In: Finance
Q1: For each of the following:
Compute the Future value (FV)
Present Value |
Years |
Interest rate |
Future Value |
$ 3,159 84,53 89,305 |
T 16 19 26 |
13% Y 9 5 |
|
Compute Present Value |
15 8 13 25 |
7% 11 10 13 |
$ 17,328 41,517 7903,82 647,816 |
Compute the interest rate |
|||
Present Value |
Years |
Interest rate |
Future Value |
$ 715 905 15,000 70,300 |
11 8 23 16 |
$ 1,381 1,718 141,832 312,815 |
Q2: Compute the Future value of $ 1,000 continuously c compounded 12 percent for:
5 years at a stated annual interest rate of
12 percent;
3 years at a stated annual interest rate of 10 percent.
10 years at a stated annual interest rate of 5 percent;
and
8 years at stated annual interest rate of 7 percent
Q3: Consider a firm with a contract to sell an asset for $ 115,000 three years from now, the asset costs $ 72,000 to produce today. Given a relevant discount rate on this asset is 13 percent per year. Will firm make a profit on this asset? At what interest rate does the firm just break even?
Formula to be used in all the questions is,
Future Value = Present Value * ( 1+ Interest Rate )^ (no of years)
Answer 1.1)
Future Value = Present Value * ( 1+ Interest Rate )^ (no of years)
Present Value | Years | Interest | Future Value | Future Value |
3159 | 16 | 13% | = (3159)*(1+13%)^16 | 22325.68 |
8453 | 19 | 9% | = (8453)*(1+9%)^19 | 43462.46 |
89305 | 26 | 5% | = (89305)*(1+5%)^26 | 317539.35 |
Answer 1.2)
Present Value = Future Value / ( 1+ Interest Rate )^ (no of years)
Present Value = (17328)/(1+7%)^15 = 6280.46
Years | Interest | Future Value | Present Value |
15 | 7% | 17328 | 6280.46 |
8 | 11% | 41517 | 18015.33 |
13 | 10% | 790382 | 228945.51 |
25 | 13% | 647816 | 30513.40 |
Answer 1.3)
PV | Years | FV |
715 | 11 | 1381 |
905 | 8 | 1718 |
15000 | 23 | 141832 |
70300 | 16 | 312815 |
Lets take the first case,
FV = PV * ( 1+i)^n
1381 = 715 * ((1+i) ^ 11
divide above equation by 715
1381/715 = (1+i)^11
1.93 = (1+i)^11
lets multuply by power of 1/11 with both sides,
1.93^1/11 = 1+i
1.0616 = 1+i
i = 1 - 1.0616 = 6.16%
In similar way remaining values have been calculated,
PV | Years | FV | FV/PV | (FV/PV)^(1/n) | i |
715 | 11 | 1381 | 1.931468531 | 1.061670586 | 6.17% |
905 | 8 | 1718 | 1.898342541 | 1.083419935 | 8.34% |
15000 | 23 | 141832 | 9.455466667 | 1.102607643 | 10.26% |
70300 | 16 | 312815 | 4.449715505 | 1.097793779 | 9.78% |
Asnwer 2)
Future Value = Present Value * (1+i)^n
PV | i | n | FV |
1000 | 12% | 5 | 1762.34 |
1000 | 10% | 3 | 1331.00 |
1000 | 5% | 10 | 1628.89 |
1000 | 7% | 8 | 1718.19 |
Answer 3)
Future Value = 115000
Asset costs today = 72000
Interest = 13%
No of years = 3 years
let us calculate the present value
PV = FV / (1+i)^n
= 115000 / (1+13%)^3
PV = 79700.76
We can conclude than present value of asset is higher than cost today hence firm will not make a profit of given scenario.
With trial amd error method, 16.89% should be the interest rate for breakeven the cost with 3 year period.