In: Accounting
Problem 7-16 Comparing Traditional and Activity-Based Product Margins [LO7-1, LO7-3, LO7-4, LO7-5]
Hi-Tek Manufacturing, Inc., makes two types of industrial component parts—the B300 and the T500. An absorption costing income statement for the most recent period is shown:
Hi-Tek Manufacturing Inc. Income Statement |
|||
Sales | $ | 1,695,300 | |
Cost of goods sold | 1,224,445 | ||
Gross margin | 470,855 | ||
Selling and administrative expenses | 560,000 | ||
Net operating loss | $ | (89,145 | ) |
Hi-Tek produced and sold 60,000 units of B300 at a price of $20 per unit and 12,700 units of T500 at a price of $39 per unit. The company’s traditional cost system allocates manufacturing overhead to products using a plantwide overhead rate and direct labor dollars as the allocation base. Additional information relating to the company’s two product lines is shown below:
B300 | T500 | Total | ||||
Direct materials | $ | 400,300 | $ | 162,300 | $ | 562,600 |
Direct labor | $ | 120,300 | $ | 42,500 | 162,800 | |
Manufacturing overhead | 499,045 | |||||
Cost of goods sold | $ | 1,224,445 | ||||
The company has created an activity-based costing system to evaluate the profitability of its products. Hi-Tek’s ABC implementation team concluded that $57,000 and $109,000 of the company’s advertising expenses could be directly traced to B300 and T500, respectively. The remainder of the selling and administrative expenses was organization-sustaining in nature. The ABC team also distributed the company’s manufacturing overhead to four activities as shown below:
Manufacturing Overhead |
Activity | |||||
Activity Cost Pool (and Activity Measure) | B300 | T500 | Total | |||
Machining (machine-hours) | $ | 202,825 | 90,400 | 62,100 | 152,500 | |
Setups (setup hours) | 135,020 | 74 | 240 | 314 | ||
Product-sustaining (number of products) | 100,600 | 1 | 1 | 2 | ||
Other (organization-sustaining costs) | 60,600 | NA | NA | NA | ||
Total manufacturing overhead cost | $ | 499,045 | ||||
Required:
1. Compute the product margins for the B300 and T500 under the company’s traditional costing system.
2. Compute the product margins for B300 and T500 under the activity-based costing system.
3. Prepare a quantitative comparison of the traditional and activity-based cost assignments.
1. Compute the product margins for the B300 and T500 under the company’s traditional costing system.
Answer:
Product Margin under Traditional costing | |||
B300 | T500 | Total | |
Product Margin | 310,634 | 160,221 | 470,855 |
Calculation:
To compute the product margins based on traditional costing system, we need to deduct the total costs from the sales. The sales quantity for both B300 and T500 is given in the question, we need to multiply it with the price. So sales will be:
B300 : 60,000 * 20 = 1200000
T500: 12,700 * 39 = 495,300
Then we need to deduct the material cost and labor cost which is directly given in the problem. And need to calculate the Manufacturing Overhead:
So, the manufacturing overhead will be the amount based on the percentage of direct labor which is calculated as below:
B300 : 499,045 * 120,300 / 162,800 = 368,766
T500: 499,045* 130,279/162,800 = 130,279
B300 | T500 | Total | |
Sales | 1200000 | 495300 | 1,695,300 |
Costs: | |||
Direct Material | 400,300 | 162,300 | 562,600 |
Direct labor | 120,300 | 42,500 | 162,800 |
Manufacturing Overhead | 368766 | 130279 | 499,045 |
Product Margin | 310,634 | 160,221 | 470,855 |
2. Compute the product margins for B300 and T500 under the activity-based costing system.
Answer:
Product Margin under Activity Based costing | |||
B300 | T500 | Total | |
Product Margin | 420,048 | (54,593) | 365,455 |
Calculation:
To compute the product margins based on activity based costing system, we need to deduct the total costs from the sales. The sales quantity for both B300 and T500 is given in the question, we need to multiply it with the price.
So sales will be:
B300 : 60,000 * 20 = 1200000
T500: 12,700 * 39 = 495,300
As we done in traditional costing, we need to consider both the direct material and direct labor. But then we need to take the advertising, machining, setup costs etc which is provided in the question.
Machining:
B300 : 202,825 * 90,400/ 152,500 = 120,232
T500: 202,825 * 62,100/ 152,500 = 82,593
Setup cost:
B300 : 135,020 * 74/ 314 = 31,820
T500: 135,020 * 240/ 314 = 103,200
Product Sustaining:
B300 : 100,600 * 1/ 2 = 50300
T500: 100,600 * 1/ 2 = 50300
Then after adding up all the cost, we need to deduct it from the sales as calculated below:
B300 | T500 | Total | |
Sales | 1200000 | 495300 | 1695300 |
Costs: | |||
Direct Material | 400,300 | 162,300 | 562,600 |
Direct labor | 120,300 | 42,500 | 162,800 |
Advertising expense | 57,000 | 109,000 | 166,000 |
Machining | 120,232 | 82,593 | 202,825 |
Setups | 31,820 | 103,200 | 135,020 |
Product sustaining | 50300 | 50300 | 100,600 |
Total cost | 779,952 | 549,893 | 1,329,845 |
Product Margin | 420,048 | (54,593) | 365,455 |
3. Prepare a quantitative comparison of the traditional and activity-based cost assignments.
Answer:
Traditional Method:
B300 |
T500 | Total | |||
% of | % of | ||||
Amount | Total Amount | Amount | Total Amount | Amount | |
Traditional Cost System | |||||
Direct Material | 400,300 | 71.15% | 162,300 | 28.85% | 562,600 |
Direct labor | 120,300 | 73.89% | 42,500 | 26.11% | 162,800 |
Manufacturing Overhead | 368,766 | 73.89% | 130,279 | 26.11% | 499,045 |
Total cost assigned to products | 889,366 | 335,079 | 1,224,445 | ||
Selling and Administrative | 560,000 | ||||
Total cost | 1,784,445 |
ABC Method:
B300 | T500 | Total | |||
% of | % of | ||||
Amount | Total Amount | Amount | Total Amount | Amount | |
Activity-Based Costing System | |||||
Direct costs: | |||||
Direct Material | 400,300 | 71.15% | 162,300 | 28.85% | 562,600 |
Direct labor | 120,300 | 73.89% | 42,500 | 26.11% | 162,800 |
Advertising expense | 57,000 | 34.34% | 109,000 | 65.66% | 166,000 |
Indirect costs: | |||||
Machining | 120,232 | 59.28% | 82,593 | 40.72% | 202,825 |
Batch Setup | 31,820 | 23.57% | 103,200 | 76.43% | 135,020 |
Product Sustained | 50,300 | 50.00% | 50,300 | 50.00% | 100,600 |
Total cost assigned to products | 779,952 | 549,893 | 1,329,845 | ||
Costs not assigned to products: | |||||
Selling and administrarive expenses | 394,000 | ||||
Others | 60,600 | ||||
Total cost | 1,784,445 |
Calculation:
Here, we need to do the comparision of the both traditional and ABC method which we calculated in the requirement 1 and 2. With the help of both the methods, we need to find the total cost that will be incurring.
First we need to include all the direct costs which includes, material, labor and overhead for both B300 and T500. Then we need to find the total.
Next step is to find the percentage of these indivudal cost to the total costs of both the B300 and T500. After adding up all these costs, we get the Total cost assigned to products. Then we need to add the selling and administrative expenses, which is provided in the question, to get the total costs as per traditional method.
The next step is to calculate the total cost as per ABC Method to do the quantitative comparison. So here, we need to take the costs which we considered in requirement 2. We need to include both direct and indirect costs to find the Total cost assigned to products. Next step is to find the percentage of these indivudal cost to the total costs of both the B300 and T500. After adding up all these costs, we get the Total cost assigned to products.
Then we need to add the Costs not assigned to products:. That is the Selling and administrarive expense and the other expenses. The other expenses is directly provided in the question, which is organization-sustaining costs of 60,600.
The selling and administrative expenses for ABC method is Total selling and administrative expenses minus the advertising cost which was already considered. So the selling and administrative expenses is:
Selling and administrative expenses = 560,000 - 57,000 - 109,000 = 394,000
Then we need to add up all these total costs to get the final amount.
As we compare, we can see that the total cost will be same for both even though the Total cost assigned to products is different.