At the end of the month, the M&M Company had completed Job
Red and Job Yellow. The individual job cost sheets reveal the
following information:
Job |
Direct Materials | Direct Labor | Machine Hours |
Job Red | $6,720 | $2,016 | 24 |
Job Yellow | 12,966 | 4,104 | 76 |
Job Red produced 144 units, and Job Yellow consisted of 228
units.
Assuming that the predetermined overhead rate is applied by using
machine hours at a rate of $142 per hour, determine the (a) balance
on the job cost sheets for each job and (b) the cost per unit at
the end of April.
Predetermined overhead rate = $ 142 per hours
Overhead applied for each job = Machine hours * Predetermined overhead rate
Calculation of Overhead applied | ||||
Machine hours (a) | overhead rate (b) | Overhead cost (a * b) | ||
Job Red | 24 | 142 | 3,408 | |
Job Yellow | 76 | 142 | 10,792 | |
Total Balance on Job cost sheet = Direct material + Direct Labour + Overhead Cost | ||||
a . Balance on the job Cost Sheet for each job | ||||
Direct Material (a) | Direct Labour ( b) | Overhead cost (c) | Total Cost ( a+b+c) | |
Job Red | 6,720 | 2,016 | 3,408 | 12,144 |
Job Yellow | 12,966 | 4,104 | 10,792 | 27,862 |
Cost per unit = Total Cost / Total units | ||||
b . Cost per unit | ||||
Total Cost (a) | Total Units ( b) | Cost per unit ( a / b ) | ||
Job Red | 12,144 | 144 | 84.33 | |
Job Yellow | 27,862 | 228 | 122.20 |