Question

In: Accounting

The Following information relates to contract #102,which was undertaken for the construction of a railway bridge...

The Following information relates to contract #102,which was undertaken for the construction of a railway bridge for the Kampton Council.The Value of the contract is $250000 and it is at a stage where profits can be attributed to it.Details of the contract are shown in the books:

                                                                                                                                                     $

                                                                            Materials sent to site                                        85349

                                                                           Labour engaged on site                                      74375

                                                                         Plant installed at cost                                           15000

                                                                         Direct expenditure                                                  4136

                                                                         General Overhead Charges                                      3167

                                                                          Materials returned to store                                      549

                                                                          Work certified                                                       195000

                                                                          Cost of Work not certified                                       4500

                                                                          Materials on hand,December 31                            1883

                                                                          Wages accrued on December 31                           2400

                                                                          Direct Expenditure                                                240

                                                                          Value of Plant December 31                                  11000

Cash has been received from the contractee,amounting to $180000

Required: (i)contract Account

              (ii) profit and loss account

              (iii)contractee accounts

Solutions

Expert Solution

PART (i):

Contract #102 Account for the year ending 31st Dec.

Particulars Amount Particulars Amount
To Materials sent to site 85349 By Materials (Return to store) 549
To Labour 74375 By Material in Hand 1883
To Plant at site 15000 By Plant at Site 11000
To Direct expenses 3167

By Work In Progress

Work Certified- 195000

Work Uncertified- 4500

199500
To Establishment charges 4136
To Wages Accrued 2400
To Direct Expenses Accrued 240
To NOTIONAL PROFIT C/D 28265
212932 212932
To Profit And Loss Account (Refer W.N. 1) 17394 By NOTIONAL PROFIT B/D 28265
To Balance C/D(RESERVE) 10871

W.N. 1

Proportion of profit transferred to Profit and Loss Account has been calculated by the following formula:

Notional profit × 2/3 × Cash received/Work certified

28,265 × 2/3 × 180000/195000 = 17,400

PART (ii):

Profit and Loss Account

Particulars Amount Particulars Amount
By #102 Contract Account 17394

PART (iii)

#102 Contractee’s Account

Particulars Amount Particulars Amount
To Balance C/D 180000 By Cash 180000
180000 180000

Related Solutions

In 2021, the Westgate Construction Company entered into a contract to construct a bridge for $12,000,000....
In 2021, the Westgate Construction Company entered into a contract to construct a bridge for $12,000,000. The bridge was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year    $1,840,000 $3,760,000 $4,500,000 Estimated costs to complete as of year-end $6,160,000 $5,600,000 $0 Billings during the year $3,000,000 $4,000,000 $5,000,000 Cash collections during thee year    $2,600,000 $3,900,000    $5,100,000 a. Westgate recognizes revenue over time according to percentage of completion....
In 2021, the Westgate Construction Company entered into a contract to construct a bridge for $12,000,000....
In 2021, the Westgate Construction Company entered into a contract to construct a bridge for $12,000,000. The bridge was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year    $1,840,000 $3,760,000 $4,500,000 Estimated costs to complete as of year-end $6,160,000 $5,600,000 $0 Billings during the year $3,000,000 $4,000,000 $5,000,000 Cash collections during thee year    $2,600,000 $3,900,000    $5,100,000 a. Westgate recognizes revenue over time according to percentage of completion....
You are trying to decide whether to bid on a construction contract for a new bridge...
You are trying to decide whether to bid on a construction contract for a new bridge in South Carolina. You think that it will take 36 months to build and that construction costs will be $2 million per month. You expect tolls to be $10 million per year once the bridge opens, which will be offset by toll collection and maintenance costs of $2 million per year. Your (minimally acceptable rate of return) MARR is 15% per year. To bid...
Required information    In 2018, the Westgate Construction Company entered into a contract to construct a...
Required information    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,156,000 $ 3,388,000 $ 2,371,600 Estimated costs to complete as of year-end 5,544,000 2,156,000 0 Billings during the year 2,130,000 3,414,000 4,456,000 Cash collections during the year 1,865,000 3,300,000 4,835,000 Westgate recognizes revenue over...
Required information    In 2018, the Westgate Construction Company entered into a contract to construct a...
Required information    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,156,000 $ 3,388,000 $ 2,371,600 Estimated costs to complete as of year-end 5,544,000 2,156,000 0 Billings during the year 2,130,000 3,414,000 4,456,000 Cash collections during the year 1,865,000 3,300,000 4,835,000 Westgate recognizes revenue over...
The following information relates to two companies which trade in a Modigliani and Miller world:
Question 2: Capital structure and dividend policy.          The following information relates to two companies which trade in a Modigliani and Miller world: Sanlam                          Santam Cost of equity 20% 18% Cost of debt 12% - Dividends 200 000 432 000 Interest 150 000 - Shares 1000 1000 Suppose Sanlam ltd wishes to finance a major restructuring project whose total cost is N$75 Million. The company follows a residual policy on dividends. Earnings for the coming year are...
The following information relates to Kate Company
  The following information relates to Kate Company Beginning inventory    150 units at $2 each Purchases                 450 units at $5 each At the end of the period , Kate had 190 units left in inventory. Kate sold the remaining units for $24 each. How many units did Kate have available for sale? 150+450-190 IS WRONG   On December 31, 2017, Extreme Fitness has adjusted balances of $80,580 in Accounts Receivable and $2,564 in Allowance for Doubtful Accounts. Assume that on...
Required information In 2018, the Westgate Construction Company entered into a contract to construct a road...
Required information In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,156,000 $ 3,388,000 $ 2,371,600 Estimated costs to complete as of year-end 5,544,000 2,156,000 0 Billings during the year 2,130,000 3,414,000 4,456,000 Cash collections during the year 1,865,000 3,300,000 4,835,000 Westgate recognizes revenue over time...
Required information In 2018, the Westgate Construction Company entered into a contract to construct a road...
Required information In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,156,000 $ 3,388,000 $ 2,371,600 Estimated costs to complete as of year-end 5,544,000 2,156,000 0 Billings during the year 2,130,000 3,414,000 4,456,000 Cash collections during the year 1,865,000 3,300,000 4,835,000 Westgate recognizes revenue over time...
Long‐term contract based on percentage of completion method Jim’s Construction Co. has a $6,800,000 contract which...
Long‐term contract based on percentage of completion method Jim’s Construction Co. has a $6,800,000 contract which began on January 1, 2015 to build a new football stadium with an expected completion date of October 31, 2017. The following table provides information gathered during the construction period. Jim uses the percentage completion method to account for this contract.                                                                                                                                  2015 2016 2017 Construction costs incurred during the year 2,040,000 2,932,500 1,657,500 Estimated costs to complete 3,060,000 1,657,500 0 Billings during the...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT