Calculating Manufacturing Cycle Efficiency

Indy Company has the following data for one of its manufacturing plants:

Maximum units produced in a quarter (3-month period): 250,000 units
Actual units produced in a quarter (3-month period): 210,000 units
Productive hours in one quarter: 25,000 hours

The actual cycle time for Indy Company is 7.14 minutes, and the theoretical cycle time is 6 minutes.

Required:

1. Calculate the amount of processing time and the amount of nonprocessing time. If required, round your answers to two decimal places.

Processing time minutes
Nonprocessing time minutes

2. Calculate the MCE. If required, round your answer to nearest whole number.
%

Solutions

Expert Solution

Answer:
1)
Processing time is nothing but a Theoretical cycle time
Processing time = 6 min.
Non processing time
              = Actual Cycle time (-) Processing time
              =    7.14 minutes (-) 6 minutes
              =     1.14 minutes
Non processing time =     1.14 minutes
2)
Manufacturing cycle Efficiency
              = Processing time /Actual Cycle time
              =   6 / 7.14
              =   84%
Manufacturing cycle time (MCE )   = 84%

Related Solutions

Calculating Cycle Time and Velocity Indy Company has the following data for one of its manufacturing...
Calculating Cycle Time and Velocity Indy Company has the following data for one of its manufacturing plants: Maximum units produced in a quarter (3-month period): 250,000 units Actual units produced in a quarter (3-month period): 199,000 units Productive hours in one quarter: 25,000 hours Required: 1. Compute the theoretical cycle time (in minutes). minutes per unit 2. Compute the actual cycle time (in minutes). Round your answer to two decimal places. minutes per unit 3. Compute the theoretical velocity in...
A steel company is considering the relocation of one of its manufacturing plants. The company’s executives...
A steel company is considering the relocation of one of its manufacturing plants. The company’s executives have selected four areas that they believe are suitable locations. However, they want to determine if the average wages are significantly different in any of the locations, since this could have a major impact on the cost of production. A survey of hourly wages of similar workers in each of the four areas is performed with the following results. Do the data indicate a...
A steel company is considering the relocation of one of its manufacturing plants. The company’s executives...
A steel company is considering the relocation of one of its manufacturing plants. The company’s executives have selected four areas that they believe are suitable locations. However, they want to determine if the average wages are significantly different in any of the locations, since this could have a major impact on the cost of production. A survey of hourly wages of similar workers in each of the four areas is performed with the following results. Do the data indicate a...
A steel company is considering the relocation of one of its manufacturing plants. The company’s executives...
A steel company is considering the relocation of one of its manufacturing plants. The company’s executives have selected four areas that they believe are suitable locations. However, they want to determine if the average wages are significantly different in any of the locations, since this could have a major impact on the cost of production. A survey of hourly wages of similar workers in each of the four areas I performed with the following results. Hourly Wages ($) Area 1...
an us company has two manufacturing plants one in UAE and one in another country. Both...
an us company has two manufacturing plants one in UAE and one in another country. Both produce the same items,eath for sale in their perspectives countries. However their productivity figures are quite different. The analyst thinks this is because the UAE plan uses more automated equipment for processing while the other uses a high percentage for labor. 1-explain how that factor can cause productivity figures to be misleading. 2-Is there another way to compare the two plants that would be...
Pitt Company has the following data for 20X4 concerning its manufacturing operations. PITT COMPANY DATA FOR...
Pitt Company has the following data for 20X4 concerning its manufacturing operations. PITT COMPANY DATA FOR 20X4 SALES AND MANUFACTURING OPERATIONS Selling price per unit $ 120 Variable manufacturing cost per unit 95 Variable operating cost per unit 15 Total fixed manufacturing costs 500,000 Total fixed operating costs 100,000 The company produced 100,000 units during the year and sold 90,000 of those units. REQUIRED: Answer the following questions related to the above data, showing appropriate calculations to support your answers....
Suppose Goodyear Tire and Rubber Company is considering divesting one of its manufacturing plants. The plant...
Suppose Goodyear Tire and Rubber Company is considering divesting one of its manufacturing plants. The plant is expected to generate free cash flows of $ 1.55 million per​ year, growing at a rate of 2.4 % per year. Goodyear has an equity cost of capital of 8.7 %​, a debt cost of capital of 7.1 %​, a marginal corporate tax rate of 32 %​, and a​ debt-equity ratio of 2.7. If the plant has average risk and Goodyear plans to...
Calculating Manufacturing Overhead Rates Windsor Company, accumulated the following data for 2017: Milling Department manufacturing overhead...
Calculating Manufacturing Overhead Rates Windsor Company, accumulated the following data for 2017: Milling Department manufacturing overhead $187,200 Finishing Department manufacturing overhead $76,800 Machine hours used Milling Department 9,000 hours Finishing Department 2,000 hours Labor hours used Milling Department 1,000 hours Finishing Department 1,000 hours Required a. Calculate the plantwide manufacturing overhead rate using machine hours as the allocation base. $Answer per machine hour b. Calculate the plantwide manufacturing overhead rate using direct labor hours as the allocation base. $Answer per...
Andalus Furniture Company has two manufacturing plants, one at Aynor and another at Spartanburg.
Problem 12-27 (Algorithmic)Andalus Furniture Company has two manufacturing plants, one at Aynor and another at Spartanburg. The cost in dollars of producing a kitchen chair at each of the two plants is given here.Aynor: Cost = 80Q1 + 5Q12 + 106Spartanburg: Cost = 28Q2 + 3Q22 + 158WhereQ1 = number of chairs produced at AynorQ2= number of chairs produced at SpartanburgAndalus needs to manufacture a total of 30 kitchen chairs to meet an order just received. How many chairs should...
17. A manufacturing company that has only one product has established the following standards for its...
17. A manufacturing company that has only one product has established the following standards for its variable manufacturing overhead. Variable manufacturing overhead standards are based on machine-hours.   Standard hours per unit of output 4.40 machine-hours   Standard variable overhead rate $11.55 per machine-hour The following data pertain to operations for the last month:   Actual hours 8,800 machine-hours   Actual total variable manufacturing overhead cost $95,910   Actual output 1,900 units What is the variable overhead efficiency variance for the month? $2,832 U $7,293...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT