In: Accounting
Becton Labs, Inc., produces various chemical compounds for industrial use. One compound, called Fludex, is prepared using an elaborate distilling process. The company has developed standard costs for one unit of Fludex, as follows:
Standard Quantity or Hours |
Standard Price or Rate |
Standard Cost | |||||
Direct materials | 2.20 | ounces | $ | 16.00 | per ounce | $ | 35.20 |
Direct labor | 0.80 | hours | $ | 12.00 | per hour | 9.60 | |
Variable manufacturing overhead | 0.80 | hours | $ | 2.50 | per hour | 2.00 | |
Total standard cost per unit | $ | 46.80 | |||||
During November, the following activity was recorded related to the production of Fludex:
There was no beginning inventory of materials; however, at the end of the month, 3,100 ounces of material remained in ending inventory.
The company employs 23 lab technicians to work on the production of Fludex. During November, they each worked an average of 150 hours at an average pay rate of $11.00 per hour.
Variable manufacturing overhead is assigned to Fludex on the basis of direct labor-hours. Variable manufacturing overhead costs during November totaled $4,200.
During November, the company produced 3,500 units of Fludex.
Required:
1. For direct materials:
a. Compute the price and quantity variances.
b. The materials were purchased from a new supplier who is anxious to enter into a long-term purchase contract. Would you recommend that the company sign the contract?
2. For direct labor:
a. Compute the rate and efficiency variances.
b. In the past, the 23 technicians employed in the production of Fludex consisted of 7 senior technicians and 16 assistants. During November, the company experimented with fewer senior technicians and more assistants in order to reduce labor costs. Would you recommend that the new labor mix be continued?
3. Compute the variable overhead rate and efficiency variances.
1a) | |||
Materials price variance = AQ (AP – SP) | |||
11000 ounces ($14.6 per ounce* – $16.00 per ounce) = -15400 F | 15400 | F | |
*$160,600 ÷ 11,000 ounces = $14.6 per ounce | |||
Materials quantity variance = SP (AQ – SQ) | |||
$16.00 per ounce (7900 – 7000* ounces) = $14400 | 14400 | U | |
*3500 units x 2 ounces = 7000 ounces | |||
^ 11000-3100(inventory at the end)=7900 | |||
Materail Price Variance | $15,400 | F | |
Material quantity Variance | $14,400 | U | |
1b) | |||
Yes | |||
2a) | |||
Labor rate variance = AH (AR – SR) | |||
3450 hours ($11 per hour – $12.00 per hour) = $3450 F | |||
Labor efficiency variance = SR (AH – SH) | |||
$12.00 per hour (3450 hours – 3,150 hours) = $3600 | |||
actual | 150*23 | 3450 | |
standard | 3500*0.9 | 3150 | |
Labour Rate Variance | $3,450 | F | |
Labour efficiency variance | $3,600 | U | |
2b) | |||
No | |||
3) | |||
Variable overhead spending variance = AH (AR – SR) | |||
3450 hours ($1.13 per hour* – $2.50 per hour) = $4726.5 F | |||
*$4200÷ 3450hours = $1.13 per hour | |||
Variable overhead efficiency variance = SR (AH – SH) | |||
$2.50 per hour (3450 hours – 3150 hours) = $750 U | |||
Variable overhead rate variance | $4,727 | F | |
Variable overhead efficiency variance | $750 | U |