Question

In: Accounting

Fixed Overhead Spending and Volume Variances, Capacity Management Lorale Company, a producer of recreational vehicles, recently...

Fixed Overhead Spending and Volume Variances, Capacity Management

Lorale Company, a producer of recreational vehicles, recently decided to begin producing a major subassembly for jet skis. The subassembly would be used by Lorale’s jet ski plants and also would be sold to other producers. The decision was made to lease two large buildings in two different locations: Little Rock, Arkansas, and Athens, Georgia. The company agreed to an 11-year, renewable lease contract. The plants were of the same size, and each had 10 production lines. New equipment was purchased for each line, and workers were hired to operate the equipment. The company also hired production line supervisors for each plant. A supervisor is capable of directing up to two production lines per shift. Two shifts are run for each plant. The practical production capacity of each plant is 300,000 subassemblies per year. Two standard direct labor hours are allowed for each subassembly. The costs for leasing, equipment depreciation, and supervision for a single plant are as follows (the costs are assumed to be the same for each plant):

Supervision (10 supervisors @ $50,000) $ 500,000
Building lease (annual payment) 800,000
Equipment depreciation (annual) 1,100,000
Total fixed overhead costs* $2,400,000

*For simplicity, assume these are the only fixed overhead costs.

After beginning operations, Lorale discovered that demand for the product in the region covered by the Little Rock plant was less than anticipated. At the end of the first year, only 240,000 units were sold. The Athens plant sold 300,000 units as expected. The actual fixed overhead costs at the end of the first year were $2,500,000 (for each plant).

1. Calculate a fixed overhead rate based on standard direct labor hours.
$ per hour

2. Calculate the fixed overhead spending and volume variances for the Little Rock and Athens plants. What is the most likely cause of the spending variance? Enter amounts as positive numbers and select Favorable or Unfavorable. If an amount is zero, enter "0" and choose "Not applicable" from the dropdown list.

Athens Plant
Spending variance $ Unfavorable
Volume variance $ Not applicable
Little Rock Plant
Spending variance $ Unfavorable
Volume variance $ Unfavorable

Solutions

Expert Solution

1. Fixed overhead rate = $2,400,000/600,000 hours*

= $4 per hour

*Standard hours allowed = 2 × 300,000 units.

2. Athens plant:

Actual FOH Budgeted FOH Applied FOH

$2,500,000 $2,400,000 $4 × 600,000 hours

$100,000 U 0

Spending Volume

Little Rock plant:

Actual FOH Budgeted FOH Applied FOH

$2,500,000 $2,400,000 $4 × 480,000 hours

$100,000 U $480,000 U

Spending Volume

The spending variance is almost certainly caused by supervisor salaries (for example, an unexpected midyear increase due to union pressures). It is unlikely that the lease payments or depreciation would be greater than budgeted. Changing the terms on a 10-year lease in the first year would be unusual (unless there is some sort of special clause permitting increased payments for something like unexpected inflation). Also, the depreciation should be on target (unless more equipment was purchased or the depreciation budget was set before the price of the equipment was known with certainty).

The volume variance is easy to explain. The Little Rock plant produced less than expected, and so there was an unused capacity cost:

$4 × 120,000 hours = $480,000. The Athens plant had no unused capacity.


Related Solutions

Fixed Overhead Spending and Volume Variances, Columnar and Formula Approaches Branch Company provided the following information:...
Fixed Overhead Spending and Volume Variances, Columnar and Formula Approaches Branch Company provided the following information: Standard fixed overhead rate (SFOR) per direct labor hour $5.00 Actual fixed overhead $305,000 BFOH $300,000 Actual production in units 16,000 Standard hours allowed for actual units produced (SH) 64,000 Required Enter amounts as positive numbers and select Favorable (F) or Unfavorable(U). 1. Using the columnar approach, calculate the fixed overhead spending and volume variances. (1) (2) (3)                   Spending Volume...
Fixed Overhead Spending and Volume Variances, Columnar and Formula Approaches Branch Company provided the following information:...
Fixed Overhead Spending and Volume Variances, Columnar and Formula Approaches Branch Company provided the following information: Standard fixed overhead rate (SFOR) per direct labor hour $5.00 Actual fixed overhead $305,000 BFOH $300,000 Actual production in units 16,000 Standard hours allowed for actual units produced (SH) 64,000 Required Enter amounts as positive numbers and select Favorable (F) or Unfavorable(U). 1. Using the columnar approach, calculate the fixed overhead spending and volume variances. (1) (2) (3)                   Spending Volume...
What is the volume variance in fixed overhead? Is the volume variance in fixed overhead favorable...
What is the volume variance in fixed overhead? Is the volume variance in fixed overhead favorable or unfavorable? Use the following scenario to help with the questions: DeFleur manufactures bicycles. The bicycles are manufactured in two divisions. In the framing division, the carbon bicycle frames are manufactured. In the assembly division, the components are assembled to the frame and the bike is ready for sale. There is no market for the unassembled frames and all manufactured frames are transferred to...
Overhead Application, Fixed and Variable Overhead Variances Zepol Company is planning to produce 600,000 power drills...
Overhead Application, Fixed and Variable Overhead Variances Zepol Company is planning to produce 600,000 power drills for the coming year. The company uses direct labor hours to assign overhead to products. Each drill requires 0.75 standard hour of labor for completion. The total budgeted overhead was $1,777,500. The total fixed overhead budgeted for the coming year is $832,500. Predetermined overhead rates are calculated using expected production, measured in direct labor hours. Actual results for the year are: Actual production (units)...
OVERHEAD APPLICATION, FIXED AND VARIABLE OVERHEAD VARIANCES Tules Company is planning to produce 2,400,000 power drills...
OVERHEAD APPLICATION, FIXED AND VARIABLE OVERHEAD VARIANCES Tules Company is planning to produce 2,400,000 power drills for the coming year. The company uses direct labour hours to assign overhead to products. Each drill requires 0.5 standard hour of labour for completion. The total budgeted overhead was $2,700,000. The total fixed overhead budgeted for the coming year is $1,320,000. Predetermined overhead rates are calculated using expected production, measured in direct labour hours. Actual results for the year are: Actual production (units)   ...
OVERHEAD APPLICATION, FIXED AND VARIABLE OVERHEAD VARIANCES Tules Company is planning to produce 2,400,000 power drills...
OVERHEAD APPLICATION, FIXED AND VARIABLE OVERHEAD VARIANCES Tules Company is planning to produce 2,400,000 power drills for the coming year. The company uses direct labour hours to assign overhead to products. Each drill requires 0.5 standard hour of labour for completion. The total budgeted overhead was $2,700,000. The total fixed overhead budgeted for the coming year is $1,320,000. Predetermined overhead rates are calculated using expected production, measured in direct labour hours. Actual results for the year are: Actual production (units)      2,360,000...
Overhead volume variances do not signal that overhead costs are in or out of control. Do...
Overhead volume variances do not signal that overhead costs are in or out of control. Do you agree? Please no hand-written answers.
TASK 5 - PC 4.5 Calculate fixed overhead total, expenditure and, where appropriate, volume, capacity and...
TASK 5 - PC 4.5 Calculate fixed overhead total, expenditure and, where appropriate, volume, capacity and efficiency variance Dhabia LLC, a producer of apple fruit juice has the following variable manufacturing overhead standard to produce a 5 litre apple juice in a bottle: 1.5 standard hours per a 5 litre apple juice at Dh 5.00 per direct labour hour. Last week 1600 hours were worked to produce a 1,000 bottles of the 5 litre fruit juice and Dh 8,480 was...
How do you calcuate the Fixed Overhead (FOH) spending variance and the Fixed Overhead (FOH) production...
How do you calcuate the Fixed Overhead (FOH) spending variance and the Fixed Overhead (FOH) production volume variance given the following information: (budgeted assembly time is 2 hrs per unit of output) Actual Results Static Budget Number of fans assembled $ sold 220 fans 150 fans Hours of assembley time 396 hours         - Variable Overhead (VOH) cost per hr of assembly time           - $ 31.00 VOH costs $ 12,693           - FOH cost $ 15,510 $ 14,100
Alden Company uses a two-variance analysis for overhead variances. Practical capacity is defined as 36 setups...
Alden Company uses a two-variance analysis for overhead variances. Practical capacity is defined as 36 setups and 36,000 machine hours to manufacture 7,200 units for the year. Selected data for 2016 follow: Budgeted fixed factory overhead: Setup $ 57,600 Other 265,000 $ 322,600 Total factory overhead incurred $ 494,000 Variable factory overhead rate: Per setup $ 650 Per machine hour $ 4 Total standard machine hours allowed for the units manufactured 24,000 hours Machine hours actually worked 28,000 hours Actual...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT