In: Accounting
Work in Process Account Data for Two Months; Cost of Production Reports
Pittsburgh Aluminum Company uses a process cost system to record
the costs of manufacturing rolled aluminum, which consists of the
smelting and rolling processes. Materials are entered from smelting
at the beginning of the rolling process. The inventory of Work in
Process—Rolling on September 1 and debits to the account during
September were as follows:
Bal., 2,600 units, ¼ completed: | ||
Direct materials (2,600 x $15.50) | $40,300 | |
Conversion (2,600 x ¼ x $8.50) | 5,525 | |
$45,825 | ||
From Smelting Department, 28,900 units | $462,400 | |
Direct labor | 158,920 | |
Factory overhead | 101,402 |
During September, 2,600 units in process on September 1 were completed, and of the 28,900 units entering the department, all were completed except 2,900 units that were 4/5 completed.
Charges to Work in Process—Rolling for October were as
follows:
From Smelting Department, 31,000 units | $511,500 |
Direct labor | 162,850 |
Factory overhead | 104,494 |
During October, the units in process at the beginning of the month were completed, and of the 31,000 units entering the department, all were completed except 2,000 units that were 2/5 completed.
Required:
2. Provide the same information for October by recording the October transactions in the four-column work in process account. Construct a cost of production report, and present the October computations (a through d) listed in part (1). If an amount box does not require an entry, leave it blank.
ACCOUNT | Work in Process-Rolling Department | ACCOUNT NO. | ||||
---|---|---|---|---|---|---|
Balance | ||||||
DATE | ITEM | POST. REF. | DEBIT | CREDIT | DEBIT | CREDIT |
Oct. 1 | Balance | |||||
Oct. 31 | Smelting Dept., 31,000 units at $16.50/unit | |||||
Oct. 31 | Direct labor | |||||
Oct. 31 | Factory overhead | |||||
Oct. 31 | Finished goods | |||||
Oct. 31 | Bal., 2,000 units, 2/5 completed |
If an amount is zero, enter in a zero "0". Round cost per unit answers to the nearest cent.
Pittsburgh Aluminum Company Cost of Production Report-Rolling Department For the Month Ended October 31 |
|||
---|---|---|---|
Whole Units | Equivalent Units | ||
Units | Direct Materials (a) | Conversion (a) | |
Units charged to production: | |||
Inventory in process, October 1 | |||
Received from Smelting Department | |||
Total units accounted for by the Rolling Department | |||
Units to be assigned costs: | |||
Inventory in process, October 1 | |||
Started and completed in October | |||
Transferred to finished goods in October | |||
Inventory in process, October 31 | |||
Total units to be assigned costs |
Costs | ||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|
Costs | Direct Materials | Conversion | Total Costs | |||||||||
Cost per equivalent unit: | ||||||||||||
Total costs for October in Rolling Department | $ | $ | ||||||||||
Total equivalent units | ||||||||||||
Cost per equivalent unit (b) | $ | $ | ||||||||||
Costs assigned to production: | ||||||||||||
Inventory in process, October 1 | $ | |||||||||||
Costs incurred in October | ||||||||||||
Total costs accounted for by the Rolling Department | $ | |||||||||||
Costs allocated to completed and partially completed units: | ||||||||||||
Inventory in process, October 1 balance (c) | $ | |||||||||||
To complete inventory in process, October 1 (c) | $ | $ | ||||||||||
Cost of completed October 1 work in process | $ | |||||||||||
Started and completed in October (c) | ||||||||||||
Transferred to finished goods in October (c) | $ | |||||||||||
Inventory in process, October 31 (d) | ||||||||||||
Total costs assigned by the Rolling Department | $ |
IN CASE OF ANY DOUBTS FEEL FREE TO COMMENT BELOW
PLEASE RATE MY ANSWER BY HITTING ??
THANK YOU!