Question

In: Accounting

QualCo manufactures a single product in two departments: Cutting and Assembly. During May, the Cutting department completed a number of units of a product and transferred them to Assembly.


QualCo manufactures a single product in two departments: Cutting and Assembly. During May, the Cutting department completed a number of units of a product and transferred them to Assembly. Of these transferred units, 38,100 were in process in the Cutting department at the beginning of May and 156,500 were started and completed in May. May’s Cutting department beginning inventory units were 70% complete with respect to materials and 30% complete with respect to conversion. At the end of May, 51,900 additional units were in process in the Cutting department and were 70% complete with respect to materials and 20% complete with respect to conversion. The Cutting department had $510,650 of direct materials and $425,810 of conversion cost charged to it during May. Its beginning inventory included $74,675 of direct materials cost and $29,093 of conversion cost.

1. Compute the number of units transferred to Assembly.

2.Using the FIFO method, assign May’s costs to the units transferred out and assign costs to its ending work in process inventory. (Round "Cost per EUP" to 2 decimal places.)

Solutions

Expert Solution

1.

Number of units transferred to Assembly:

Units in beginning work in process 38,100
Units started and completed in May 156,500
Total number of units transferred to Assembly 194,600

2.

Equivalent units
Whole units Direct material Conversion
Units in beginning work in process 38,100 11,430 (38,100*30%) 26,670 (38,100*70%)
Units started and completed 156,500 156,500 156,500
Units in ending work in process 51,900 36,330 (51,900*70%) 10,380 (51,900*20%)
Total equivalent units 204,260 193,550
Direct material Conversion
Cost charged during May $510,650 $425,810
Total equivalent units 204,260 193,550
Cost per equivalent unit $2.5 $2.2

Cost of units transferred out

Cost of beginning work in process:
Beginning balance $103,768
Add: Cost incurred to complete $28,575 (11,430*$2.5)+$58,674 (26,670*$2.2) 87,249 $191,017
Cost of units started and completed:
Direct material (156,500*$2.5) $391,250
Conversion (156,500*$2.2) 344,300 735,550
Total cost of units transferred out $926,567

Cost of ending work in process:

Direct material (36,330*$2.5) $90,825
Conversion (10,380*$2.2) 22,836
Total cost of ending work in process $113,661

Related Solutions

QualCo manufactures a single product in two departments: Cutting and Assembly. During May, the Cutting department...
QualCo manufactures a single product in two departments: Cutting and Assembly. During May, the Cutting department completed a number of units of a product and transferred them to Assembly. Of these transferred units, 37,700 were in process in the Cutting department at the beginning of May and 153,800 were started and completed in May. May’s Cutting department beginning inventory units were 70% complete with respect to materials and 30% complete with respect to conversion. At the end of May, 51,500...
THE Company operates two departments, the assembly department and the shipping department. During May, the assembly...
THE Company operates two departments, the assembly department and the shipping department. During May, the assembly department reported the following information: % complete % complete units DM conversion work in process, May 1 46,000 55% 39% units started during May 68,000 work in process, May 31 23,000 60% 75% The cost of beginning work in process and the costs added during May were as follows: DM Conversion work in process, May 1 $ 62,880 $ 75,775 costs incurred during May...
THE Company operates two departments, the assembly department and the shipping department. During May, the assembly...
THE Company operates two departments, the assembly department and the shipping department. During May, the assembly department reported the following information: % complete % complete units DM conversion work in process, May 1 46,000 45% 59% units started during May 68,000 work in process, May 31 23,000 75% 60% The cost of beginning work in process and the costs added during May were as follows: DM Conversion work in process, May 1 $ 60,620 $ 75,775 costs incurred during May...
Cutting Department and Assembly Department are two departments in Ideal AA Garment that are considering operating...
Cutting Department and Assembly Department are two departments in Ideal AA Garment that are considering operating a machine together. The operating cost of each 1 department to operate the machine on its own is RM36,000 for Cutting Department and RM24,000 for Assembly Department. If they operate the machine together, the operating cost will decrease to RM48,000. a. Calculate Cutting Department and Assembly Department respective share of operating cost under the stand-alone cost-allocation. b. Calculate Cutting Department and Assembly Department using...
Carlberg Company has two manufacturing departments, assembly and painting. The assembly department started 12,100 units during...
Carlberg Company has two manufacturing departments, assembly and painting. The assembly department started 12,100 units during November. The following production activity unit and cost information refers to the assembly department’s November production activities. Assembly Department Units Percent of Direct Materials Percent of Conversion Beginning work in process 3,500 60 % 40 % Units transferred out 10,500 100 % 100 % Ending work in process 5,100 80 % 30 % Beginning work in process inventory—Assembly dept $ 3,359 (consists of $1,902...
During the period, the mixing department completed 500 units and transferred then out to the baking...
During the period, the mixing department completed 500 units and transferred then out to the baking department. at the end of the period there were 4000.00 units that are 40% complete as to direct material in the mixing department. the equivalent units of production for direct materials equal
The Carlberg Company has two manufacturing departments, assembly and painting. The assembly department started 10,000 units...
The Carlberg Company has two manufacturing departments, assembly and painting. The assembly department started 10,000 units during November. The following production activity unit and cost information refers to the assembly department’s November production activities. Assembly Department Units Percent of Direct Materials Added Percent of Conversion Beginning work in process 2,000 60 % 40 % Units transferred out 9,000 100 % 100 % Ending work in process 3,000 80 % 30 % Beginning work in process inventory—Assembly dept $ 1,581 (includes...
The Carlberg Company has two manufacturing departments, assembly and painting. The assembly department started 11,400 units...
The Carlberg Company has two manufacturing departments, assembly and painting. The assembly department started 11,400 units during November. The following production activity unit and cost information refers to the assembly department’s November production activities. Assembly Department Units Percent of Direct Materials Added Percent of Conversion Beginning work in process 2,000 75 % 25 % Units transferred out 9,000 100 % 100 % Ending work in process 4,400 85 % 35 % Beginning work in process inventory—Assembly dept $ 2,186 (includes...
The Carlberg Company has two manufacturing departments, assembly and painting. The assembly department started 11,400 units...
The Carlberg Company has two manufacturing departments, assembly and painting. The assembly department started 11,400 units during November. The following production activity unit and cost information refers to the assembly department’s November production activities. Assembly Department Units Percent of Direct Materials Added Percent of Conversion Beginning work in process 2,000 75 % 25 % Units transferred out 9,000 100 % 100 % Ending work in process 4,400 85 % 35 % Beginning work in process inventory—Assembly dept $ 2,186 (includes...
The Carlberg Company has two manufacturing departments, assembly and painting. The assembly department started 10,300 units...
The Carlberg Company has two manufacturing departments, assembly and painting. The assembly department started 10,300 units during November. The following production activity unit and cost information refers to the assembly department’s November production activities. Assembly Department Units Percent of Direct Materials Added Percent of Conversion Beginning work in process 3,000 60 % 40 % Units transferred out 10,000 100 % 100 % Ending work in process 3,300 80 % 30 % Beginning work in process inventory—Assembly dept $ 2,696 (includes...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT