Question

In: Finance

Fairfax Paint is evaluating a 2-year project that would involve buying equipment for 420,000 dollars that...

Fairfax Paint is evaluating a 2-year project that would involve buying equipment for 420,000 dollars that would be depreciated to 20,000 dollars over 2 years using straight-line depreciation. Cash flows from capital spending would be 0 dollars in year 1 and 26,000 dollars in year 2. To finance the project, Fairfax Paint would borrow 420,000 dollars. The firm would receive 420,000 dollars from the bank today and would pay the bank $0 in 1 year and 477,246 dollars in 2 years (consisting of an interest payment of 57,246 dollars and a principal payment of 420,000 dollars). Relevant annual revenues are expected to be 348,000 dollars in year 1 and 380,000 dollars in year 2. Relevant annual costs are expected to be 92,000 dollars in year 1 and 88,000 dollars in year 2. The tax rate is 50 percent. The cost of capital is 9.28 percent and the interest rate on the loan would be 6.6 percent. What is the net present value of the project?

Solutions

Expert Solution

Note & Assumption:

1) Financial interest is not relevant fo cash flow. However it is deducted from EBIT to calculate the tax.

2) Net working capital requirement / change is zero.

3) After tax salvage value of the machine is assumed to be 20000. There will not be any capital gain

Deprciation.

Initial Cost = 420000 and after 2 years value come to 20000

As per straight line method, Depriciation / year = (420000-20000)/2 = 200000

Interest Calculation

Loan(Interest @ 6.6%)
Amt at Beging Initerest Amt at the End
Year1 420000 27720 447720
Year2 447720 29550 477270

Cashflow & NPV calculation

Year0 Year1 Year2
Annual Revenue $                -   $ 3,48,000 $ 3,80,000
Cost $     92,000 $     88,000
EBITDA $ 2,56,000 $ 2,92,000
(-) Depriciation $ 2,00,000 $ 2,00,000
EBIT $     56,000 $     92,000
(-)Interest $     27,720 $     29,550
EBT $     28,280 $     62,450
Tax @ 50% $     14,140 $     31,225
A. Opearational Cash Flow
EBIT $                -   $     56,000 $     92,000
(-) Tax $     14,140 $     31,225
(+) Depriciation $ 2,00,000 $ 2,00,000
Total Operational Cashflow $                -   $ 2,41,860 $ 2,60,775
B. Capital Expenditure
Initial Outlay $ -4,20,000
Capital Spending $              -   $   -26,000
Salvage (after Tax) $                -   $              -   $     20,000
Total Capital Spending Cashflow $ -4,20,000 $              -   $     -6,000
Total Net Working Capital Cash Flow $                -   $              -   $              -  
Total Project Cashflow $ -4,20,000 $ 2,41,860 $ 2,54,775
Cost of Capital 9.28%
NPV= $14,662.72

NPV function of Xcel is used with cost of capital of 9.28%


Related Solutions

10) Fairfax Paint is evaluating a project that would cost 6,728 dollars today. The project is...
10) Fairfax Paint is evaluating a project that would cost 6,728 dollars today. The project is expected to have the following other cash flows: 2,220 dollars in 1 year, 2,506 dollars in 3 years, and 3,169 dollars in 4 years. The internal rate of return for the project is 5.89 percent and the cost of capital for the project is 5.22 percent. What is the net present value of the project?
Fairfax Paint operates stores in Virginia. The firm is evaluating the Vienna project, which would involve...
Fairfax Paint operates stores in Virginia. The firm is evaluating the Vienna project, which would involve opening a new store in Vienna. During year 1, Fairfax Paint would have total revenue of 300,000 dollars and total costs of 225,000 dollars if it pursues the Vienna project, and the firm would have total revenue of 239,000 dollars and total costs of 184,000 if it does not pursue the Vienna project. Depreciation taken by the firm would be 64,000 dollars if the...
Fairfax Paint operates stores in Virginia. The firm is evaluating the Vienna project, which would involve...
Fairfax Paint operates stores in Virginia. The firm is evaluating the Vienna project, which would involve opening a new store in Vienna. During year 1, Fairfax Paint would have total revenue of 362,000 dollars and total costs of 280,000 dollars if it pursues the Vienna project, and the firm would have total revenue of 310,000 dollars and total costs of 253,000 if it does not pursue the Vienna project. Depreciation taken by the firm would be 65,000 dollars if the...
Fairfax Paint operates stores in Virginia. The firm is evaluating the Vienna project, which would involve...
Fairfax Paint operates stores in Virginia. The firm is evaluating the Vienna project, which would involve opening a new store in Vienna. During year 1, Fairfax Paint would have total revenue of 357,000 dollars and total costs of 215,000 dollars if it pursues the Vienna project, and the firm would have total revenue of 298,000 dollars and total costs of 182,000 if it does not pursue the Vienna project. Depreciation taken by the firm would be 60,000 dollars if the...
Litchfield Design is evaluating a 3-year project that would involve buying a new piece of equipment...
Litchfield Design is evaluating a 3-year project that would involve buying a new piece of equipment for 340,000 dollars today. The equipment would be depreciated straight-line to 20,000 dollars over 2 years. In 3 years, the equipment would be sold for an after-tax cash flow of 34,000 dollars. In each of the 3 years of the project, relevant revenues are expected to be 212,000 dollars and relevant costs are expected to be 111,000 dollars. The tax rate is 50 percent...
Litchfield Design is evaluating a 3-year project that would involve buying a new piece of equipment...
Litchfield Design is evaluating a 3-year project that would involve buying a new piece of equipment for 450,000 dollars today. The equipment would be depreciated straight-line to 50,000 dollars over 2 years. In 3 years, the equipment would be sold for an after-tax cash flow of 63,000 dollars. In each of the 3 years of the project, relevant revenues are expected to be 369,000 dollars and relevant costs are expected to be 142,000 dollars. The tax rate is 50 percent...
Litchfield Design is evaluating a 3-year project that would involve buying a new piece of equipment...
Litchfield Design is evaluating a 3-year project that would involve buying a new piece of equipment for 400,000 dollars today. The equipment would be depreciated straight-line to 30,000 dollars over 2 years. In 3 years, the equipment would be sold for an after-tax cash flow of 42,000 dollars. In each of the 3 years of the project, relevant revenues are expected to be 246,000 dollars and relevant costs are expected to be 127,000 dollars. The tax rate is 50 percent...
Litchfield Design is evaluating a 3-year project that would involve buying a new piece of equipment...
Litchfield Design is evaluating a 3-year project that would involve buying a new piece of equipment for 430,000 dollars today. The equipment would be depreciated straight-line to 40,000 dollars over 2 years. In 3 years, the equipment would be sold for an after-tax cash flow of 52,000 dollars. In each of the 3 years of the project, relevant revenues are expected to be 259,000 dollars and relevant costs are expected to be 95,000 dollars. The tax rate is 50 percent...
Silver Sun Food is evaluating the medical clinic project, a 2-year project that would involve buying...
Silver Sun Food is evaluating the medical clinic project, a 2-year project that would involve buying equipment for 38,000 dollars that would be depreciated to zero over 2 years using straight-line depreciation. Cash flows from capital spending would be $0 in year 1 and 15,000 dollars in year 2. Relevant annual revenues are expected to be 100,000 dollars in year 1 and 100,000 dollars in year 2. Relevant expected annual variable costs from the project are expected to be 10,000...
Violet Sky Entertainment is evaluating the trampoline park project, a 2-year project that would involve buying...
Violet Sky Entertainment is evaluating the trampoline park project, a 2-year project that would involve buying equipment for 54,000 dollars that would be depreciated to zero over 2 years using straight-line depreciation. Cash flows from capital spending would be $0 in year 1 and 5,000 dollars in year 2. Relevant annual revenues are expected to be 83,000 dollars in year 1 and 83,000 dollars in year 2. Relevant expected annual variable costs from the project are expected to be 10,000...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT