Question

In: Accounting

BJenkins Company uses a job order cost system with overhead applied to jobs on the basis...

BJenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during April, but not sold. Job C was started during April, but not completed. The job cost sheets revealed the following costs for April:

Job A Job B Job C
Cost of Jobs in Process, 4/1/2016 $ 12,400 $ 1,100 $
Direct Materials Used 2,400 8,800 10,200
Direct Labor 10,800 8,800 3,400
Applied Manufacturing Overhead ? ? ?


Required:
If no other jobs were started, completed, or sold, determine the balance in each of the following accounts at the end of April:

a.) Work in Process

b.) Finished Goods

c.) Cost of Goods Sold

Solutions

Expert Solution

Job A Job B Job C
Cost of Jobs in Process, 4/1/2016 12400 1100 -
Direct Materials Used 2400 8800 10200
Direct Labor 10800 8800 3400
Applied Manufacturing Overhead
(Note:1) 8100 6600 2550
Notes:
1 Job A Job B Job C
Direct Labor a 10800 8800 3400
direct labor rate b 20 20 20
Direct Labor hours c=a/b 540 440 170
predetermined overhead rate d 15 15 15
Applied Manufacturing Overhead e=c*d 8100 6600 2550
a) Work-in-process
Job A Job B Job C
Beginning balance 12400 1100
Direct Materials Used 2400 8800 10200
Direct Labor 10800 8800 3400
Applied Manufacturing Overhead 8100 6600 2550
33700 25300 16150
Less:Jobs completed 33700 25300 0
0 0 16150
Balance in work-in-process=$16150
b) Finished goods
Job A Job B
Jobs completed 33700 25300
Less: Job sold 33700 0
0 25300
Balance in finished goods=$ 25300.
c) Balance in cost of goods sold=Cost of Job Sold=Cost of Job A=$ 33700

Related Solutions

ABC Company uses a job order cost system with overhead applied to products on the basis...
ABC Company uses a job order cost system with overhead applied to products on the basis of machine hours. For the upcoming year, the company estimated its total manufacturing overhead cost at $259,530 and total machine hours at 63,300. During the first month of operations, the company worked on three jobs and recorded the following actual direct materials cost, direct labor cost, and machine hours for each job:     Job 101 Job 102 Job 103 Total Direct materials used $ 11,800...
ABC Company uses a job order cost system with overhead applied to products on the basis...
ABC Company uses a job order cost system with overhead applied to products on the basis of machine hours. For the upcoming year, the company estimated its total manufacturing overhead cost at $222,840 and total machine hours at 61,900. During the first month of operations, the company worked on three jobs and recorded the following actual direct materials cost, direct labor cost, and machine hours for each job: Job 101 Job 102 Job 103 Total Direct materials used $ 10,200...
Medusa Products uses a job-order costing system. Overhead costs are applied to jobs on the basis...
Medusa Products uses a job-order costing system. Overhead costs are applied to jobs on the basis of machine-hours. At the beginning of the year, management estimated that the company would work 88,800 machine-hours and incur $346,320 in manufacturing overhead costs for the year.     Required: 1. Compute the company's predetermined overhead rate. (Round your answer to 2 decimal places.) Predetermined overhead rate ............................... Per MH 2. Assume that during the year the company actually worked only 81,900 machine-hours and incurred...
The company uses a job-order costing system in which overhead is applied to jobs on the...
The company uses a job-order costing system in which overhead is applied to jobs on the basis of direct labor cost. Its predetermined overhead rate is based on a cost formula that estimated $94,500 of manufacturing overhead for an estimated activity level of $45,000 direct labor dollars. At the beginning of the year, the inventory balances were as follows: Raw materials $ 10,800 Work in process $ 4,400 Finished goods $ 8,900 During the year, the following transactions were completed:...
Harwood Company uses a job-order costing system that applies overhead cost to jobs on the basis...
Harwood Company uses a job-order costing system that applies overhead cost to jobs on the basis of machine-hours. The company's predetermined overhead rate of $2.30 per machine-hour was based on a cost formula that estimates $213,900 of total manufacturing overhead for an estimated activity level of 93,000 machine-hours. Required: 1. Assume that during the year the company works only 88,000 machine-hours and incurs the following costs in the Manufacturing Overhead and Work in Process accounts: Compute the amount of overhead...
Job Order Costing: Wadadli Products uses a job-order costing system Overhead costs are applied to jobs...
Job Order Costing: Wadadli Products uses a job-order costing system Overhead costs are applied to jobs on the basis of machine-hours. At the beginning of the year, management estimated that 170,000 machine-hours would be required for the periods estimated level of production. The company also estimated $212,500 of fixed manufacturing overhead expenses for the coming period and variable manufacturing overhead of $1.50 per machine hour. Required: 1. Compute the company’s predetermined overhead rate. 2. Assume that during the year of...
Best Products Inc. Uses a job-order system in which overhead is applied to jobs on the...
Best Products Inc. Uses a job-order system in which overhead is applied to jobs on the basis od DIRECT LABOR COST. At he beginning of the year the inventories are follows: Raw Material ………………………. $ 42,000 Work in Process …………………….   30,000 Finished Goods ……………………… 58,000 During the year, the following transactions were completed: Raw material purchased on account, $ 190,000 (crédito) Raw material requisitioned for use in production, $200,000 ( 80% direct, 20 % indirect ) Cost for employees services...
hardwood company uses a job order costing system that applies overhead cost to jobs on the...
hardwood company uses a job order costing system that applies overhead cost to jobs on the basis of machine hours. The companys predetermined overhead rate of $2.50 Per machine hour was based on the cost formula that estimates $237,500 of total manufacturing overhead for an estimated activity level of 95,000 machine hours. 1. Manufacturing Overhead Maintenance                          36,000                        ???                (a) Indirect Materials                    9,500 Indirect Labor                         75,000 Utilities                                    44,000 Insurance                                8,500 Depreciation                            56,000 Balance:                                    ???         Work in Process: Direct Materials              860,000 Direct...
Tyler Tooling Company uses a job order cost system with overhead applied to products on the...
Tyler Tooling Company uses a job order cost system with overhead applied to products on the basis of machine hours. For the upcoming year, the company estimated its total manufacturing overhead cost at $225,720 and total machine hours at 62,700. During the first month of operations, the company worked on three jobs and recorded the following actual direct materials cost, direct labor cost, and machine hours for each job:     Job 101 Job 102 Job 103 Total Direct materials used $...
Tyler Tooling Company uses a job order cost system with overhead applied to products on the...
Tyler Tooling Company uses a job order cost system with overhead applied to products on the basis of machine hours. For the upcoming year, the company estimated its total manufacturing overhead cost at $201,920 and total machine hours at 63,100. During the first month of operations, the company worked on three jobs and recorded the following actual direct materials cost, direct labor cost, and machine hours for each job: Job 101 Job 102 Job 103 Total Direct materials used $...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT