Question

In: Accounting

A company in the civil engineering industry with headquarters locate in Accra undertakes contract anywhere in...

A company in the civil engineering industry with headquarters locate in Accra undertakes contract anywhere in Ghana

The company has had its tender for a job in Kumasi Accepted for GHS 288,000 and work is due to begin in June 2020. However, the company has also been asked to undertake a contract on the Coast of Accra. The price offered for this contract is GHS 352,000. Both of the contracts cannot be undertaken simultaneously because of constraints on staff site management personnel and on plant available. An escape clause enables the company to withdraw from the contract in Accra, provided notice is given before the end of April, 2020 and an agreed penalty of GHS 28,000 is paid.

The company’s quantity surveyor has submitted the following estimates

Cost Estimates

Kumasi

Coastal Accra

GHS

GHS

Materials:

In inventory at original cost, Material X

21,600

In inventory at original cost, Material Y

24,800

Firm orders placed at original cost, Material X

30,400

Not yet ordered - Current cost, Material X

60,000

Not yet ordered - Current cost, Material Z

71,200

Labour - hired locally

86,000

110,000

Site management

34,000

34,000

Staff accommodation and travel for site management

6,800

5,600

Plant on site - depreciation

9,600

12,800

Interest on capital

5,120

6,400

Total local contract cost

253,520

264,800

Headquarters cost allocated at 5% to total contract

cost

12,676

13,240

Contract Cost

266,196

278,040

Contract Price

288,000

352,000

Estimated Profit

21,804

73,960

Additional Information:

  1. X, Y and Z are three building materials. Material X is not in common use and would not realize much money if re-sold; however, it could be used on other contracts but only as a substitute for another material currently quoted at 10% less than the original cost of X. The price of Y a material in common use has doubles since it was purchased; it net realizable value if resold would be the new price less 15% to cover the disposal cost. Alternatively, it could be kept for use on another contract in the following year.
  1. With the construction industry not yet recovered from the recent recession, the company is confident that manual labour, both skilled and unskilled could be hired locally on a sub-contract basis to meet the needs of each of the contracts
  1. The plant, which would be needed for the Coast of Accra contract, has been owned by for some years and GHS 12,800 is the year’s depreciation on a straight-line basis. If the Kumasi contract is undertaken , less plan will be required but the surplus plant will be hired out for the period of the contract at a rental of GHS 6,000
  1. It is the company’s policy to charge all contracts with nominal interest at 8% on estimated working capital involved in contracts. Progress payments would be made receivable from the contractee
  1. Salaries and general cost of operating the small headquarters amount to about GHS 108,000 each year. There are usually ten contracts being supervised at the same time
  1. Each of the two contracts is expected to last from June 2020 to December 2020 which, coincidentally is the company’s financial year
  1. Site management is treated as a fixed cost

Required:

As a management accountant to the company, present comparative statements to show the net benefit to the company for undertaking the more advantageous of the two contracts.

Explain the reasoning behind the inclusion and omission from your comparative financial statement for each item given in the cost estimates and the notes relating thereto

Solutions

Expert Solution

Comparative statement is shown below:

The penalty fees and loss on X is included in computation of profit from the coastal acrra contract while the rental equipment is included in the Kumasi contract. All the other items given are included in the comparitive statement as they are necessary for the comparison of the two projects.

Based on the above computation the Coastal Acrra contract should be preferred as the net profit for this contract is higher than the other contract.


Related Solutions

didference between a bid price and a contract price to civil engineering project
didference between a bid price and a contract price to civil engineering project
Construction codes and specifications Discuss the importance of documentation in the construction and civil engineering industry....
Construction codes and specifications Discuss the importance of documentation in the construction and civil engineering industry. What method(s) are used to ensure proper documentation during construction?
Business Case – Manchester Business School (Civil Engineering) The Company (Civil Engineers) consists of two divisions....
Business Case – Manchester Business School (Civil Engineering) The Company (Civil Engineers) consists of two divisions. The divisions are Transportation and Infrastructure. The company sells engineering services to various customers. The following are the bill rates for the various staff classifications: Vice President $250/hour Senior Engineer $200/hour Associate Engineer $190/hour Staff Engineer $160/hour The two divisions expect to bill the following hours: Transportation - 10,000 hours, vice president at 10% of the time, 20% of Senior Engineer time 10% to...
Katie is a shareholder in Engineers One, a civil engineering company. This year, Katie’s share of...
Katie is a shareholder in Engineers One, a civil engineering company. This year, Katie’s share of net business income from Engineers One is $170,000. Assume that Katie’s allocation of wages paid by Engineers One to its employees is $300,000 and her allocation of Engineers One’s qualified property is $150,000 (unadjusted basis of equipment, all purchased within past three years). Assume Katie has no other business income, no capital gains or qualified dividends, and that her taxable income before the deduction...
Katie is a shareholder in Engineers One, a civil engineering company. This year, Katie's share of...
Katie is a shareholder in Engineers One, a civil engineering company. This year, Katie's share of the net business income from Engineers. One is $200,000. Assume that Katie's allocation of wages paid by Engineers One to it's employees is $300,000 and her allocation of Engineers One's qualified property is $150,000 (unadjusted basis of equipment , all purchased within the past three years) Assume Katie, has no other business income, no capital gains or qualified dividends, and that her taxable income...
Payback Method The management of Deitrich Inc., a civil engineering design company, is considering an investment...
Payback Method The management of Deitrich Inc., a civil engineering design company, is considering an investment in a high-quality blueprint printer with the following cash flows: Year               Investment   Cash Inflow 1                    $28,000          $2,000 2                      $4,000          $3,000 3                                            $6,000 4                                            $8,000 5                                            $9,000 6                                            $8,000 7                                            $6,000 8                                            $5,000 9                                            $4,000 10                                            $4,000 Required: Determine the payback period of the investment. Would the payback period be affected if the cash inflow...
1. Katie is a shareholder in Engineers One, a civil engineering company. This year, Katie’s share...
1. Katie is a shareholder in Engineers One, a civil engineering company. This year, Katie’s share of net business income from Engineers One is $180,000. Assume that Katie’s allocation of wages paid by Engineers One to its employees is $300,000 and her allocation of Engineers One’s qualified property is $150,000 (unadjusted basis of equipment, all purchased within past three years). Assume Katie has no other business income, no capital gains or qualified dividends, and that her taxable income before the...
Company ARC Inc. is a medium sized civil engineering firm with 150 employees in offices in...
Company ARC Inc. is a medium sized civil engineering firm with 150 employees in offices in Ontario, Alberta, and British Columbia. The design of the payroll system calculates the hourly, bi-weekly, and monthly compensation wages for temporary, contract, and full-time engineering employees. The company wants to revamp its payroll system with consideration of multiple employee type groups mentioned above. You are assigned to create this payroll system that calculates the correct wages for each employee and report the total wage...
The WIX Company Civil Engineers consists of two divisions. The divisions are Water (WA) and Infrastructure (IF). The company sells engineering services to various customers.
  The WIX Company Civil Engineers consists of two divisions. The divisions are Water (WA) and Infrastructure (IF). The company sells engineering services to various customers.The following are the bill rates for the various staff classifications:Vice President $280/hourSenior Engineer $220/hourAssociate Engineer $200/hourStaff Engineer $160/hourThe two divisions expect to bill the following hours:• Water- 12,000 hours, vice president at 15% of the time, 20% of Senior Engineer time 10% to Associate engineers and remaining to Staff Engineers.• Infrastructure- 4,000 hours, vice...
Construction Engineering question: Produce a environmental management plan Company has been awarded the contract for a...
Construction Engineering question: Produce a environmental management plan Company has been awarded the contract for a bridge replacement, including 2km approach resurfacing on each side and has placed you and your team in charge. Produce a environmental management plan. Thanks!!
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT