In: Accounting
1. Acme Company’s production budget for August is 17,600 units and includes the following component unit costs: direct materials, $7.70; direct labor, $10.10; variable overhead, $6.20. Budgeted fixed overhead is $33,000. Actual production in August was 18,810 units. Actual unit component costs incurred during August include direct materials, $8.50; direct labor, $9.10; variable overhead, $6.90. Actual fixed overhead was $34,600. The standard direct material cost per unit consists of 11 pounds of raw material at $0.7 per pound. During August, 319,770 pounds of raw material were used that were purchased at $0.50 per pound.
Required: Calculate the materials price variance and materials usage variance for August. (Do not round intermediate calculations. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance).)
Material price variance | ||
Material usage variance |
2. Acme Company’s production budget for August is 18,100 units
and includes the following component unit costs: direct materials,
$8.00; direct labor, $10.50; variable overhead, $6.50. Budgeted
fixed overhead is $38,000. Actual production in August was 19,872
units. Actual unit component costs incurred during August include
direct materials, $9.00; direct labor, $10.00; variable overhead,
$7.50. Actual fixed overhead was $40,100. The standard direct labor
cost per unit consists of 0.5 hour of labor time at $21 per hour.
During August, $198,720 of actual labor cost was incurred for 8,640
direct labor hours.
Required:
Calculate the labor rate variance and labor efficiency variance for
August. (Indicate the effect of each variance by selecting
"F" for favorable, "U" for unfavorable, and "None" for no effect
(i.e., zero variance).)
Labor rate variance | ||
Labor efficiency variance |
3. Acme Company’s production budget for August is 18,900 units
and includes the following component unit costs: direct materials,
$7.2; direct labor, $11.4; variable overhead, $5.4. Budgeted fixed
overhead is $46,000. Actual production in August was 21,840 units.
Actual unit component costs incurred during August include direct
materials, $9.60; direct labor, $10.80; variable overhead, $6.20.
Actual fixed overhead was $48,900. The standard variable overhead
rate per unit consists of $5.4 per machine hour and each unit is
allowed a standard of 1 hour of machine time. During August,
$135,408 of actual variable overhead cost was incurred for 24,180
machine hours.
Required:
Calculate the variable overhead spending variance and the variable
overhead efficiency variance. (Do not round intermediate
calculations. Indicate the effect of each variance by selecting "F"
for favorable, "U" for unfavorable, and "None" for no effect (i.e.,
zero variance).)
Variable overhead spending variance | ||
Variable overhead efficiency variance |
4. Acme Company’s production budget for August is 23,000 units
and includes the following component unit costs: direct materials,
$9.0; direct labor, $11.0; variable overhead, $5.8. Budgeted fixed
overhead is $49,000. Actual production in August was 24,075 units.
Actual unit component costs incurred during August include direct
materials, $10.00; direct labor, $10.00; variable overhead, $6.80.
Actual fixed overhead was $52,200. The standard fixed overhead
application rate per unit consists of $2.4 per machine hour and
each unit is allowed a standard of 1 hour of machine time.
Required:
Calculate the fixed overhead budget variance and the fixed overhead
volume variance. (Indicate the effect of each variance by
selecting "F" for favorable, "U" for unfavorable, and "None" for no
effect (i.e., zero variance).)
Fixed overhead budget variance | ||
Fixed overhead volume variance |