1.Following are costs incurred in the past year involved with the opening of a new branch in a company. Use the following information to calculate the total amount that was debited to the land account.
| 
 Description  | 
 Amount  | 
| 
 Fee for Title  | 
 300  | 
| 
 Architect Fee  | 
 3,100  | 
| 
 Cash paid for land and old building  | 
 80,000  | 
| 
 Remova lof building  | 
 7,000  | 
| 
 Salavage Value of Building Removed  | 
 1,000  | 
| 
 Purchased machinery  | 
 10,000  | 
| 
 New building constructed  | 
 500,000  | 
| 
 Assessment by city for building permit  | 
 600  | 
| 
 Installation on machinery  | 
 1,500  | 
| 
 Tree's and landscaping  | 
 5,000  | 
Cost of Land :
a)Cash paid for land and old building $80000
b)Fee for Title $300
c)Tree's and landscaping $5000
d)Remova lof building $7,000
e)Salavage Value of Building Removed ($1,000)
Cost Of land to be Debited(a+b+c+d-e) = $91300
Explanation :
Note : Architect Fee, Assessment by city for building permit are the cost related to building hence they will form part of the building not land