In: Economics
Question 1. Consider a queuing system with a single queue and two servers in series.
How many statements are true? (A) 0 (B) 1 (C) 2 (D) 3 (E) 4
Statement 1. Johnson’s rule is a sequencing rule that generates a schedule to minimize the total processing time.
Statement 2. Johnson’s rule concept is to schedule jobs with smaller times on first server early in the schedule.
Statement 3. A Gantt chart is a time plot of a schedule.
Statement 4. Flow of the first job in a schedule is the time of completion of the project.
Part 2.
Question 2. Consider a queuing system with a single queue and a single server.
How many statements are true? (A) 0 (B) 1 (C) 2 (D) 3 (E) 4
Statement 1. The MPT rule minimizes the total flow of a schedule.
Statement 2. The flow time of a job in a schedule equals the queue time plus the processing time.
Statement 3. The flow time of a schedule will always be greater than the processing time of a schedule.
Statement 4. The queue time of a job in a schedule is the flow of the preceding job.