Question

In: Accounting

A company makes customized components to specifications. Its old cost accounting system allocated all overhead costs...

A company makes customized components to specifications. Its old cost accounting system allocated all overhead costs to customer jobs based on machine hours. Its new activity-based costing system uses the following information:

Activity Cost Pool and Budgeted Costs: Machine setup $ 90,000, Supervision 140,000, Machine maintenance 170,000

Activity Cost Driver and Estimated Cost Driver Level: Number of setups 180, Direct labor hours 4,000m Machine-hours 5,000

A new Kamlet Company’s order requires 4 setups, 30 direct labor hours and 50 machine-hours.

1. What was the overhead rate in the old cost accounting system? $___ per machine hours

2. What was the total overhead cost charged to the Kamlet Company’s order under the old cost accounting system?

3. What is the overhead rate for the supervision activity in the new activity-based costing system?

4. What is the amount of overhead charged to the Kamlet Company order for the supervision activity under the new activity-based costing system?

5. What is the total overhead cost charged to the Kamlet Company order under the new activity-based costing system?

Solutions

Expert Solution

Solution 1:

Estimated Budgeted costs = $90,000 + $140,000 +$170,000 = $400,000

Esmated machine hours = 5000 hours

Overhead rate in old cost accounting system = estimated Overhead / estimated machine hours
= 400,000/ 5000 = $80 per machine hour

Solution 2:

Total Overhead cost charged to Kamlet Company's order = Machine hours required in order*Overhead rate
= 50 *$80 = $4,000

Solution 3:

Overhead rate for Supervision Activity in ABC costing stystem = Supervision overhead / Direct labor hours
$140000 / 4000 = $35 per labor hour

Solution 4:

Supervision overhead charged to kamlet company's order under ABC system = 30 *$35 = $1050

Solution 5:

Activity Cost pool Budgeted Costs Activity cost driver Estimated Cost Driver level Overhead Rate Cost driver in Kamlet's order Allocated Overhead to Kamlet company's order
Machine Setup $90,000.00 No. of setups 180 $500.00 4 $2,000.00
Supervision $140,000.00 Direct labor hours 4000 $35.00 30 $1,050.00
Machine Maintenance $170,000.00 Machine hours 5000 $34.00 50 $1,700.00
Total Overhead costs $400,000.00 $4,750.00

Therefore, Total overhead charged to kamlet company's order under ABC Sysyem = $4,750


Related Solutions

Script Company uses a job costing accounting system for its production costs. A predetermined overhead rate...
Script Company uses a job costing accounting system for its production costs. A predetermined overhead rate based on direct labor-hours is used to apply overhead to individual jobs. An estimate of overhead costs at different volumes was prepared for the current year as follows: Direct labor-hours 18,000 24,000 30,000 Variable overhead costs 864,000 1,152,000 1,440,000 Fixed overhead costs 1,200,000 1,200,000 1,200,000 Total overhead 2,064,000 2,352,000 2,640,000 The expected volume is 24,000 direct labor-hours for the entire year. The following information...
JUNO company allocated overhead costs to its two products (Basic and Deluxe) using ABC. Juno prepared...
JUNO company allocated overhead costs to its two products (Basic and Deluxe) using ABC. Juno prepared the following annual estimates of each activity and cost driver. Overhead Cost Pool Cost Driver Budgeted Overhead Budgeted Activity (Cost Driver) Machine setups # setups $300,000 100 setups Machining # machine hours $700,000 35,000 machine hours Finishing # direct labor hours $1,000,000 10,000 direct labor hours Calculate the activity pool rate for each activity a) Machine setups b) Machining c) Finishing Calculate the total...
West Manufacturing Company uses a standard cost system in its accounting records. The standard costs for...
West Manufacturing Company uses a standard cost system in its accounting records. The standard costs for its one product are as follows:                      Materials                                    8 pounds at $1.00 =   $ 8.00                      Direct labor                              1.2 hours at $14.00 =     16.80                      Variable overhead     1.2 direct-labor hours at $4.00 =       4.80                      Fixed overhead         1.2 direct-labor hours at $6.00 =       7.20                      Total standard cost                                                      $36.80             The standard costs per unit are based on normal capacity of 3,600 direct-labor...
Horton Company uses a normal costing system. Factory overhead is allocated on the basis of labor...
Horton Company uses a normal costing system. Factory overhead is allocated on the basis of labor hours. At the beginning of the year, management estimated that the company would incur $1,050,000 of manufacturing overhead costs and use 70,000 labor hours. The company recorded the following events during the month of March. (a) Purchased $800,000 of materials on account. b) Used $600,000 of materials in production, of which $80,000 were used as indirect materials. (c) Incurred $250,000 of direct labor costs...
Brookster Inc. used a standard costing system for its production process. Fixed overhead is allocated based...
Brookster Inc. used a standard costing system for its production process. Fixed overhead is allocated based on machine hours. Budgeted fixed overhead for the month was $16,910 for budgeted capacity of 8,900 machine hours. Actual fixed overhead was $17,500 for 1,800 units of output. The standard time allowed was 5 machine hours per unit of output. Required: (a) Compute SQ in total: (b) Compute the Standard Price for fixed overhead: (c) Compute the Fixed Overhead Spending Variance and Fixed Overhead...
Lackawanna Licorice Company uses a standard cost accounting system and applies production overhead to products on...
Lackawanna Licorice Company uses a standard cost accounting system and applies production overhead to products on the basis of machine hours. The following information is available for the year just ended:    Actual variable overhead: $202,920 Actual total overhead: $558,030 Actual machine hours worked: 26,700 Standard variable-overhead rate per hour: $7.90 Standard fixed-overhead rate per hour: $13.20 Planned activity during the period: 26,000 machine hours Actual production: 15,700 finished units Machine-hour standard: Two completed units per machine hour    Required:...
CHAMPIONManufacturing Company uses a normal costing system. The activity base for all overhead costs is direct...
CHAMPIONManufacturing Company uses a normal costing system. The activity base for all overhead costs is direct labor hours. All goods which were produced during the period were completed and sold during the period. Costs of manufacturing and non-manufacturing for the current period are: Estimated Actual Fixed selling expenses $200,000 250,000 Number of units produced            1,000 1,800 Administrative expenses $500,000 500,000 Direct labor                               $128,000 240,000 Direct materials                           $125,000 120,000 Direct labor hours                          3,000 5,000 Indirect labor $130,000 135,000 Indirect materials $200,000...
1. A) If a company makes 100 units of product, the allocated fixed cost per unit...
1. A) If a company makes 100 units of product, the allocated fixed cost per unit is $5 and the variable cost per unit is $6. What will be the per-unit total cost (fixed plus variable cost) if the company makes 200 units? B) At a production and sales level of 1,000 units, the company’s costs are as follows: Variable manufacturing costs per unit $20 Allocated fixed manufacturing cost per unit $10 Variable selling costs per unit $ 5 Allocated...
Cost Accounting Ltd manufactures three products. The company allocates overhead costs as a rate per total...
Cost Accounting Ltd manufactures three products. The company allocates overhead costs as a rate per total direct labour hour. The following cost driver values have been identified: Machine hours / unit Production units Percentage of expert work Number of orders packed Labour hours Alpha 0.70 5 000 30% 4 1 200 Beta 0.30 3 500 20% 8 800 Gamma 0.50 8 000 50% 23 1 500 An analysis of the manufacturing overhead cost for the period shows the following: Activities...
Stockin Company produces Tablets and Books. Total overhead costs traditionally have been allocated on the basis...
Stockin Company produces Tablets and Books. Total overhead costs traditionally have been allocated on the basis of direct labor hours. After implementing activity-based costing, managers determined the following cost pools and cost drivers. They also decided that general costs should no longer be allocated to products. Activity Pool Department Costs Cost driver Binding $266,825.00 Number of units Printing 800,084.25 Machine hours Product design 175,104.00 Change orders General 757,486.75 None Total overhead costs $1,999,500.00 Other information is as follows: Tablets Books...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT