In: Accounting
Question 8 Soren Health Corporation provides Covid testing for medical professional. Shown below are the standard costs for a Covid test:
Direct materials (2 test tubes @ $1.30 per tube) $2.60
Direct labor (1 hour @ $24 per hour) 24.00
Variable overhead (1 hour @ $6.00 per hour) 6.00
Fixed overhead (1 hour @ $10.00 per hour) 10.00
Total standard cost per test $42.60
Actual activity for the month of November 2020, when 1,290 tests
were conducted, resulted in the following:
Direct materials (2,690 test tubes) $3,228
Direct labor (1,366 hours) 31,418
Variable overhead 6,360
Fixed overhead 13,150
a) Calculate the total direct labor variance
b) Calculate the direct labor price variance
c) Calculate the direct labor quantity variance
d) Discuss possible reasons (2 for each) why the price variance and
quantity variances may have occurred
WORKING NOTES: | |||||||||||
Actual Cost for 1,290 Tests | |||||||||||
Standard Cost Per unit | Standard Cost for Actual Production | ||||||||||
Standard Time | Std. Rate | Total Cost | Standard Time | Std. Rate | Total Std. Cost | Actual Time | Act. Rate | Actual Cost | |||
1 | $ 24.00 | $ 24 | 1290 | $ 24.00 | $ 30,960 | 1366 | $ 23.00 | $ 31,418 | |||
Hrs | Per Hours | Hrs (1,190 X 1Hr) | Per Hours | Hrs | Per Hours | ||||||
SOLUTION : A | |||||||||||
Labour Total Direct Labor Variance = Standard Cost of Labour " -" Actual Cost of Labour | |||||||||||
Labour Cost Variance = | $ 30,960.00 | '-' | $ 31,418.00 | ||||||||
Labour Cost Variance = | $ 458.00 | (Unfavorable) | |||||||||
SOLUTION : B | |||||||||||
Labour Price Variance = (Actual Rate - Standard Rate ) X Actual Hours | |||||||||||
Labour Price Variance = (Actual Rate - Standard Rate ) X Actual Hours | $ 23.00 | '-' | $ 24.00 | ) X | 1,366 | ||||||
Labour Price Variance = (Actual Rate - Standard Rate ) X Actual Hours | $ 1.00 | X | 1,366 | ||||||||
Labour Price Variance = (Actual Rate - Standard Rate ) X Actual Hours | 1366 | (favorable) | |||||||||
SOLUTION : C | |||||||||||
Labour Efficiency Variance = (Actual Hours '-' Standard Hours )X Standard Rate | |||||||||||
Labour Efficiency Variance = ( | 1,366.00 | '-' | 1,290.00 | ) X | $ 24.00 | ||||||
Labour Efficiency Variance = | $ 76.00 | X | $ 24.00 | ||||||||
Labour Efficiency Variance = | 1824 | (Unfavorable) | |||||||||
Solution: D | |||||||||||
Price Variances : | |||||||||||
1) Price Variances is due actual rate and standard rate is different | |||||||||||
2) Actual hours used is difference as per budgeted hours so this is also one rason for variances | |||||||||||
Quantity Variances: | |||||||||||
1) Actual hours used is difference as per budgeted hours so there is variances | |||||||||||
2) Standard rate and actual rate is also different | |||||||||||