In: Operations Management
13. Who has responsibility for risk acceptance?
The correct answer is
14. Which of the following is done FIRST in operational risk management?
The correct answer is ___
15. Which of the following would have the HIGHEST priority in a business continuity plan?
A. Resuming critical processes
B. Recovering sensitive processes
C. Restoring the site
D. Relocating operations to an alternative site
The correct answer is __
16. Which of the following statement is INCORRECT in operational risk management?
The correct answer is ___
13
Chief risk officer
Chief risk officers often assess the risk and takes the responsibility for risks that are not mitigated.
14
Identification of risks
The first step of any risk management process is to identify the risks. Then we identify the controls and check if the controls can handle the risks.
15
Resuming critical processes
In business continuity plan we need to make sure that the cyclical nature of the business continues. As a result, it is important to make sure that critical process for the business can resume.
16
Cost of controls should be more than the risk being mitigated
If the risk is not very expensive then there is no point in creating a control that is more expensive than the risk.