Question

In: Accounting

It was spring 2019 when John Edgeworth was a project manager at Kreative Toy Corporation (KTC)...

It was spring 2019 when John Edgeworth was a project manager at Kreative Toy Corporation (KTC) submitted a proposal for funding to the recently established product review committee. He was proposing that KTC introduce through its distribution channels a new toy based on a popular cartoon character. John felt that Kreative could get this new product out for Christmas, Kreative could take advantage of the strong market for gift giving. John also knew that the toy market was very volatile and these types of toys may only last one season, so he felt the committee needed to approve the proposal quickly to ensure that the product would be ready for the Christmas season. John looked at the calendar on his desk which read Monday, May 11, 2019, and knew it the proposal was approved he would have to manage the project very carefully to meet the delivery date he put in the proposal of September 18, 2019, just nineteen weeks away.

Headquartered in Mississauga, Ontario where Kreative had both a manufacturing facility and its distribution centre. Creative was proud of the fact that could produce a wide variety of products in their Mississauga plant and had a preference for manufacturing products in-house.

John expected to receive approval and feedback from the committee by the end of the week, at which time he would earnestly start co-ordinating the product plan. As John was an experienced project manager he created a preliminary list of activities, as shown in Exhibit A attached.

Based on the schedule John created, he felt he could begin to work on some of the activities immediately. He felt he could finalize the product design and placing an order for the new equipment required. This being said, John realized that many of the activities had to be performed sequentially, as an example John could not train workers on the new equipment until it was installed and the tooling for the machine was complete. He also knew he could not order the raw materials until the engineering work was complete and an advertising plan was complete, as the advertising plan would influence the colour selection of the new toy.

John was concerned about the delivery schedule and investigated opportunities to cut the project time. He went to speak to the Marketing Manager, Cicely Carmichael, who told him after looking at his plan that she could probably reduce the product advertising, but she also told him that she anticipated a reduction in sales of three percent for each week of “lost” advertising. Cicely also told John that on a new product he could not get away with anything less than six weeks of advertising for the new product. She further said that she would have to double up on the amount of advertising during those six weeks and that would mean the advertising budget would not change.

After discussing the plan with Cicely, John went to speak with the Production Manager in the tool shop, Jeffrey Lynch. Lynch offered to speed up the tool build by working extra hours, most likely on weekends but the additional cost would add $5,500.00 to the budget. Jeffrey felt if this extra cost was approved by Edgeworth, he could improve delivery time by two weeks.

Exhibit A

Activities Needed for a New Product Introduction

Activity

Description

Immediate

Predecessor

Estimated Time

(in Weeks)

A

Obtain Funding Approval

1

B

Finalize Engineering

A

1

C

Delivery of New Equipment

A

8

D

Build dies/tools

B

12

E

Install Equipment

C

1

F

Train Workers

D, E

1

G

De-Bug Process

F

1

H

Establish an Advertising Plan

A

1

I

Finalize Package and Artwork

H

2

J

Advertise

H

12

K

Raw Material Delivery

D, I

2

L

Initial Production Run

G, K

3

M

Ship Product

J, L

1

Creative Toy Corporation Case Study

  1. Create a Network Diagram for the above Activity Table. How can they meet on the date? If crashing is necessary to create the crashing Network Diagram as well.
  2. Create a high-level WBS diagram with a final cost for the overall project. Break down the costs in the WBS. Refer to page 138 in the textbook for a diagram. Make some assumptions on the costs and use the costs that have been given to you make some assumptions

The fundamental cause questions to be answered:

  1. How can Kreative Toy, with your leadership as a Project Manager, ensure the physical product is ready for delivery to customers by September 18? Explain your action plan – how will you accomplish this?

If the project cannot be completed on time, what can you do? Please explain your decision

Solutions

Expert Solution

Well, as per the time and schedule the product should be in the market before the Christmas and the prime intention behind this date is to grab the lion share of toy market. As per the current circumstances it seems a herculean task for the company to get their product out for sale before Christmas since the time required for advertising and tool build taking almost 12 weeks, which is not acceptable in the current situation. In order to make the delivery on time the company should outsource their production since company can only provide training to the workers only when new machines are installed and also there is a delay in ordering raw materials due to the incomplete engineering work. So If the the company outsource their product they can cut their time in large extent and can deliver the product to the market on time.

Any doubt comment below i will explain or resolve until you got....
PLEASE.....UPVOTE....ITS REALLY HELPS ME....THANK YOU....SOOO MUCH....
Please comment if any querry i will resolve as soon as possible


Related Solutions

A toy cannon uses a spring to project a 5.20-g soft rubber ball. The spring is...
A toy cannon uses a spring to project a 5.20-g soft rubber ball. The spring is originally compressed by 5.03 cm and has a force constant of 8.08 N/m. When the cannon is fired, the ball moves 15.6 cm through the horizontal barrel of the cannon, and the barrel exerts a constant friction force of 0.032 1 N on the ball. (a) With what speed does the projectile leave the barrel of the cannon? (b) At what point does the...
A toy cannon uses a spring to project a 5.38-g soft rubber ball. The spring is...
A toy cannon uses a spring to project a 5.38-g soft rubber ball. The spring is originally compressed by 4.91 cm and has a force constant of 8.08 N/m. When the cannon is fired, the ball moves 15.6 cm through the horizontal barrel of the cannon, and the barrel exerts a constant friction force of 0.032 6 N on the ball. (a) With what speed does the projectile leave the barrel of the cannon? m/s (b) At what point does...
A toy cannon uses a spring to project a 5.39-g soft rubber ball. The spring is...
A toy cannon uses a spring to project a 5.39-g soft rubber ball. The spring is originally compressed by 5.04 cm and has a force constant of 8.10 N/m. When the cannon is fired, the ball moves 15.6 cm through the horizontal barrel of the cannon, and the barrel exerts a constant friction force of 0.032 5 N on the ball. (a) With what speed does the projectile leave the barrel of the cannon? m/s (b) At what point does...
26. A toy cannon uses a spring to project a 5.34 g soft rubber ball. The...
26. A toy cannon uses a spring to project a 5.34 g soft rubber ball. The spring is originally compressed by 5.08 cm and has a force constant of 8.09 N/m. When the cannon is fired, the ball moves 15.1 cm through the horizontal barrel of the cannon, and there is a constant frictional force of 0.0318 N between the barrel and the ball. (a) With what speed does the projectile leave the barrel of the cannon? m/s (b) At...
When it comes to a project, if a project manager were to pad their time when...
When it comes to a project, if a project manager were to pad their time when creating our schedule are we being unethical? Where do we draw the line?
At the beginning of 2019, Dr. John opened his medical practice as a personal service corporation....
At the beginning of 2019, Dr. John opened his medical practice as a personal service corporation. The entity uses a December 31 year-end and the accrual method of accounting. During the year, the corporation billed patients and insurance companies for $485,000 for medical services. At the end of the year, $60,000 of this amount had not been collected. The entity earned $1,500 interest on a money market account held in the local bank and another $1,500 interest on an investment...
On May 31, 2019, Teri Corporation sold spring floral arrangements for $27,000 (on account). Teri paid...
On May 31, 2019, Teri Corporation sold spring floral arrangements for $27,000 (on account). Teri paid $12,000 to acquire the flowers from a wholesaler. Which of the entries will be made on May 31, 2019? A. Debit Cost of Goods Sold $12,000; Credit Inventory $12,000 B. Debit Cash $27,000; Credit Sales Revenue $27,000 C. Debit Accounts Receivable $27,000; Credit Unearned Revenue $27,000 D. Debit Cost of Goods Sold $12,000; Credit Revenue $27,000 ___________________________________________________________________________ Manny Corporation (“Manny”) has the following information...
Staffing a Project Team. What problems or obstacles may be encountered by the project manager when...
Staffing a Project Team. What problems or obstacles may be encountered by the project manager when attempting to staff his or her project team? Offer 2-3 problems or issues that may be experienced when staffing a project and provide a recommendation for managing and resolving the issue. What issues have you encountered and how were they responded to?
Corporation A plans to launch a new project and the financial manager is considering whether this...
Corporation A plans to launch a new project and the financial manager is considering whether this is a valuable investment for the corporation. Consider: The initial cost of this project is $197.92, and it offers cash flows in the next 3 years, with an estimated cash flow of $ 50 in the first year, $100 in the second year and $150 in the third year. Questions: 1. What is the Internal Rate of Return (IRR) of this project? 2. If...
5) A project manager at System Design Corporation has collected the following data on the size...
5) A project manager at System Design Corporation has collected the following data on the size of software programs and the length of programming time. The company is bidding on a new system that is estimated to consist of 300,000 lines of code. Use a scatter plot to find the correlation function of coding time to the program size and estimate the number of days it would take to code the system. Module Size in 1000 lines of code Number...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT