Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic...

Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic centimeters (cc) of solvent H300 are required to manufacture each unit of Supermix, one of the company’s products. The company now is planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following inventory requirements:

  1. The finished goods inventory on hand at the end of each month must equal 4,000 units of Supermix plus 25% of the next month’s sales. The finished goods inventory on June 30 is budgeted to be 18,250 units.

  2. The raw materials inventory on hand at the end of each month must equal one-half of the following month’s production needs for raw materials. The raw materials inventory on June 30 is budgeted to be 87,375 cc of solvent H300.

  3. The company maintains no work in process inventories.

A monthly sales budget for Supermix for the third and fourth quarters of the year follows.

Budgeted Unit Sales
July 57,000
August 62,000
September 72,000
October 52,000
November 42,000
December 32,000

Required:

1. Prepare a production budget for Supermix for the months July, August, September, and October.

3. Prepare a direct materials budget showing the quantity of solvent H300 to be purchased for July, August, and September, and for the quarter in total.

Require 1) prepare a production budget for Supermix for the months July, August, September, and October.

Pearl Products Limited
Production Budget
July August September October
Budgeted unit sales 57,000 22,000 17,000 14,500
Add: Desired units of ending finished goods inventory
Total needs
Less: Units of beginning finished goods inventory
Required production in units

Required 3) Prepare a direct materials budget showing the quantity of solvent H300 to be purchased for July, August, and September, and for the quarter in total.

Pearl Products Limited
Direct Materials Budget
July August September Third Quarter
Estimated sales in units of finished goods
Units of raw materials needed per unit of finished goods cc cc cc cc
Units of raw materials needed to meet production
Total units of raw materials needed
Units of raw materials to be purchased

Solutions

Expert Solution

PRODUCTION BUDGET
July Aug Sep Oct
Budgeted Sales Units 57,000 62,000 72,000 52,000
Add: Desired Ending Finished inventory 19,500 22,000 17,000 14,500 (42000*25%+4000)
Total Needs 76,500 84,000 89,000 66,500
Less: Beginning Finished Inventory 18,250 19,500 22,000 17,000
Required Production in units 58,250 64,500 67,000 49,500
RAW MATERIAL PURCHASE BUDGET
July Aug Sep Q-3 Oct
Budgeted Production units 58,250 64,500 67,000 1,89,750 49,500
RM required per unit 3 3 3 3 3
Total RM requiremnt 1,74,750 1,93,500 2,01,000 5,69,250 1,48,500
Add: Desired Ending Inventory 96,750 1,00,500 74,250 74,250
Total needs 2,71,500 2,94,000 2,75,250 6,43,500
Less: Beginning Inventory 87,375 96,750 1,00,500 87,375
Purchase Units 1,84,125 1,97,250 1,74,750 5,56,125

Related Solutions

Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic...
Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic centimeters (cc) of solvent H300 are required to manufacture each unit of Supermix, one of the company’s products. The company now is planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following inventory requirements: The finished goods inventory on hand at the end of each...
Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic...
Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic centimeters (cc) of solvent H300 are required to manufacture each unit of Supermix, one of the company’s products. The company now is planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following inventory requirements: The finished goods inventory on hand at the end of each...
Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic...
Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic centimeters (cc) of solvent H300 are required to manufacture each unit of Supermix, one of the company’s products. The company now is planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following inventory requirements: The finished goods inventory on hand at the end of each...
Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic...
Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic centimeters (cc) of solvent H300 are required to manufacture each unit of Supermix, one of the company’s products. The company now is planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following inventory requirements: The finished goods inventory on hand at the end of each...
Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic...
Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic centimeters (cc) of solvent H300 are required to manufacture each unit of Supermix, one of the company’s products. The company is now planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following inventory requirements: a. The finished goods inventory on hand at the end of...
Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic...
Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic centimeters (cc) of solvent H300 are required to manufacture each unit of Supermix, one of the company’s products. The company now is planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following inventory requirements: The finished goods inventory on hand at the end of each...
Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic...
Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic centimeters (cc) of solvent H300 are required to manufacture each unit of Supermix, one of the company’s products. The company now is planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following inventory requirements: The finished goods inventory on hand at the end of each...
Pearl Products Limited of Shenzhen China manufactures and distributes toys throughout South East Asia. Three cubic...
Pearl Products Limited of Shenzhen China manufactures and distributes toys throughout South East Asia. Three cubic centimeters (cc) of solvent H300 are required to manufacture each unit of Supermix, One of the company's products. The company now is planning raw materials needs for the third quarter, the quarter in which peak sales of supermix occur. To keep production and sales moving smoothly, the company has the following inventory requirements: a. The Finished goods inventrory on hand at the end of...
Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic...
Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic centimeters (cc) of solvent H300 are required to manufacture each unit of Supermix, one of the company’s products. The company now is planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following inventory requirements: The finished goods inventory on hand at the end of each...
Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic...
Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic centimeters (cc) of solvent H300 are required to manufacture each unit of Supermix, one of the company’s products. The company is now planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following inventory requirements: a. The finished goods inventory on hand at the end of...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT