Question

In: Finance

Unilate’s required rate of return is 10%. Assume that you are confident about the estimates of...

Unilate’s required rate of return is 10%.

Assume that you are confident about the estimates of all the variables that affect the project’s cash flows except unit sales. If product acceptance is poor, sales would be only 75,000 units a year, whereas a strong consumer response would produce sales of 125,000 units. In either case, cash costs would still amount to 60% of revenues. You believe that there is a 25% chance of poor acceptance, a 25% chance of excellent acceptance, and a 50% chance of average acceptance (the base case).

(1) What is the worst-case NPV? The best-case NPV?

(2) Use the worst-case, most likely (or base) case, and best-case NPVs and probabilities of occurrence to find the project’s expected NPV, standard deviation (σNPV), and coefficient of variation (CVNPV).

(3) Discuss how one would perform a sensitivity analysis on the unit sales, salvage value, and required rate of return for the project. Assume that each of these variables deviates from its base-case, or expected, value by plus and minus 10, 20, and 30%.

(4) How would you calculate the NPV, IRR, and the payback for each case?

Year

0

1

2

3

4

Investment in:

   Equipment cost

-240

Newt Working capital

20

Unit sales (Thousand)

100

100

100

100

Price / Unit Dollars

$2.10

$2.205

$2.315

$2.431

Total revenue

$210.0

$220.5

$231.5

$243.1

Depreciation

-79.2

-108

-6

-16.8

Cash operating costs (60%)

-126

-132.3

-138.9

145.9

Earning before taxes (EBT)

4.8

-19.8

56.5

80.4

Taxes (40%)

-1.9

7.9

-22.6

-32.2

Net income

2.9

-11.9

34

48.2

Plus Depreciation

79.2

108

36

16.8

Net operating CF

82.1

96.1

70

65

Salvage value

25

Tax on salvage value (40%)

-10

Recovery of NWC

20

Net cash flow

260

82.1

96.1

70

100

Cumulative CD for paycheck

-260

-177.9

-81.8

-11.8

88.2

NVP

$15

IRR

12.60%

Solutions

Expert Solution

1) We used a spreadsheet model to develop the scenarios (in thousands of dollars), which are summarized below:

                          Case           Probability      NPV (000s)

                          Worst                0.25              ($27.8)

                           Base                 0.50                 15.0

                            Best                 0.25                 57.8

2)

The expected NPV is $14,968 (rounded to the nearest thousand below).

E(NPV) = 0.25(-$27.8) + 0.50($15.0) + 0.25($57.8) = $15.

The standard deviation of NPV is $30.3:

sNPV = [0.25(-$27.8 – $15)2 + 0.50($15 – $15)2+ 0.25($57.8 – $15)2]½

        = [916]½ = $30.3,

and the project's coefficient of variation is 2.0:

CVNPV = Stdev NPV/E(NPV) = 30.3/15 = 2

3) The base case value for unit sales was 100; therefore, if you were to assume that this value deviated by plus and minus 10%, 20%, and 30%, the unit sales values to be used in the sensitivity analysis would be 70, 80, 90, 110, 120, and 130 units. You would then go back to the table at the beginning of the problem, insert the appropriate sales unit number, say 70 units, and rework the table for the change in sales units arriving at different net cash flow values for the project. Once you had the net cash flow values, you would calculate the NPV, IRR, MIRR, and payback as you did previously. (Note that sensitivity analysis involves making a change to only one variable to see how it impacts other variables.) Then, you would go back and repeat the same steps for 80 units—this would be done for each of the unit sales values. Then, you would repeat the same procedure for the sensitivity analysis on salvage value and on cost of capital. (Note that for the cost of capital analysis, the net cash flows would remain the same, but the cost of capital used in the NPV and MIRR calculations would be different.)

Excel® is ideally suited for sensitivity analysis. In fact we created a spreadsheet to obtain this project’s net cash flows and its NPV, IRR, MIRR, and payback. Once a model has been created, it is very easy to change the values of variables and obtain the new results. The results of the sensitivity analysis on the project's NPV (for the 5% inflation case, using Table IC 12-2) assuming the plus and minus 10%, 20%, and 30% deviations are shown below.

We generated these data with a spreadsheet model.

1.    The sensitivity lines intersect at 0% change and the base case NPV, at approximately $15,000. Since all other variables are set at their base case, or expected, values, the zero change situation is the base case.

2.    The plots for unit sales and salvage value are upward sloping, indicating that higher variable values lead to higher NPVs. Conversely, the plot for WACC is downward sloping, because a higher WACC leads to a lower NPV.

3.    The plot of unit sales is much steeper than that for salvage value. This indicates that NPV is more sensitive to changes in unit sales than to changes in salvage value.

4.    Steeper sensitivity lines indicate greater risk. Thus, in comparing two projects, the one with the steeper lines is considered to be riskier.

The sensitivity data are given here in tabular form (in thousands of dollars):

Change from              Resulting NPV after the Indicated Change in:

    Base Level                      Unit Sales     Salvage Value      WACC      

        -30%                          ($36.4)               $11.9             $34.1

        -20                                (19.3)                 12.9               27.5

        -10                                  (2.1)                 13.9               21.1

           0                                 15.0                  15.0               15.0

       +10                                 32.1                  16.0                 9.0

       +20                                 49.2                  17.0                 3.3

       +30                                 66.3                  18.0               (2.2)

4) The NPV, IRR and Payback can be calculated using the values generated and the excel function for NPV, IRR and payback.


Related Solutions

Assume that the risk-free rate is 2.5% and the required return on the market is 10%....
Assume that the risk-free rate is 2.5% and the required return on the market is 10%. What is the required rate of return on a stock with a beta of 2.1? Round your answer to two decimal places.
Assume that the risk-free rate of return (Krf) is 3% and the required rate of return...
Assume that the risk-free rate of return (Krf) is 3% and the required rate of return on the market (Km) is 8%. A given stock, say, Caterpillar (CAT) has a beta coefficient of 1.03. If the dividend per share during the coming year, meaning D1, is $4.12 and g = 3.50%, what is the current intrinsic value of the stock? Exactly how much was D0? How long will it take for the dividend to double, given the growth rate, approximately?...
How much "error" is too much before you are no longer confident about your estimates or...
How much "error" is too much before you are no longer confident about your estimates or research findings? Do sampling methods have anything to do with this? Discuss.
Assume that your required rate of return is eight percent and you are given the following...
Assume that your required rate of return is eight percent and you are given the following stream of cash flows: Year Cash Flow 1 $434 2 $696 3 $767 4 $646 5 $862 6 $397 If payments are made at the end of each period, what is the present value of the cash flow stream? Select one: a. $2,809.88 b. $2,668.92 c. $42,344.29 d. $34,434.92 e. $2,919.10
You are informed that the effective annual required rate of return is 10%. Cash flows for...
You are informed that the effective annual required rate of return is 10%. Cash flows for the projects are indicated in the table below (in thousands of dollars): Year 0 1 2 3 A -1,800 600 1,00 1,200 B 12,000 -600   -10,800 -5,000 For the following problems, show all your work (i.e. express al formulas used with values in place of variables). a) Consider Project A and Project B independent projects. Calculate the internal rate of return (IRR) for Project...
4)   Assume that your required rate of return is 12 percent and you are given the following...
4)   Assume that your required rate of return is 12 percent and you are given the following stream of cash flows: Year                  Cash Flow 0                     $10,000 1                     $15,000 2                     $15,000 3                     $15,000 4                     $15,000 5                     $20,000 If payments are made at the end of each period, what is the present value of the cash flow stream? A. $66,909 B. $57,323 C. $61,815 D. $52,345 show how to calculate it by financial calculator
Assume that the risk-free rate is 3% and the required return on the market is 9%....
Assume that the risk-free rate is 3% and the required return on the market is 9%. What is the required rate of return on a stock with a beta of 2.2? Round your answer to two decimal places.
Assume that Techtron is a constant growth company with a required rate of return of 13...
Assume that Techtron is a constant growth company with a required rate of return of 13 percent whose last dividend (D0, which was paid yesterday) was $2.00, and whose dividend is expected to grow indefinitely at a 5 percent rate. a. What is the firm’s expected dividend stream over the next 3 years?                          b. What is the firm’s current stock price? c. What is the stock's expected value 1 year from now?             d. What are the expected dividend yield, the...
Assume that the risk-free rate is 4.5% and the required return on the market is 8%....
Assume that the risk-free rate is 4.5% and the required return on the market is 8%. What is the required rate of return on a stock with a beta of 2? Round your answer to two decimal places.
 Assume the​ following: • the​ investor's required rate of return is 18 ​percent, • the expected...
 Assume the​ following: • the​ investor's required rate of return is 18 ​percent, • the expected level of earnings at the end of this year ​(E1​) is ​$9​, • the retention ratio is 55 ​percent, • the return on equity ​(ROE​) is 19 percent​ (that is, it can earn 19 percent on reinvested​ earnings), and • similar shares of stock sell at multiples of 5.960 times earnings per share. QUESTIONS: a.  What is the expected growth rate for​ dividends? (?)​%...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT