In: Accounting
Production and cost data for the Molding Department during June 2020 are presented below.
Production Data |
June |
||
Beginning work in process units | 0 | ||
Units started into production | 24,860 | ||
Ending work in process units | 2,260 | ||
Percent complete—ending inventory | 40 | % |
Cost Data |
||
Materials | $223,740 | |
Labor | 60,568 | |
Overhead | 127,464 | |
Total | $411,772 |
Prepare a schedule showing physical units of production.
.
Determine the equivalent units of production for materials and conversion costs.
.
Compute the unit costs of production.
.
Determine the costs to be assigned to the units transferred out and in process for June.
.
Prepare a production cost report for the Molding Department for the month of June.
SWIFTY COMPANY |
||||||||
Equivalent Units |
||||||||
Quantities |
Physical |
|
Conversion |
|||||
Units to be accounted for |
||||||||
Work in process, June 1 |
||||||||
Started into production |
||||||||
Total units |
||||||||
Units accounted for |
||||||||
Transferred out |
||||||||
Work in process, June 30 |
||||||||
Total units |
||||||||
|
|
Conversion |
|
|||||
Unit costs |
||||||||
Total Costs |
$ |
$ |
$ |
|||||
Equivalent units |
||||||||
Unit costs |
$ |
$ |
$ |
|||||
Costs to be accounted for |
||||||||
Work in process, June 1 |
$ |
|||||||
Started into production |
||||||||
Total costs |
$ |
|||||||
Cost Reconciliation Schedule |
||||||||
Costs accounted for |
||||||||
Transferred out |
$ |
|||||||
Work in process, June 30 |
||||||||
Materials |
$ |
|||||||
Conversion costs |
||||||||
Total costs |
$ |
Equivalent Units | ||||
Quantities | Physical | Conversion | ||
Units | Materials | Costs | ||
Units to be accounted for: | ||||
Work in process, June 1 | 0 | |||
Started into production | 24860 | |||
Total units | 24860 | |||
Units accounted for: | ||||
Transferred out | 22600 | 22600 | 22600 | |
Work in process, June 30 | 2260 | 2260 | 904 | |
Total units | 24860 | 24860 | 23504 | |
Conversion | ||||
Costs | Materials | Costs | Total | |
Unit costs | ||||
Total Costs | $223,740 | $ 188,032 | $ 411,772 | |
Equivalent units | 24860 | 23504 | ||
Unit costs | $ 9.00 | $ 8.00 | $ 17.00 | |
Costs to be accounted for: | ||||
Work in process, June 1 | $ - | $ - | $ - | |
Started into production | $223,740 | $ 188,032 | $ 411,772 | |
Total costs | $223,740 | $ 188,032 | $ 411,772 | |
Cost Reconciliation Schedule | ||||
Costs accounted for: | ||||
Transferred out | $203,400 | $ 180,800 | $ 384,200 | |
Work in process, June 30 | ||||
Materials | $ 20,340 | |||
Conversion costs | $ 7,232 | |||
Total costs | $ 411,772 |