Ratio = 20% Cost of Equity = 15% Total Cost of Capital = 12% The firm does not intend to change its debt to equity ratio when making additional investments. Using FCFF, what is the expected net present value (NPV) of this...
Model x is considering a new project requiring an upfront fixed-asset investment of $1,000,000 with an...
Model x is considering a new project requiring an upfront fixed-asset investment of $1,000,000 with an economic life of five years. Depreciation is taken on a straight-line basis, with no expected salvage value. Net working capital required immediately is expected to be $100,000 and will be recovered in full upon the project's completion in five years. In the optimistic-scenario forecast, the annual sales volume is 47,000 units, while the sale price is $122 per unit with a variable cost of...
A company is considering a new project requiring an upfront fixed-asset investment of $1,000,000 with an...
A company is considering a new project requiring an upfront fixed-asset investment of $1,000,000 with an economic life of five years. Depreciation is taken on a straight-line basis, with no expected salvage value. Net working capital required immediately is expected to be $100,000 and will be recovered in full upon the project's completion in five years. In the expected-scenario forecast, the annual sales volume is 49,200 units, while the sale price is $133 per unit with a variable cost of...
A company is considering a new project requiring an upfront fixed-asset investment of $1,000,000 with an...
A company is considering a new project requiring an upfront fixed-asset investment of $1,000,000 with an economic life of five years. Depreciation is taken on a straight-line basis, with no expected salvage value. Net working capital required immediately is expected to be $100,000 and will be recovered in full upon the project's completion in five years. In the expected-scenario forecast, the annual sales volume is 44,700 units, while the sale price is $121 per unit with a variable cost of...
A company is considering a new project requiring an upfront fixed-asset investment of $1,000,000 with an...
A company is considering a new project requiring an upfront fixed-asset investment of $1,000,000 with an economic life of five years. Depreciation is taken on a straight-line basis, with no expected salvage value. Net working capital required immediately is expected to be $100,000 and will be recovered in full upon the project's completion in five years. In the expected-scenario forecast, the annual sales volume is 35,700 units, while the sale price is $97 per unit with a variable cost of...
A company is considering a new project requiring an upfront fixed-asset investment of $1,000,000 with an...
A company is considering a new project requiring an upfront fixed-asset investment of $1,000,000 with an economic life of five years. Depreciation is taken on a straight-line basis, with no expected salvage value. Net working capital required immediately is expected to be $100,000 and will be recovered in full upon the project's completion in five years. In the optimistic-scenario forecast, the annual sales volume is 53,400 units, while the sale price is $138 per unit with a variable cost of...
A company is considering a new project requiring an upfront fixed-asset investment of $1,000,000 with an...
A company is considering a new project requiring an upfront fixed-asset investment of $1,000,000 with an economic life of five years. Depreciation is taken on a straight-line basis, with no expected salvage value. Net working capital required immediately is expected to be $100,000 and will be recovered in full upon the project's completion in five years. In the expected-scenario forecast, the annual sales volume is 53,700 units, while the sale price is $145 per unit with a variable cost of...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT