Question

In: Accounting

Ayala Corporation accumulates the following data relative to jobs started and finished during the month of...

Ayala Corporation accumulates the following data relative to jobs started and finished during the month of June 2020.

Costs and Production Data

                                                                Actual

Standard

Raw materials unit cost                 $2.00                     $1.80

Raw materials units                         11,200                   10,800

Direct labor payroll                          $177,310              $170,240

Direct labor hours                            14,900                   15,200

Manufacturing overhead incurred                            $225,608                             

Manufacturing overhead applied                                                              $228,608

Machine hours expected to be used at normal capacity                   41,500

Budgeted fixed overhead for June                                                            $62,250

Variable overhead rate per machine hour                                              $3.20

Fixed overhead rate per machine hour                                                   $1.50

Overhead is applied on the basis of standard machine hours. 3.20 hours of machine time are required for each direct labor hour. The jobs were sold for $500,000. Selling and administrative expenses were $41,400. Assume that the amount of raw materials purchased equaled the amount used.

               

(a)

Compute all of the variances for (1) direct materials and (2) direct labor. (Round per unit values to 2 decimal places, e.g. 52.75 and final answers to 0 decimal places, e.g. 52.)

  1. Total materials variance                $

2. Materials price variance                   $

3. Materials quantity variance                    $

  1. Total labor variance                        $

Labor price variance                      $

Labor quantity variance                $

Solutions

Expert Solution

a)

Direct materials:
        Price variance 2,160.0 Favorable
        Quantity variance          800 Favorable
        Total Material Variance 2,960.0 Favorable
Direct labor:
        Price variance    10,640 Favorable
        Quantity variance      3,570 Unfavorable
        Total Labor Variance      7,070 Favorable
Calculation of Direct material price variance:
Direct Material Price Variance= = ( SP -AP ) * AQ
= ( $ 2.00 - $ 1.80 ) * 10,800.
= $ 2,160 Favorable
Thus, Direct Material Price Variance is $ 2,160 Favorable
Calculation of Direct Material Quantity Variance is as follows:
Direct Material Quantity Variance = ( SQ - AQ ) * SP
= ( 11,200 - 10,800 ) * $ 2.00
= $ 800 Favorable
Thus, Direct Material Quantity Variance is $ 800 Favorable
Calculation of Direct Material Cost Variance is as follows:
Direct Material Cost Variance = Standard Cost - Actual cost
= ( SQ * SP ) - ( AQ * AP )
= ( 11,200 * $ 2.00 ) - ( 10,800 * $ 1.80 )
= $ 22,400 - $ 19,440
= $ 2,960 Favorable
Thus, Direct Material Cost Variance is $ 2,960 Favorable
Calculation of Direct labor price variance is as follows:
Direct Labor price variance = ( SR - AR ) * AH
= ( $ 11.90 - $ 11.20 ) * 15,200
= $ 10,640 Favorable
Therefore, Direct labor price variance $ 10,640 Favorable
Working note:
SR = Standard Labor cost / Standard labor hours
= $ 177,310 / 14,900
= $ 11.90
AR = Acutal labor cost/ Acutal labor hours
= $ 170,240 / 15,200
= $ 11.20
Calculation of Direct labor quantity variance is as follows:
Direct Labor Quantity variance = ( SH - AH ) * SR
= ( 14,900 - 15,200 ) * $ 11.90
= $ 3,570 Unfavorable
Thus, Direct Labor quantity variance is $ 3,570 Unfavorable
Calculation of Direct labor cost variance is as follows:
Direct Labor cost variance = Standard cost - Actual cost
= $ 177,310 - $ 170,240
= $ 7,070
Thus, Direct Labor efficiency variance is $ 7,070 Favorable
Where,
AH = Actual labor hours
SH = Standard labor hours
AR = Actual labor rate per hour
SR = Standard labor rate per hour
SQ = Standard Quantity of Material
AQ = Actual Quantity of Material
SP = Standard Price of per material
AP = Actual Price of per material

Related Solutions

Ayala Corporation accumulates the following data relative to jobs started and finished during the month of...
Ayala Corporation accumulates the following data relative to jobs started and finished during the month of June 2017. Costs and Production Data Actual Standard Raw materials unit cost $2.25 $2.10 Raw materials units used 10,600 10,000 Direct labor payroll $120,960 $120,000 Direct labor hours worked 14,400 15,000 Manufacturing overhead incurred $189,500 Manufacturing overhead applied $193,500 Machine hours expected to be used at normal capacity 42,500 Budgeted fixed overhead for June $55,250 Variable overhead rate per machine hour $3.00 Fixed overhead...
Ayala Corporation accumulates the following data relative to jobs started and finished during the month of...
Ayala Corporation accumulates the following data relative to jobs started and finished during the month of June 2017. Costs and Production Data Actual Standard Raw materials unit cost $2.25 $2.10 Raw materials units used 10,600 10,000 Direct labor payroll $120,960 $120,000 Direct labor hours worked 14,400 15,000 Manufacturing overhead incurred $189,500 Manufacturing overhead applied $193,500 Machine hours expected to be used at normal capacity 42,500 Budgeted fixed overhead for June $55,250 Variable overhead rate per machine hour $3.00 Fixed overhead...
Ayala Corporation accumulates the following data relative to jobs started and finished during the month of...
Ayala Corporation accumulates the following data relative to jobs started and finished during the month of June 2020. Costs and Production Data Actual Standard Raw materials unit cost $2.20 $2.10 Raw materials units 11,300 10,900 Direct labor payroll $166,500 $159,600 Direct labor hours 15,000 15,200 Manufacturing overhead incurred $210,420 Manufacturing overhead applied $214,320 Machine hours expected to be used at normal capacity 43,500 Budgeted fixed overhead for June $73,950 Variable overhead rate per machine hour $3.00 Fixed overhead rate per...
Ayala Corporation accumulates the following data relative to jobs started and finished during the month of...
Ayala Corporation accumulates the following data relative to jobs started and finished during the month of June 2020. Costs and Production Data Actual Standard Raw materials unit cost $2.10 $1.90 Raw materials units 11,300 10,900 Direct labor payroll $168,720 $166,770 Direct labor hours 14,800 15,300 Manufacturing overhead incurred $232,608 Manufacturing overhead applied $235,008 Machine hours expected to be used at normal capacity 41,500 Budgeted fixed overhead for June $66,400 Variable overhead rate per machine hour $3.20 Fixed overhead rate per...
Ayala Corporation accumulates the following data relative to jobs started and finished during the month of...
Ayala Corporation accumulates the following data relative to jobs started and finished during the month of June 2020. Costs and Production Data Actual Standard Raw materials unit cost $2.10 $1.95 Raw materials units 11,100 10,300 Direct labor payroll $150,000 $145,350 Direct labor hours 15,000 15,300 Manufacturing overhead incurred $232,308 Manufacturing overhead applied $235,008 Machine hours expected to be used at normal capacity 43,500 Budgeted fixed overhead for June $69,600 Variable overhead rate per machine hour $3.20 Fixed overhead rate per...
Ayala Corporation accumulates the following data relative to jobs started and finished during the month of...
Ayala Corporation accumulates the following data relative to jobs started and finished during the month of June 2017. Costs and Production Data Actual Standard Raw materials unit cost $2.40 $2.25 Raw materials units used 11,100 10,400 Direct labor payroll $177,000 $171,360 Direct labor hours worked 15,000 15,300 Manufacturing overhead incurred $204,550 Manufacturing overhead applied $206,550 Machine hours expected to be used at normal capacity 41,500 Budgeted fixed overhead for June $62,250 Variable overhead rate per machine hour $3.00 Fixed overhead...
Problem 24-02A Ayala Corporation accumulates the following data relative to jobs started and finished during the...
Problem 24-02A Ayala Corporation accumulates the following data relative to jobs started and finished during the month of June 2020. Costs and Production Data Actual Standard Raw materials unit cost $2.20 $2.10 Raw materials units 11,400 10,700 Direct labor payroll $175,500 $167,200 Direct labor hours 15,000 15,200 Manufacturing overhead incurred $202,600 Manufacturing overhead applied $205,200 Machine hours expected to be used at normal capacity 43,500 Budgeted fixed overhead for June $65,250 Variable overhead rate per machine hour $3.00 Fixed overhead...
Problem 25-2A Ayala Corporation accumulates the following data relative to jobs started and finished during the...
Problem 25-2A Ayala Corporation accumulates the following data relative to jobs started and finished during the month of June 2017. Costs and Production Data Actual Standard Raw materials unit cost $2.00 $1.85 Raw materials units used 11,500 10,900 Direct labor payroll $163,900 $159,600 Direct labor hours worked 14,900 15,200 Manufacturing overhead incurred $223,976 Manufacturing overhead applied $226,176 Machine hours expected to be used at normal capacity 42,500 Budgeted fixed overhead for June $72,250 Variable overhead rate per machine hour $3.10...
Problem 23-2A (Part Level Submission) Ayala Corporation accumulates the following data relative to jobs started and...
Problem 23-2A (Part Level Submission) Ayala Corporation accumulates the following data relative to jobs started and finished during the month of June 2017. Costs and Production Data Actual Standard Raw materials unit cost $2.40 $2.25 Raw materials units used 11,500 10,600 Direct labor payroll $177,600 $171,760 Direct labor hours worked 14,800 15,200 Manufacturing overhead incurred $202,000 Manufacturing overhead applied $205,200 Machine hours expected to be used at normal capacity 41,500 Budgeted fixed overhead for June $62,250 Variable overhead rate per...
Problem 23-2A (Part Level Submission) Ayala Corporation accumulates the following data relative to jobs started and...
Problem 23-2A (Part Level Submission) Ayala Corporation accumulates the following data relative to jobs started and finished during the month of June 2017. Costs and Production Data Actual Standard Raw materials unit cost $2.40 $2.25 Raw materials units used 11,100 10,400 Direct labor payroll $177,000 $171,360 Direct labor hours worked 15,000 15,300 Manufacturing overhead incurred $204,550 Manufacturing overhead applied $206,550 Machine hours expected to be used at normal capacity 41,500 Budgeted fixed overhead for June $62,250 Variable overhead rate per...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT