Question

In: Economics

In a construction project today, 600 square meters of thermic isolation is required. Main inputs consist...

In a construction project today, 600 square meters of thermic isolation is required. Main inputs consist of styro-foam and labor. In 2010, the cost of styro-foam was $8 per kg, knowing that the isolation used weighs 12 kilograms per 50 square meter. The cost index in 2010 was 190 while today in 2017 it is equal to 180. The estimated labor cost for a first installation is $27000. Past experience has shown that the cost related to the labor required for producing each new pump is lowered by 20%. Use the cost of the sixth installation as your standard cost to estimate the total direct labor cost, if the project needs 10 installations per each square meter. Calculate the total cost of the installed thermic isolation for this project.

Solutions

Expert Solution

Particulars Amount Calculation Remarks
Total sq metre                 600 Area of thermic isolation
Cost of styrofoam in 2010                     8
Cost adjusted for inflation (A)               7.58 (8/190)*180 (Cost base year/ Cost index base)* current cost index
Styrofoam required (B)                 144 (600/50)*12 (12Kg per 50 sqm)
Total cost of styrofoam (C=A*B)             1,091
Total installations (D)             6,000 (10*600) 10 installation per sqm *600 sq m
Cost per installation ('E)             7,078 (27000)*(1-0.2)^6 Cost of labour reduced till 6th installation
Cost of labour per installation (F=D*E) 4,24,67,328
Total Cost (F+C) 4,24,68,419

Please Upvote and Support.

Total cost is highlighted in bold.


Related Solutions

Provide 3 types of construction permits may be required in a construction project and elaborate on...
Provide 3 types of construction permits may be required in a construction project and elaborate on their impact on the construction schedule.
The mean time required to complete a certain type of construction project is 52 weeks with...
The mean time required to complete a certain type of construction project is 52 weeks with a standard deviation of 3 weeks. Answer questions 4–7 using the preceding information and modeling this situation as a normal distribution. 4. What is the probability of the completing the project in no more than 52 weeks? a) 0.25 b) 0.50 c) 0.75 d) 0.05 5. What is the probability of the completing the project in more than 55 weeks? a) 0.1587 b) 0.5091...
The mean time required to complete a certain type of construction project is 52 weeks with...
The mean time required to complete a certain type of construction project is 52 weeks with a standard deviation of 3 weeks. Answer questions 4–7 using the preceding information and modeling this situation as a normal distribution. What is the probability of the completing the project in no more than 52 weeks? 0.25 0.50 0.75 0.05 What is the probability of the completing the project in more than 55 weeks? 0.1587 0.5091 0.7511 0.0546 What is the probability of completing...
in Some mill investment project ,construction period of 2 years, 18-year production, infrastructure investment of 600...
in Some mill investment project ,construction period of 2 years, 18-year production, infrastructure investment of 600 $, floating capital of 400$, construction fund in the first year of an input, no salvage value, if the desired rate of return on investments is 10%, try begging after put into production, the project's annual profit at least how much to make the project possible?
An analyst wanted to predict the time required to complete a construction project using four variables...
An analyst wanted to predict the time required to complete a construction project using four variables - size of the contract ?1x1 (in $1000 units), number of workdays adversely affected by the weather ?2x2, number of subcontractors involved in the project ?4x4, and a variable ?3x3 that measured the presence ( ?3=1x3=1) or absence ( ?3=0x3=0) of a workers' strike during the construction. Fifteen construction projects were randomly chosen, and each of the four variables as well as the time...
WITH PROCESS: A construction project has the following data: initial disbursement $ 40,000. The required rate...
WITH PROCESS: A construction project has the following data: initial disbursement $ 40,000. The required rate of return is 9% per year. Net cash income for the following years: 1st. Year $ 8,000 = 2nd. Year $ 10,500 = 3rd. Year $ 19,000 = 4th. Year $ 18,800 = 5th. Year $ 18,800 = Net Present Value _____________ Determine the payback present value _______ PREPA is offering a $ 45 Bonus, payable semi-annually, for the next 20 years. The prevailing...
A construction project has the following data: initial disbursement $ 400,000. The required rate of return...
A construction project has the following data: initial disbursement $ 400,000. The required rate of return is 9% per year.          Net cash income for the following years:    1st. year $ 87,000 = 2nd. years $ 106,500 = 3rd. years $ 192,000 = 4th. years $ 184,800 = 5th. years $ 184,800 = Net Present Value _____________ Determine the payback present value _______
once a project is under construction, what level of inspections are required during the various phases...
once a project is under construction, what level of inspections are required during the various phases of construction?
A project that provides annual cash flows of $3,100 for 8 years costs $13,400 today. Required:...
A project that provides annual cash flows of $3,100 for 8 years costs $13,400 today. Required: (a) If the required return is 10 percent, what is the NPV for this project? (b) Determine the IRR for this project.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT