Question

In: Accounting

Badgersize Company has the following information for its Forming Department for the month of August. Work...

Badgersize Company has the following information for its Forming Department for the month of August.

Work in Process Inventory, August 1: 20,000 units

Direct materials: 100% complete

$

80,000

Conversion: 20% complete

24,000

Balance in work in process, August 1

$

104,000

Units started during August

54,000

Units completed and transferred in August

58,000

Work in process (70% complete), August 31

?

Costs charged to Work in Process in August

Direct materials

$

164,000

Conversion costs:

Direct labor

$

101,000

Overhead applied

139,000

Total conversion

$

240,000


Assume materials are added at the start of processing.

Required:

a.    Calculate the equivalent units for the Forming Department for the month of August.

Direct Materials:

Conversion:

b.   Find the cost per equivalent unit of input resource. (Round your answers to 2 decimal places.)

Direct Materials:

Conversion:

Solutions

Expert Solution

Since method of calculating Equivalent units was not provided in the question. Solution is provided for Weighted average method and FOFO method .

Weighted average

Units

Reconciliation of Units

A

Opening WIP

                    20,000

B

Introduced

                    54,000

C=A+B

TOTAL

                    74,000

D

Transferred

                    58,000

E=C-D

Closing WIP

                    16,000

Statement of Equivalent Units (Weighted Average)

Material

Conversion Cost

Units

Complete %

Equivalent units

Complete %

Equivalent units

Transferred

             58,000

100%

              58,000

100%

           58,000

Closing WIP

             16,000

100%

              16,000

70%

           11,200

Total

             74,000

Total

              74,000

Total

           69,200

Cost per Equivalent Units (Weighted Average)

COST

Material

Conversion Cost

TOTAL

Beginning WIP Inventory Cost

$          80,000.00

$            24,000.00

$            104,000.00

Cost incurred during period

$        164,000.00

$          240,000.00

$            404,000.00

Total Cost to be accounted for

$        244,000.00

$          264,000.00

$            508,000.00

Total Equivalent Units

                    74,000

                     69,200

Cost per Equivalent Units

$                3.2973

$                  3.8150

Statement of cost (Weighted Average)

Cost

Equivalent Cost/unit

Ending WIP

Transferred

Units

Cost Allocated

Units

Cost Allocated

Material

$               3.30

                    16,000

$            52,756.76

                        58,000

$ 191,243.24

Conversion Cost

$               3.82

                    11,200

$            42,728.32

                        58,000

$ 221,271.68

TOTAL

$ 508,000.00

TOTAL

$            95,485.08

TOTAL

$ 412,514.92

Cost to be accounted for

Beginning Work In Progress:

Material

$    80,000.00

Conversion Cost

$   24,000.00

$        104,000.00

Cost incurred during period:

Cost Transferred

$                   -  

Material

$ 164,000.00

Conversion Cost

$ 240,000.00

$        404,000.00

Total Cost to be accounted for

$            508,000.00

Cost accounted for

Cost of Units transferred

Equivalent Units

Cost per Equivalent Units

Cost accounted for

Material

             58,000

$                     3.30

$          191,243.24

Conversion Cost

             58,000

$                     3.82

$          221,271.68

$            412,514.92

Cost of ending WIP

Equivalent Units

Cost per Equivalent Units

Cost accounted for

Cost Transferred

                       -  

$                          -  

$                           -  

Material

             16,000

$                     3.30

$            52,756.76

Conversion Cost

             11,200

$                     3.82

$            42,728.32

$               95,485.08

Total Cost accounted for

$            508,000.00

FIFO METHOD

EUP-FIFO Method

Units

% Material

EUP Material

% Conversion

EUP Conversion

Beginning Work in Process

20000

100%

20000

20%

4000

Started and completed

54000

100%

54000

100%

54000

Ending Work in Process

16000

100%

16000

70%

11200

Total Units

90000

90000

69200

Cost per Equivalent Unit of Production

Materials

Conversion

Cost incurred

$      164,000.00

$      240,000.00

Total costs

Costs

$      164,000.00

Costs

$      240,000.00

EUP

EUP

90000

EUP

69200

Cost per Equivalent Units of production

$                   1.82

$                   3.47

Total cost accounted for: Under FIFO

Beginning Inventory Cost:

$      104,000.00

Cost to complete beginning inventory

EUP

Cost per EUP

Total cost

Direct Material

20000

$                         1.82

36444.44444

Conversion

4000

$                         3.47

13872.83237

Total cost to complete beginningf inventory

50317.27681

Total cost of units in beginning inventory

$      154,317.28

Cost of units started and completed

EUP

Cost per EUP

Total cost

Direct Material

54000

$                        1.82

$        98,400.00

Conversion

54000

$                         3.47

$      187,283.24

Total cost of units started and completed

$      285,683.24

Total cost of Units transferred out

$      440,000.51

Costs of Ending WIP:

EUP

Cost per EUP

Total cost

Direct Material

16000

$                         1.82

$        29,155.56

Conversion

11200

$                         3.47

$        38,843.93

Total cost of Ending WIP

$        67,999.49

Total cost accounted for

$      508,000.00


Related Solutions

Badgersize Company has the following information for its Forming Department for the month of August. Work...
Badgersize Company has the following information for its Forming Department for the month of August. Work in Process Inventory, August 1: 20,000 units Direct materials: 100% complete $ 80,000 Conversion: 20% complete 24,000 Balance in work in process, August 1 $ 104,000 Units started during August 50,000 Units completed and transferred in August 58,000 Work in process (70% complete), August 31 ? Costs charged to Work in Process in August Direct materials $ 141,000 Conversion costs: Direct labor $ 124,000...
Badgersize Company has the following information for its Forming Department for the month of August Work...
Badgersize Company has the following information for its Forming Department for the month of August Work in Process Inventory, August 1: 20,000 units Direct materials: 100% complete $ 80,000 Conversion: 20% complete 24,000 Balance in work in process, August 1 $ 104,000 Units started during August 47,000 Units completed and transferred in August 57,000 Work in process (70% complete), August 31 ? Costs charged to Work in Process in August Direct materials $ 142,000 Conversion costs: Direct labor $ 104,000...
Badgersize Company has the following information for its Forming Department for the month of August. Work...
Badgersize Company has the following information for its Forming Department for the month of August. Work in Process Inventory, August 1: 20,000 units Direct materials: 100% complete $ 80,000 Conversion: 20% complete 24,000 Balance in work in process, August 1 $ 104,000 Units started during August 54,000 Units completed and transferred in August 59,000 Work in process (70% complete), August 31 ? Costs charged to Work in Process in August Direct materials $ 165,000 Conversion costs: Direct labor $ 113,000...
Badgersize Company has the following information for its Forming Department for the month of August. Work...
Badgersize Company has the following information for its Forming Department for the month of August. Work in Process Inventory, August 1: 20,000 units Direct materials: 100% complete $ 80,000 Conversion: 20% complete 24,000 Balance in work in process, August 1 $ 104,000 Units started during August 54,000 Units completed and transferred in August 56,000 Work in process (70% complete), August 31 ? Costs charged to Work in Process in August Direct materials $ 165,000 Conversion costs: Direct labor $ 115,000...
The following information is available for Department C for the month of June: Units Cost Work...
The following information is available for Department C for the month of June: Units Cost Work in process, June 1 (70% complete) 10,000 Direct materials $ 36,000 Direct labor 18,000 Manufacturing overhead 24,000 Total work in process, June 1 $78,000 Started in production during June 40,000 Costs added: Direct materials $108,000 Direct labor 48,000 Manufacturing overhead 60,600 Total costs added during June $216,600 Work in process, June 30 (80% complete) 4,000 Materials are added at the beginning of the process....
The Xio Company uses a job-costing system at its plant. The plant has a forming department...
The Xio Company uses a job-costing system at its plant. The plant has a forming department and a boxing department. Xio uses normal costing with two direct-cost categories (direct materials and direct manufacturing labor) and two manufacturing overhead cost pools (the Forming department with machine-hours as the allocation base and the Boxing department with direct manufacturing labor costs as the allocation base). The 2017 budget for the plant is as follows: Forming Department Boxing Department Manufacturing overhead costs $21,662,500 $20,452,500...
Altira Corporation provides the following information related to its merchandise inventory during the month of August...
Altira Corporation provides the following information related to its merchandise inventory during the month of August 2021: Aug.1 Inventory on hand—2,000 units; cost $5.30 each. 8 Purchased 8,000 units for $5.50 each. 14 Sold 6,000 units for $12.00 each. 18 Purchased 6,000 units for $5.60 each. 25 Sold 7,000 units for $11.00 each. 28 Purchased 4,000 units for $5.80 each. 31 Inventory on hand—7,000 units. Required: Using calculations based on a periodic inventory system, determine the inventory balance Altira would...
Altira Corporation provides the following information related to its merchandise inventory during the month of August...
Altira Corporation provides the following information related to its merchandise inventory during the month of August 2021: Aug.1 Inventory on hand—3,600 units; cost $6.90 each. 8 Purchased 18,000 units for $7.10 each. 14 Sold 14,400 units for $13.60 each. 18 Purchased 10,800 units for $7.20 each. 25 Sold 13,400 units for $12.60 each. 28 Purchased 5,600 units for $5.80 each. 31 Inventory on hand—10,200 units. Required: Using calculations based on a periodic inventory system, determine the inventory balance Altira would...
Altira Corporation provides the following information related to its merchandise inventory during the month of August...
Altira Corporation provides the following information related to its merchandise inventory during the month of August 2021: Aug.1 Inventory on hand—3,800 units; cost $7.10 each. 8 Purchased 19,000 units for $7.30 each. 14 Sold 15,200 units for $13.80 each. 18 Purchased 11,400 units for $7.40 each. 25 Sold 14,200 units for $12.80 each. 28 Purchased 5,800 units for $5.80 each. 31 Inventory on hand—10,600 units. Required: Using calculations based on a periodic inventory system, determine the inventory balance Altira would...
Altira Corporation provides the following information related to its merchandise inventory during the month of August...
Altira Corporation provides the following information related to its merchandise inventory during the month of August 2021: Aug.1 Inventory on hand—2,600 units; cost $5.90 each. 8 Purchased 13,000 units for $6.10 each. 14 Sold 10,400 units for $12.60 each. 18 Purchased 7,800 units for $6.20 each. 25 Sold 9,400 units for $11.60 each. 28 Purchased 4,600 units for $5.80 each. 31 Inventory on hand—8,200 units. Required: Using calculations based on a periodic inventory system, determine the inventory balance Altira would...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT