Question

In: Economics

The textbook solution for " Principle of Engineering Economic Analysis Edition 6th" by White, Case Pratt,...

The textbook solution for " Principle of Engineering Economic Analysis Edition 6th" by White, Case Pratt, seems to lack the step by step solution for problem chap 1- problem 30. Would you please provide it? Here is the problem

The process engineer at Strowbridge MetalWorks has the choice of machining a particular part on either of two machines. Orders for this part are received regularly, but the order size varies. When the order is processed on Manchine A, four sequential setup operations of 1 hour each are required. Once set up, the machining time is 0.50 hours per unit. When the order is processed on Machine B, eight sequential setup operations of 0.75 hours each are required. Once set up, the machining time per unit is 0.55 hours. The hourly wage rates for operators are $20 and $18 for Machine A and Machine B, respectively.
a. Which machine is preferred if the order size is 100 units?
b. Which machine is preferred id the order size is 500 units?
c. What is the breakeven order size?

Solutions

Expert Solution

a) Which machine is preferred if the order size is 100 units?

Machine A total cost for total unit is

Total hours required for setup of machine ( Four sequential steps) (1 hour * 4) = 4 hours.

Total Hours required for 100 units = (0.50 hours per unit * 100 units) = 50 hours.

Total hours for production of 100 units = ( 4 + 50) = 54 hours.

Total cost for 100 units = (54 hours * $20 per hour) = $1080

Machine B total cost for total units is

Total hours required for setup of machine ( Eight sequential steps) (0.75 hour * 8) = 6 hours.

Total Hours required for 100 units = (0.55 hours per unit * 100 units) = 55 hours.

Total hours for production of 100 units = ( 6 + 55) = 61 hours.

Total cost for 100 units = (61 hours * $18 per hour) = $1098

DECISION:

Machine A is better option for producing order size of 100 units since it has lower cost than machine B.

b) Which machine is preferred if the order size is 500 units?

Machine A

Total hours required for setup of machine ( Four sequential steps) (1 hour * 4) = 4 hours.

Total Hours required for 500 units = (0.50 hours per unit * 500 units) = 250 hours.

Total hours for production of 500 units = ( 4 + 250) = 254 hours.

Total cost for 500 units = (254 hours * $20 per hour) = $5080

Machine B

Total hours required for setup of machine ( Eight sequential steps) (0.75 hour * 8) = 6 hours.

Total Hours required for 500 units = (0.55 hours per unit * 500 units) = 275 hours.

Total hours for production of 500 units = ( 6 + 275) = 281 hours.

Total cost for 500 units = (281 hours * $18 per hour) = $5058

DECISION :

Machine B is the better option for the production of order size of 500 units. Since it has lower cost.

c) What is the break even order size?

Break even order size is the order size when there is no cost difference for the production of order size from either of the machine.

Break even order = Order cost cost in machine A = Order size cost in machine B

Let assume the order size is X

Order cost in machine A = (4 hours + X*0.50) * $20

Order cost in machine B = ( 6 hours + X * 0.55) * $18

Break even order size

= (4 hours + X*0.50) * $20 = ( 6 hours + X * 0.55) * $18......................... Solving the equation

= 80 + 10X = 108 + 9.9X

= X = 280 units .

Hence the break even order size is 280 units.


Related Solutions

Database Systems: A Practical Approach to Design, Implementation, and Management, 6th Edition, Chapter 11 Database Analysis...
Database Systems: A Practical Approach to Design, Implementation, and Management, 6th Edition, Chapter 11 Database Analysis and the DreamHome Case Study. Based on Dreamhome Case Study; Title suitable for the project based on the case study? The problem statement ? Objectives? Boundary(scope)? User views? ExtraFeatures?
Book :Business Analytics 6th edition (data analysis and decision making) By s. Chirstian albright and wayne....
Book :Business Analytics 6th edition (data analysis and decision making) By s. Chirstian albright and wayne. L . w A If your company makes a particular decision in the face of uncertainty, you estimate that it will either gain $10,000, gain $1000, or lose $5000, with probabilities 0.40, 0.30, and 0.30, respectively. You (correctly) calculate the EMV as $2800. However, you distrust the use of this EMV for decision-making purposes. After all, you reason that you will never receive $2800;...
In textbook Engineering and Chemical Thermodynamics (2nd Edition), chapter 7 problem 33 7.33 A mixture of...
In textbook Engineering and Chemical Thermodynamics (2nd Edition), chapter 7 problem 33 7.33 A mixture of 2 moles propane (1), 3 moles butane (2), and 5 moles pentane (3) is contained at 30 bar and 200°C. The van der Waals constants for these species are: Species a3Jm3mol22 4 b3m3/mol4 Propane 0.94 9.06 3 1025 Butane 1.45 1.22 3 1024 Pentane 1.91 1.45 3 1024 Determine the fugacity and fugacity coeffi cient of propane using the following approximations: (a) the Lewis...
Explain the relationship between engineering economic analysis and engineering design. How does economic analysis assist decision...
Explain the relationship between engineering economic analysis and engineering design. How does economic analysis assist decision making in the design process? Give an example. use any engineering design parameter as an example
I would like the textbook solution to Auditing & Assurance Services 10th edition Chapter 21 problem...
I would like the textbook solution to Auditing & Assurance Services 10th edition Chapter 21 problem 32P please. There isn't an answer in the textbook solutions. This question has remained unanswered.
Chapter 7 in Horngren's cost accounting 16th edition textbook In summarizing its painstaking analysis of revenue...
Chapter 7 in Horngren's cost accounting 16th edition textbook In summarizing its painstaking analysis of revenue and direct cost variances, the textbook refers to three levels of analysis. What specifics are revealed with regard to the difference between a master budget and actual results at each level?
Chapter 7 in Horngren's cost accounting 16th edition textbook In summarizing its painstaking analysis of revenue...
Chapter 7 in Horngren's cost accounting 16th edition textbook In summarizing its painstaking analysis of revenue and direct cost variances, the textbook refers to three levels of analysis. What specifics are revealed with regard to the difference between a master budget and actual results at each level? Please use the textbook only.
Health Policy Issues: An Economic Perspective 6th edition by Paul J. Feldstein ISBN 978-1-56793-696-4 From Chapters...
Health Policy Issues: An Economic Perspective 6th edition by Paul J. Feldstein ISBN 978-1-56793-696-4 From Chapters 1 to 3 Need help identifying what Feldstein's view of government involvement in the US healthcare system.
Principle of Conservation Energy is always being applied to solve engineering mechanic analysis. Explain what is...
Principle of Conservation Energy is always being applied to solve engineering mechanic analysis. Explain what is Principle of Conservation Energy and when it is suitable to use this principle. Use appropriate real life application in your discussion.
Engineering Economic Analysis PLEASE TYPE OUT THE RESPONSE TO EACH QUESTION Why is an understanding of...
Engineering Economic Analysis PLEASE TYPE OUT THE RESPONSE TO EACH QUESTION Why is an understanding of depreciation important in performing economic analyses? After learning in CH 8 about depreciation, which is a non-cash expense, how does the method used affect income taxes, and why is this important from an economic analysis perspective? How does rationing affect Capital Decisions? Distinguish between Independent Opportunities and Mutually Exclusive Opportunities. Please explain from a risk perspective, the potential ramifications of making an incorrect Capital...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT