Question

In: Civil Engineering

A contractor has submitted a tender while specifying that it is available for acceptance for a...

A contractor has submitted a tender while specifying that it is available for acceptance for a

period of five weeks after the tender submission. However, the contractor withdrew its bid

after two weeks due to an unexpected rise in its workload. Can the owner recover the costs

for employing a different contractor? Explain.

Solutions

Expert Solution

The owner can recover the costs from the contractor who as accepted initially for employing a different contractor, only when the contract conditions are made firm at initial stage itself. In all general conditions contract one should give the provision of EMD or bid bond, in order to avoid or tackle the situation stated above.Earnest money is demanded from each tenderer to ensure the owner that a tenderer/bidder does not withdraw his tender / offer before its acceptance, or refuse or deny to execute the work after it has been awarded to him. This is to safeguard the process of bidding and time and resources spent during process by all. If this is not done, any bidder will withdraw at any stage and the bidding process would become a laughing stock or a joke and hence redundant. If no such financial guarantee is demanded, the bidder would not take the bidding process seriously in terms of time, process, offer and conditions. Not only that after bidding process is over and contract is finalized, the bidder has to start work i.e. performance of the contract. EMD is also a guarantee against that. In short EMD is one type of guarantee that once the bidder enters the bidding process and the owner awards the work or contract to any of the bidder, the bidder can neither withdraw nor change any terms of contract of the bid and has to perform once the deal is done.So, EMD can be forfieted to recover the costs for employing a different contractor.


Related Solutions

e) If the claims submitted by the Contractor cannot be agreed by the Architect, advice the...
e) If the claims submitted by the Contractor cannot be agreed by the Architect, advice the Contractor what can he do and what are the dispute resolution mechanisms available within PAM 2006 for him to resolve the claim issues ?
Type a 500-600 word response to this topic to be submitted for assessment: While an immune...
Type a 500-600 word response to this topic to be submitted for assessment: While an immune response to a pathogen such as a Covid 19 will involve many features of immunity we have learn about, a critical aspect will be the T cell response. T cells, once activated can differentiate into one of the various effector T cell subsets that are known and in particular to this conversation, the CD4 T subsets, Th1, Th2 and TH17 cells and the CD8...
Type a 500-600 word response to this topic to be submitted for assessment: While an immune...
Type a 500-600 word response to this topic to be submitted for assessment: While an immune response to a pathogen such as a Covid 19 will involve many features of immunity we have learn about, a critical aspect will be the T cell response. T cells, once activated can differentiate into one of the various effector T cell subsets that are known and in particular to this conversation, the CD4 T subsets, Th1, Th2 and TH17 cells and the CD8...
[3] The Home country has 2,200 units of labor available while the Foreign country has 1600...
[3] The Home country has 2,200 units of labor available while the Foreign country has 1600 units of labor. The two countries produce two goods, textiles and soybeans. The unit labor requirements in textile production for the Home and Foreign countries is 7 and 2.5, respectively, while soybean production requirements is respectively 3 and 5. a.) Graph the Home and Foreign production possibilities frontiers. b.) What is the opportunity cost of textiles in terms of soybeans for both countries? c.)...
[4] The Home country has 2,500 units of labor available while the Foreign country has 1700...
[4] The Home country has 2,500 units of labor available while the Foreign country has 1700 units of labor. The two countries produce two goods, textiles and soybeans. The unit labor requirements in textile production for the Home and Foreign countries is 7.2 and 2.2, respectively, while soybean production requirements is respectively 2.9 and 5.1. a.) Graph the Home and Foreign production possibilities frontiers. b.) What is the opportunity cost of textiles in terms of soybeans for both countries? c.)...
The Home country has 2,800 units of labor available while the Foreign country has 1700 units...
The Home country has 2,800 units of labor available while the Foreign country has 1700 units of labor. The two countries produce two goods, textiles and soybeans. The unit labor requirements in textile production for the Home and Foreign countries is 7.2 and 2.7, respectively, while soybean production requirements is respectively 3.1 and 5.5. a.) Graph the Home and Foreign production possibilities frontiers. b.) What is the opportunity cost of textiles in terms of soybeans for both countries? c.) What...
The NCO Corporation has won a tender to drill an oil field in the Oman Sea....
The NCO Corporation has won a tender to drill an oil field in the Oman Sea. In order to transport the workers to the site, NCO has the following two options with related cost: Option1:To buy a ship for O.R 20,000,000. Annual fixed operating costs will be O.R 500,000 the variable cost per journey is O.R 1,000. At the end of the four-year project, the ship can be disposed of for O.R 12,000,000. Option2:To buy a helicopter for O.R 12,000,000....
The Birmingham Road Company (BRC) has won a tender to build a highway extension. The project...
The Birmingham Road Company (BRC) has won a tender to build a highway extension. The project will last 10 years and will generate free cash flows (FCFs) of £100 million per year for 10-years. These FCFs are after-tax but before financing costs. The unlevered (i.e., all equity) cost of capital for the project is 10% and BRC’s tax rate is 40%. BRC will finance the project with a combination of debt and equity and is considering three alternatives as regards...
The Birmingham Road Company (BRC) has won a tender to build a highway extension. The project...
The Birmingham Road Company (BRC) has won a tender to build a highway extension. The project will last 10 years and will generate free cash flows (FCFs) of £100 million per year for 10-years. These FCFs are after-tax but before financing costs. The unlevered (i.e., all equity) cost of capital for the project is 10% and BRC’s tax rate is 40%. BRC will finance the project with a combination of debt and equity and is considering three alternatives as regards...
The UCC Perfect Tender Rule sets out certain options that the buyer of goods has if...
The UCC Perfect Tender Rule sets out certain options that the buyer of goods has if the delivery fails to conform to the contract. What are these options? What conditions must the buyer meet?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT