Question

In: Chemistry

A water treatment plant has 6 settling tanks that operate in parallel (the flow gets split...

A water treatment plant has 6 settling tanks that operate in parallel (the flow gets split into six equal flow streams), and each tank has a volume of 600m^3. If the flow to the plant is 10mgd, what is the retention time in each of the settling tanks? If, instead, the tanks operated in series (the entire flow goes first through one tank, then the second, and so on), what would be the retention time in each tank?

Solutions

Expert Solution

mgd stands for million gallons per day

Now 1 mgd will be 3785.4 m3/day

so 10 mgd will be 37854 m3/day

6 settling tanks each of volume 600 m3

So total settling volume is 3600 m3

a) So as per this the input low is 37854 m3/day this is split into 6 streams so each stream is

37854 m3/6 = 6309 m3/day which is 6309/24 = 262.875 m3/hr when it goes to a tank of capacity 600 m3

The filling time will be 600 m3/262.875 m3/hr = 2.28 Hr. But since the flow is continous after it is filled it has to be immediately entied to be filled again.

So the retention times after filling in each tank will be 0

b) Now the entire flow is 37854 m3/day or 1577.25 m3/Hr

So each tank of capacity 600 m3 gets filled in 600 m3/1577.25 m3/Hr = 0.38 Hr.

going from one tank to th next it takes 0.38 Hr x 6 to fill 6 tanks that is 2.28 Hr to fill 6 tanks before it returns to the first.

So the settling time in each tank after it is filled will be 2.28 Hr. - 0.38 Hr = 1.48 Hr


Related Solutions

A water treatment plant has three identical horizontal shaft flocculation tanks. Each tank is composed of...
A water treatment plant has three identical horizontal shaft flocculation tanks. Each tank is composed of three stages with size of 4 m depth, 14.1 m length and 15 m width. G value of each stage is 40 s-1, 30 s-1 and 20 s-1. Mean water temperature is 15°C (μ = 1.139×10-3). What are the power requirements for flocculation stages in a single flocculation tank. And Is the flocculation tank in an efficient way? ( Plant's average flow rate of...
A water treatment plant is designed for a constant flow rate of 3 MGD. The flocculation...
A water treatment plant is designed for a constant flow rate of 3 MGD. The flocculation system consists of three tanks, each having a water depth of 10 ft and an average hydraulic residence time (HRT) of 30 min.    (a) Determine the dimension of each tank (i.e., width and length). (b) Determine whether the flow through velocity is acceptable. (c) The plant is planning to take one tank out of service for maintenance. Determine the increase in power requirement...
The Iowa City Water Treatment Plant and the University of Iowa Water Treatment Plant remove calcium...
The Iowa City Water Treatment Plant and the University of Iowa Water Treatment Plant remove calcium hardness (Ca2+) by precipitating (making) CaCO3(s). If, after establishing equilibrium with CaCO3(s), the dissolved Ca2+ concentration is 10 mg/L and the pH is 10.5. a. What is the CO32- concentration in mol/L? b. What is the HCO3- concentration in mol/L? c. What is the alkalinity in mg/L as CaCO3?
The Water Treatment Plant and the University Water Treatment Plant remove calcium hardness (Ca2+) by precipitating...
The Water Treatment Plant and the University Water Treatment Plant remove calcium hardness (Ca2+) by precipitating (making) CaCO3(s). If, after establishing equilibrium with CaCO3(s), the dissolved Ca2+ concentration is 10 mg/L and the pH is 10.5. a. What is the CO32- concentration in mol/L? b. What is the HCO3- concentration in mol/L? c. What is the alkalinity in mg/L as CaCO3?
Design rapid sand filters for a water treatment plant to treat a flow rate of 25...
Design rapid sand filters for a water treatment plant to treat a flow rate of 25 mgd. Use 1.5 for a peak factor. Consider the location of overflow troughs, freeboard, and pressure head of water. Assume that the length of the filters is 2 times the width and that the filtration rate is 3 gpm/ft2. Assume anthracite over sand with 1 ft gravel under media, top of water level during filtration is below troughs, and a 3 ft head drop...
Two large tanks are connected by two pipes of different size in parallel. Water temperature is...
Two large tanks are connected by two pipes of different size in parallel. Water temperature is 20°C. The surface water elevation in the upstream reservoir (Reservoir I) is 175m. The length of each pipe is 1250 m, and other properties are specified in the following: Pipe A: diameter 0.5m, and frictional factor 0.025; Pipe B: diameter 0.25m, the frictional factor is not given, but relative roughness is 0.006 under the flow condition observed. Flow velocity in Pipe A is 2m/s....
A wastewater treatment plant has a rupture in one of their flow tubes, thereby leading to...
A wastewater treatment plant has a rupture in one of their flow tubes, thereby leading to the discharge of waste material into a local lake system. The rupture goes unnoticed for a long enough time that the concentration of the waste in the lake reaches a steady state. Assume that the lake can be modeled as a continuously stirred tank reactor, with inflow, outflow, and complete mixing, and that the lake flows so that the volume remains constant at 107...
Suppose that a city has to justify the net benefits of a proposed water treatment plant....
Suppose that a city has to justify the net benefits of a proposed water treatment plant. (A) Name and discuss the importance of the four things that the City must consider in terms of estimating the Present Value of Net Benefits (PVNB). (B) Calculate the PVNB’s from the following information: Year​ 0 ​1​ 2​ 3​ 4​ 5​ 6​ Cost​ 100 ​ 50​ 30​ 20​ 20​ 10​ 10​​ Benefit​ 10​ 20 ​20​ 40​ 100​ 120​ 150​ (i) PVNB (@ 4%) =...
Q4. You are working in a waste water treatment plant, once your treatment plant receives sewage...
Q4. You are working in a waste water treatment plant, once your treatment plant receives sewage water with more colloidal or dissolved organic materials. As an Engineer what type of treatment will you prefer for this sewage water? Justify and explain the method selected by you.
The total flow at a wastewater treatment plant is 682 m3/day. The purpose of the plant...
The total flow at a wastewater treatment plant is 682 m3/day. The purpose of the plant is to remove compound Z from the wastewater by treating it in reactors, using a newly developed microbial process. Assume the microbial treatment can be modeled as a first order reaction with a rate coefficient of 0.36/h. Suppose the flow is split evenly and treated in two parallel reactors– one complete mix and one plug flow -- each with a volume of 88 x...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT