Question

In: Accounting

DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations.

Month
1 2 3 4
Throughput time (days) ? ? ? ?
Delivery cycle time (days) ? ? ? ?
Manufacturing cycle efficiency (MCE) ? ? ? ?
Percentage of on-time deliveries 88 % 83 % 80 % 77 %
Total sales (units) 2830 2709 2570 2473

Management has asked for your help in computing throughput time, delivery cycle time, and MCE. The following average times have been logged over the last four months:

Average per Month (in days)
1 2 3 4
Move time per unit 0.9 0.6 0.7 0.7
Process time per unit 3.8 3.6 3.4 3.2
Wait time per order before start of production 18.0 19.7 22.0 23.8
Queue time per unit 4.5 5.1 5.8 6.6
Inspection time per unit 0.8 1.0 1.0 0.8


Required:

1-a. Compute the throughput time for each month.

1-b. Compute the delivery cycle time for each month.

1-c. Compute the manufacturing cycle efficiency (MCE) for each month.

2. Evaluate the company’s performance over the last four months.

3-a. Refer to the move time, process time, and so forth, given for month 4. Assume that in month 5 the move time, process time, and so forth, are the same as in month 4, except that through the use of Lean Production the company is able to completely eliminate the queue time during production. Compute the new throughput time and MCE.

3-b. Refer to the move time, process time, and so forth, given for month 4. Assume in month 6 that the move time, process time, and so forth, are again the same as in month 4, except that the company is able to completely eliminate both the queue time during production and the inspection time. Compute the new throughput time and MCE.

Solutions

Expert Solution

Data Span, Inc.
1) Throughput time=Process Time+Inspection time+Move Time+Queue Time
Month 1 Month 2 Month 3 Month 4
Process Time 3.8 3.6 3.4 3.2 Days
Inspection Time 0.8 1 1 0.8 Days
Move Time 0.9 0.6 0.7 0.7 Days
Queue Time 4.5 5.1 5.8 6.6 Days
ThroughPut time 10 10.3 10.9 11.3 Days
1b) Delivery Cycle Time=Wait Time+Throughput Time
Month 1 Month 2 Month 3 Month 4
Wait Time per order =(A) 18 19.7 22.0 23.8 Days
Throughput Time=(B) (Calulated in A above) 10 10.3 10.9 11.3 Days
Delivery Cycle Time=(A)+(B) 28 30 32.9 35.1 Days
1c ) Manufacturing Cycle Efficiency (MCE)=Process Time/Throughput Time
Month 1 Month 2 Month 3 Month 4
Process Time=(A) 3.8 3.6 3.4 3.2 Days
Throughput Time=(B)=(Caluculated in (A) above 10 10.3 10.9 11.3 Days
Manufacturing Cycle Efficiency=(A)/(B) 38.00% 34.95% 31.19% 28.32% Days
2) Month Throughput Time(Days) Delivery Cycle Time(Days) Manufacturing Cycle Efficiency(MCE)(%)
Month1 10 28 38.00%
Month 2 10.3 30 34.95%
Month 3 10.9 32.9 31.19%
Month 4 11.3 35.1 28.32%
In all the cases performance are not favourable due to :
Trend Favorable/Unfavorable
a) The Throughput time measues displays Increasing Unfavorable
b) Delivery Cycle time is also in increasing trend. Increasing Unfavorable
c ) Manufacturing Efficiency has declining trend. Reducing Unfavorable
3a)
Month 5
Process Time 3.2
Inspection Time 0.8
Move Time 0.7
ThroughPut time 4.7
Month 5
Process Time=(A) 3.2
ThroughPut time=(B) 4.7
Manufacturing Cycle Efficiency=(A)/(B) 68.09%
3b) Month 6
Process Time 3.2
Move Time 0.7
ThroughPut time 3.9
Month 6
Process Time=(A) 3.2
ThroughPut time=(B) 3.9
Manufacturing Cycle Efficiency(A)/(B) 82.05%
Month 5 Month 6
Throughput Time(Days) 4.7 3.9
Manufacturing Efficiency Time(%) 68.09% 82.05%

Related Solutions

DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 4 Throughput time (days) ?...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 4 Throughput time (days) ?...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 4 Throughput time (days) ?...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 4 Throughput time (days) ?...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 4 Throughput time (days) ?...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 4 Throughput time (days) ?...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 4 Throughput time (days) ?...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 4 Throughput time (days) ?...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 4 Throughput time (days) ?...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 4 Throughput time (days) ?...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT