Question

In: Economics

The table sets out Sue’s Surfboards’ total product schedule.              Labor                   &

The table sets out Sue’s Surfboards’ total product schedule.

             Labor                                     Output

      (workers per week)                (surfboards per week)

               1                                        30

               2                                        70

               3                                       120

               4                                       160

               5                                       190

               6                                       210

               7                                       220

(a). Draw the total product curve.
Calculate the average product of labor and draw the average product curve. Calculate the marginal product of labor and draw the marginal product curve.

(b). Sue’s Surfboards, in Problem 3, hires workers at $500 a week and its total fixed cost is $1,000 a week.

(i). Calculate total cost, total variable cost, and total fixed cost of each output in the table. Plot these

points and sketch the short-run total cost curves passing through them.

(ii). Calculate average total cost, average fixed cost, average variable cost, and marginal cost of each output in the table. Plot these points and sketch the short-run average and marginal cost curves passing through them.

Solutions

Expert Solution

A) the total product curve has been plotted in figure 1

figure 1

Average product can be found out by dividing the total product with the quantity of labor.

Marginal product is the change in output that results from employing an additional worker.

Table 1 shows the value of Average product and marginal product and they have been drawn in figure 2.

Table 1

Figure 2

b.1) Sue's surfboards hires workers at $500 a week. Variable cost can be calculated by multiplying $500 to number of workers hired. Fixed cost = $1000. Total costs can be calculated by adding the variable costs and fixed costs. Table 2 gives these costs and they are plotted in figure 3

Table 2

Figure 3

b.2) Average total cost = total cost/quantity of output

average fixed cost = fixed cost/ quantity of output

average variable cost = variable cost/quantity of output

marginal cost = change in the total cost as an additional output is produced.

Table 3 gives these costs and they are plotted in figure 4.

Table 3

Figure 4

Please upvote if this answer helped you. Thank you.


Related Solutions

Complete the following table calculating marginal product and average product. Labor Inputs Total Product Marginal Product...
Complete the following table calculating marginal product and average product. Labor Inputs Total Product Marginal Product Average Product 0 0 0 0 1 60 2 136 3 204 4 256 5 300 6 336
Use the following table to answer questions a through d. Labor Input Total Product Marginal Product...
Use the following table to answer questions a through d. Labor Input Total Product Marginal Product Average Product 0 0 --- --- 1 A 70 B 2 135 C D 3 E F 63 4 G 51 H 5 I J 57 6 324 K L a. What is the value of A in the table? b. What is the value of C in the table? c. What is the value of B in the table? d. What is the...
Complete the table below showing labor (ex: # of workers), total output, and the marginal product...
Complete the table below showing labor (ex: # of workers), total output, and the marginal product (MP) of labor for a company. Labor Total Output MP of labor 0 0 NA 1 5 5 2 12 3 6 4 4 5 25 6 27 2
Question 1) In table 1, Calculate the marginal product of labor and average product of labor....
Question 1) In table 1, Calculate the marginal product of labor and average product of labor. Table 1: Surfboard Production Labor (workers per week) Total Product (surfboards per week) Marginal Product Average product 0 0 - - 1 30 2 70 3 120 4 160 5 190 6 210 7 220 Question 2) Surfboard Production Costs    Labor (workers per week) Total Product (surfboards per week) TFC (SAR per surfboard) TVC TOTAL COST AFC AVC ATC MC 0 0 3000...
The table sets out the data for an economy when the​government's budget is balanced. If the​...
The table sets out the data for an economy when the​government's budget is balanced. If the​ government's budget becomes a deficit of ​$2.0 ​trillion, what are the real interest rate and​ investment? Does crowding out​ occur? Real interest rate ​(percent per​ year) Loanable funds demanded Loanable funds supplied ​(trillions of 2009​ dollars) 4 7.5 6.5 5 7.0 7.0 6 6.5 7.5 7 6.0 8.0 8 5.5 8.5 9 5.0 9.0 10 4.5 9.5 If the​ government's budget becomes a deficit...
The top table sets out the market demand schedule for smoothies. Each of the 100 producers of smoothies has the costs shown in the bottom table when it uses its least-cost plant.
PRICE (dollars per smoothie); Quantity demanded (smoothies per hour) 1.90 ; 1,000 2.00 ; 950 2.20 ; 800 2.91; 700 4.25 ; 550 5.25 ; 400 5.50 ; 300 _________________________________________________________________________________________________________ Quantity (smoothies per hour) ; Marginal cost (dollars per additional smoothie) ; Average variable cost (dollars per smoothie) ; Average total cost (dollars per smoothie) 3 ; 2.50 ; 4.00 ; 7.33 4 ; 2.20 ; 3.53 ; 6.03 5 ; 1.90 ; 3.24 ; 5.24    6 ; 2.00 ;...
1.Table 27 Labor Output Marginal Product of Labor Marginal Revenue Product of Labor Wage 0       0...
1.Table 27 Labor Output Marginal Product of Labor Marginal Revenue Product of Labor Wage 0       0 --- --- --- 1   400 400 $800 $450 2   700 300 $600 $450 3   950 250 $500 $450 4 1050 100 $200 $450 Refer to Table 27. How many workers should the firm hire? A.1 B. 2 C. 3 D. 4 2. If education produces positive externalities and the government does not intervene in the market, we would expect Group of answer choices A....
.   From the hypothetical market demand schedule in the table, determine the total revenue. On two...
.   From the hypothetical market demand schedule in the table, determine the total revenue. On two graphs, plot the demand schedule and total revenue. Find the elasticity of market demand between the points (A and B, B and C, etc) and indicate whether the price elasticity of demand is elastic, inelastic, or unitary elastic. Please show all work to receive full marks. Alternative or point   Price (in $)   Quantity demanded (million units/year) A   $3.50   1 B   3.00   2 C   2.50  ...
Suppose a single firm has the marginal revenue product schedule for a particular type of labor...
Suppose a single firm has the marginal revenue product schedule for a particular type of labor given in the following table. Number of units of labor MRP of labor 1 $16 2 15 3 14 4 13 5 12 6 11 7 10 8 9 (a) Assume there are 200 firms with the same marginal-revenue-product schedules for this particular type of labor. Compute the total or market demand for this labor by completing column 1 in the table below. (1)...
1. The following is a total-product schedule for a factor. Assume that the firm employs only...
1. The following is a total-product schedule for a factor. Assume that the firm employs only one factor for production of the output. Units of factor 1 2 3 4 5 6 7 Total product 24 42 54 64 72 78 82 a. If the product the firm produces sells for a constant $2 per unit, what is the marginal revenue product of the third unit of the factor? b. If the firm's product sells for a constant $2 and...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT