Question

In: Finance

Megan Company has two departments, X and Y. Overhead is applied based on direct-labor hours in...

  1. Megan Company has two departments, X and Y. Overhead is applied based on direct-labor hours in Department X and machine hours in Department Y. The following additional information is available:
BUDGETED AMOUNTS
Department X Department Y
Direct-Labor Hours 18,000 16,500
Machine Hours 51,000 40,000
Factory Overhead $225,000 $180,000

Actual Data for Job #10

Department X Department Y
Direct materials $10,000 $16,000
Direct-labor cost $11,000 $14,000
Machine hours 5,000 3,000
Direct-labor hours 1,100 1,400

Required:

1. Compute the budgeted factory-overhead rate (i.e., the $ rate per activity base hour, etc.) for Department X.

2. Compute the budgeted factory-overhead rate (i.e., the $ rate per activity base hour, etc.) for Department Y.

3. What is the total overhead cost of Job #10?

4. What is the total cost of Job #10?

5. If Job 10 consists of 50 units of product, what is the unit cost of this job?

Solutions

Expert Solution

Department-X Department-Y
Factory overhead $           225,000 $     180,000
Cost driver Direct labor hours Machine hours
Cost driver 18000 40000
Factory overhead rate= =225000/18000 =180000/40000
Factory overhead rate= $               12.50 $           4.50
Job 10 data
Department-X Department-Y
Labor hours 1100
Machine hours 3000
Overhead recovery rate $               12.50 $           4.50
Overhead cost =1100*12.5 =3000*4.5
Overhead cost $        13,750.00 $ 13,500.00
Job 10 data
Department-X Department-Y Total
Direct Material $             10,000 $       16,000 $ 26,000
Direct labor $             11,000 $       14,000 $ 25,000
Factory overheads $             13,750 $       13,500 $ 27,250
Total cost $ 78,250
Job 10
Total cost $             78,250
No of units 50
Cost per unit =78250/50
Cost per unit $               1,565

Related Solutions

Megan Company has two departments, X and Y. Overhead is applied based on direct-labor hours in...
Megan Company has two departments, X and Y. Overhead is applied based on direct-labor hours in Department X and machine hours in Department Y. The following additional information is available: BUDGETED AMOUNTS Department X Department Y Direct-Labor Hours 18,000 16,500 Machine Hours 51,000 40,000 Factory Overhead $225,000 $180,000 Actual Data for Job #10 Department X Department Y Direct materials $10,000 $16,000 Direct-labor cost $11,000 $14,000 Machine hours 5,000 3,000 Direct-labor hours 1,100 1,400 Required: 1. Compute the budgeted factory-overhead rate...
Megan Company has two departments, X and Y. Overhead is applied based on direct-labor hours in...
Megan Company has two departments, X and Y. Overhead is applied based on direct-labor hours in Department X and machine hours in Department Y. The following additional information is available: BUDGETED AMOUNTS Department X Department Y Direct-Labor Hours 18,000 16,500 Machine Hours 51,000 40,000 Factory Overhead $225,000 $180,000 Actual Data for Job #10 Department X Department Y Direct materials $10,000 $16,000 Direct-labor cost $11,000 $14,000 Machine hours 5,000 3,000 Direct-labor hours 1,100 1,400 Required: 1. Compute the budgeted factory-overhead rate...
United Kingdom Company has two departments, X and Y. Overhead is applied based on direct labor...
United Kingdom Company has two departments, X and Y. Overhead is applied based on direct labor cost in Department X and machine-hours in Department Y. The following additional information is available:                Budgeted Amounts                     Department X           Department Y                Direct labor cost                           $180,000                     $165,000                Factory overhead                         $225,000                     $200,000                Machine-hours                                  51,000 mh                 40,000    mh                Actual data for Job #25                  Department X       Department Y                Direct materials requisitioned            $15,000               $18,000                Direct labor cost                                     $11,000               $14,000                Machine-hours                                            5,000...
MAnufacturing overhead is applied on the basis of direct labor hours. The direct labor hours for...
MAnufacturing overhead is applied on the basis of direct labor hours. The direct labor hours for the period are 500 and the estimated manufacturing overhead is 2000. actual direct labor hours were 160 and actual overhead was 1000. Compute the manufacturing overhead applied during this period.
Overhead is applied on the basis of direct labor hours. Three direct labor hours are required...
Overhead is applied on the basis of direct labor hours. Three direct labor hours are required for each product unit. Planned production for the period was set at 8,000 units. Manufacturing overhead for the period is budgeted at $204,000, of which 30 percent is fixed. The 26,200 hours worked during the period resulted in production of 8,500 units. Manufacturing overhead cost incurred was $220,500. Required: a. Calculate the overhead spending variance: b. Calculate the overhead efficiency variance: c. Calculate the...
Freytag Corporation's variable overhead is applied on the basis of direct labor-hours. The company has established...
Freytag Corporation's variable overhead is applied on the basis of direct labor-hours. The company has established the following variable overhead standards for product N06C: Standard direct labor-hours 3.7 hours per unit of N06C Standard variable overhead rate $ 5.50 per hour The following data pertain to the most recent month's operations during which 1,800 units of product N06C were made: Actual direct labor-hours worked 6,500 Actual variable overhead incurred $ 36,640 Required: a. What was the variable overhead rate variance...
A manufacturing company applies factory overhead based on direct labor hours.
A manufacturing company applies factory overhead based on direct labor hours. At the beginning of the year, it estimated that factory overhead costs would be $360,000and direct labor hours would be 45,000. Actual manufacturing overhead costs incurred were $377,200, and actual direct labor hours were 47,000. The entry to apply the factory overhead costs for the year would include aa. debit to factory overhead for $377,200.b. debit to factory overhead for $360,000.c. credit to factory overhead for $376,000.d. credit to...
A manufacturing company applies factory overhead based on direct labor hours. At the beginning of the...
A manufacturing company applies factory overhead based on direct labor hours. At the beginning of the year, it estimated that factory overhead costs would be $327,691 and direct labor hours would be 46,813. Actual factory overhead costs incurred were $344,427, and actual direct labor hours were 51,254. What is the amount of overapplied or underapplied manufacturing overhead at the end of the year? a.$31,087 underapplied b.$14,351 overapplied c.$14,351 underapplied d.$358,778 overapplied
A manufacturing company applies factory overhead based on direct labor hours. At the beginning of the...
A manufacturing company applies factory overhead based on direct labor hours. At the beginning of the year, it estimated that factory overhead costs would be $540,000 and direct labor hours would be 45,000. Actual factory overhead costs incurred were $566,000, and actual direct labor hours were 47,000. What is the amount of overapplied or underapplied manufacturing overhead at the end of the year?
A manufacturing company applies factory overhead based on direct labor hours. At the beginning of the...
A manufacturing company applies factory overhead based on direct labor hours. At the beginning of the year, it estimated that factory overhead costs would be $344,000 and direct labor hours would be 45,000. Actual manufacturing overhead costs incurred were $316,200, and actual direct labor hours were 54,400. The entry to apply the factory overhead costs for the year would include a a.debit to Factory Overhead for $316,200 b.credit to Factory Overhead for $344,000 c.credit to Factory Overhead for $415,616 d.debit...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT