In: Accounting
Direct Labor Variances
Glacier Bicycle Company manufactures commuter bicycles from recycled materials. The following data for October of the current year are available:
| Quantity of direct labor used | 550 hrs. |
| Actual rate for direct labor | $12.80 per hr. |
| Bicycles completed in October | 260 bicycles |
| Standard direct labor per bicycle | 2 hrs. |
| Standard rate for direct labor | $13.10 per hr. |
a. Determine for October the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.
| Direct Labor Rate Variance | $ | |
| Direct Labor Time Variance | $ | |
| Total Direct Labor Cost Variance | $ |
b. How much direct labor should be debited to
Work in Process?
$
| Answer: |
| (a) |
|
Direct labor rate variance = Actual hours x ( Actual rate (-) Standard Rate ) = 550 x ( $ 12.80 (-) $ 13.10) = ($ 165) Favourable |
| Direct labor rate variance = ($ 165) Favourable |
|
Direct labor time variance = Standard Rate x ( Actual hours (-) Standard Hours ) = $ 13.10 x ( 550 (-) ( 260 x 2) = $ 393 Unfavourable |
| Direct labor time variance = $ 393 Unfavourable |
|
Total Direct labor cost variance = $ 393 (-) $ 165 = ( $ 228 ) Favourable |
| Total Direct labor cost variance = ( $ 228 ) Favourable |
| (b) |
|
Direct labor debited to Work in
process = 260 x 2 x $ 13.10 = $ 6,812 |
| Direct labor debited to Work in process = $ 6,812 |