Question

In: Accounting

Lehner Corporation has provided the following data from its activity-based costing accounting system:   Indirect factory wages...

Lehner Corporation has provided the following data from its activity-based costing accounting system:
  Indirect factory wages $577,000
  Factory equipment depreciation $346,000  
Distribution of Resource Consumption across Activity Cost Pools:
Activity Cost Pools
Customer
Orders
Product
Processing
Other Total
  Indirect factory wages 35%       55%       10% 100%
  Factory equipment depreciation 30%       55%       15% 100%

The "Other" activity cost pool consists of the costs of idle capacity and organization-sustaining costs that are not assigned to products.

How much indirect factory wages and factory equipment depreciation cost would NOT be assigned to products using the activity-based costing system?

$577,000

$346,000

$109,600

$0

Lehner Corporation has provided the following data from its activity-based costing accounting system:
  Indirect factory wages $569,000
  Factory equipment depreciation $270,000  
Distribution of Resource Consumption across Activity Cost Pools:
Activity Cost Pools
Customer
Orders
Product
Processing
Other Total
  Indirect factory wages 60%       25%       15% 100%
  Factory equipment depreciation 30%       45%       25% 100%

The "Other" activity cost pool consists of the costs of idle capacity and organization-sustaining costs that are not assigned to products.

How much indirect factory wages and factory equipment depreciation cost would be assigned to the Customer Orders activity cost pool?

$422,400

$565,400

$389,900

$839,000

Solutions

Expert Solution

  • All working forms part of the answer and clearly shown
  • Requirement 1: Note that ‘Other cost’ are not to be assigned

Calculation of allocation of overheads

Cost to be assigned

Cost not to be assigned

Cost

Amount

Customer Orders

Product Processing

Other

Total

Indirect Factory Wages

577000

[35%] 201950

[55%] 317350

[10%] 57700

[100%] 577000

Factory Equipment depreciation

346000

[30%] 103800

[55%] 190300

[15%] 51900

[100%] 346000

Since, ‘other’ allocated cost is not to be assigned and its total is asked in the question, The CORRECT ANSWER will be 57700 + 51900 = $ 109,600 [OPTION – C]

  • Requirement 2:

Cost to be assigned

Cost not to be assigned

Cost

Amount

Customer Orders

Product Processing

Other

Total

Indirect Factory Wages

569000

[60%] 341400

[25%] 142250

[15%] 85350

[100%] 569000

Factory Equipment depreciation

270000

[30%] 81000

[45%] 121500

[25%] 67500

[100%] 270000

Question’s requirement is regarding total cost allocated to Customer Order activity cost pool, and the answer will e 341400 + 81000 = $422,400 which is OPTION - A


Related Solutions

Beckley Corporation has provided the following data from its activity based costing accounting systems: Indirect factory...
Beckley Corporation has provided the following data from its activity based costing accounting systems: Indirect factory wages $16,000 Factor Equipment Depreciation $193,000 Distribution of resource Consumption across activity cost pools: Indirect factory wages customer orders(48%) product processing (47%) other (5%) total(100%) Factory equipment depreciation customer orders(61%) product processing (25%) other(14%) total(100%) The other activity cost pool consists of the costs of idle capacity and organization sustaining costs that are not assigned to products Required: a) determine the total amount of...
omasini Corporation has provided the following data from its activity-based costing accounting system: Supervisory wages $...
omasini Corporation has provided the following data from its activity-based costing accounting system: Supervisory wages $ 600,000 Factory supplies $ 200,000 Distribution of Resource Consumption across Activity Cost Pools: Activity Cost Pools Batch Processing Unit Processing Other Total Supervisory wages 25% 60% 15% 100% Factory supplies 40% 30% 30% 100% The "Other" activity cost pool consists of the costs of idle capacity and organization-sustaining costs that are not assigned to products. How much supervisory wages and factory supplies cost would...
Desilets Corporation has provided the following data from its activity-based costing accounting system: Supervisory wages $...
Desilets Corporation has provided the following data from its activity-based costing accounting system: Supervisory wages $ 83,600 Factory utilities $ 336,000 Distribution of Resource Consumption across Activity Cost Pools: Activity Cost Pools Batch Set-Ups Unit Processing Other Total Supervisory wages 64 % 34 % 2 % 100 % Factory utilities 34 % 59 % 7 % 100 % The "Other" activity cost pool consists of the costs of idle capacity and organization-sustaining costs that are not assigned to products. Required:...
Desilets Corporation has provided the following data from its activity-based costing accounting system: Supervisory wages $...
Desilets Corporation has provided the following data from its activity-based costing accounting system: Supervisory wages $ 85,600 Factory utilities $ 306,000 Distribution of Resource Consumption across Activity Cost Pools: Activity Cost Pools Batch Set-Ups Unit Processing Other Total Supervisory wages 60 % 37 % 3 % 100 % Factory utilities 29 % 63 % 8 % 100 % The "Other" activity cost pool consists of the costs of idle capacity and organization-sustaining costs that are not assigned to products. Required:...
Millner Corporation has provided the following data from its activity-based costing accounting system:Millner Corporation has provided...
Millner Corporation has provided the following data from its activity-based costing accounting system:Millner Corporation has provided the following data from its activity-based costing accounting system:        ACTIVITY COST POOLS          TOTAL COST                     TOTAL ACTIVITY DESIGNING PRODUCTS                $1,372,4478       7,798       PRODUCT DESIGN HOURS SETTING UP BATCHES                    33,300              740        BATCH SET UP ASSEMBLING PRODUCTS             126,160            6,640      ASSEBLY HOURS The activity rate for the "designing products" activity cost pool is closest to
Vanguard Corporation has provided the following data from its activity-based costing system: Activity Cost Pool Total...
Vanguard Corporation has provided the following data from its activity-based costing system: Activity Cost Pool Total Cost Total Activity Assembly $ 1,078,920 74,000 machine-hours Processing orders $ 76,560 1,650 orders Inspection $ 119,616 1,680 inspection-hours The company makes 400 units of product O37W a year, requiring a total of 630 machine-hours, 50 orders, and 10 inspection-hours per year. The product's direct materials cost is $36.92 per unit and its direct labor cost is $30.06 per unit. According to the activity-based...
Feldpausch Corporation has provided the following data from its activity-based costing system: Activity Cost Pool Total...
Feldpausch Corporation has provided the following data from its activity-based costing system: Activity Cost Pool Total Cost Total Activity Assembly $ 1,471,965 60,500 machine-hours Processing orders $ 54,224 1,850 orders Inspection $ 152,154 2,140 inspection-hours The company makes 1,230 units of product W26B a year, requiring a total of 1,380 machine-hours, 103 orders, and 39 inspection-hours per year. The product's direct materials cost is $52.21 per unit and its direct labor cost is $17.15 per unit. The product sells for...
Petitte Corporation has provided the following data from its activity-based costing system: Activity Cost Pool Total...
Petitte Corporation has provided the following data from its activity-based costing system: Activity Cost Pool Total cost Total activity Assembly $612,560 31,000 machine hours Processing orders $35,451 1,300 orders Inspection $100,217 1,690 Inspection hours Data concerning the company's product K54A appear below: Selling price $150 per unit Annual production and sales 410 units Annual machine hours 700 machine hours Annual number of orders 30 orders Annual inspection hours 30 orders Direct materials cost $45.67 per unit Direct labor cost $31.24...
Paparo Corporation has provided the following data from its activity-based costing system: Activity Cost Pool Total...
Paparo Corporation has provided the following data from its activity-based costing system: Activity Cost Pool Total Cost Total Activity Assembly $ 794,300 47,000 machine-hours Processing orders $ 61,280 1,600 orders Inspection $ 109,681 1,430 inspection-hours Data concerning the company's product Q79Y appear below: Annual unit production and sales 500 Annual machine-hours 1,130 Annual number of orders 115 Annual inspection hours 20 Direct materials cost $ 42.00 per unit Direct labor cost $ 41.31 per unit According to the activity-based costing...
Ravelo Corporation has provided the following data from its activity-based costing system: Activity Cost Pools Estimated...
Ravelo Corporation has provided the following data from its activity-based costing system: Activity Cost Pools Estimated Overhead Cost Expected Activity Assembly $ 510,520 50,000 machine-hours Processing orders $ 60,263 1,700 orders Inspection $ 83,589 1,710 inspection-hours Data concerning the company's product L19B appear below: Annual unit production and sales 550 Annual machine-hours 1,110 Annual number of orders 190 Annual inspection hours 140 Direct materials cost $ 49.74 per unit Direct labor cost $ 22.45 per unit According to the activity-based...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT