In: Accounting
Production and cost data for the Molding Department during June 2020 are presented below.
|
Production Data |
June |
||
| Beginning work in process units | 0 | ||
| Units started into production | 24,860 | ||
| Ending work in process units | 2,260 | ||
| Percent complete—ending inventory | 40 | % | |
|
Cost Data |
||
| Materials | $223,740 | |
| Labor | 60,568 | |
| Overhead | 127,464 | |
| Total | $411,772 |
Prepare a schedule showing physical units of production.
.
Determine the equivalent units of production for materials and conversion costs.
.
Compute the unit costs of production.
.
Determine the costs to be assigned to the units transferred out and in process for June.
.
Prepare a production cost report for the Molding Department for the month of June.
|
SWIFTY COMPANY |
||||||||
|
Equivalent Units |
||||||||
|
Quantities |
Physical |
|
Conversion |
|||||
|
Units to be accounted for |
||||||||
|
Work in process, June 1 |
||||||||
|
Started into production |
||||||||
|
Total units |
||||||||
|
Units accounted for |
||||||||
|
Transferred out |
||||||||
|
Work in process, June 30 |
||||||||
|
Total units |
||||||||
|
|
|
Conversion |
|
|||||
|
Unit costs |
||||||||
|
Total Costs |
$ |
$ |
$ |
|||||
|
Equivalent units |
||||||||
|
Unit costs |
$ |
$ |
$ |
|||||
|
Costs to be accounted for |
||||||||
|
Work in process, June 1 |
$ |
|||||||
|
Started into production |
||||||||
|
Total costs |
$ |
|||||||
|
Cost Reconciliation Schedule |
||||||||
|
Costs accounted for |
||||||||
|
Transferred out |
$ |
|||||||
|
Work in process, June 30 |
||||||||
|
Materials |
$ |
|||||||
|
Conversion costs |
||||||||
|
Total costs |
$ |
|||||||
| Equivalent Units | ||||
| Quantities | Physical | Conversion | ||
| Units | Materials | Costs | ||
| Units to be accounted for: | ||||
| Work in process, June 1 | 0 | |||
| Started into production | 24860 | |||
| Total units | 24860 | |||
| Units accounted for: | ||||
| Transferred out | 22600 | 22600 | 22600 | |
| Work in process, June 30 | 2260 | 2260 | 904 | |
| Total units | 24860 | 24860 | 23504 | |
| Conversion | ||||
| Costs | Materials | Costs | Total | |
| Unit costs | ||||
| Total Costs | $223,740 | $ 188,032 | $ 411,772 | |
| Equivalent units | 24860 | 23504 | ||
| Unit costs | $ 9.00 | $ 8.00 | $ 17.00 | |
| Costs to be accounted for: | ||||
| Work in process, June 1 | $ - | $ - | $ - | |
| Started into production | $223,740 | $ 188,032 | $ 411,772 | |
| Total costs | $223,740 | $ 188,032 | $ 411,772 | |
| Cost Reconciliation Schedule | ||||
| Costs accounted for: | ||||
| Transferred out | $203,400 | $ 180,800 | $ 384,200 | |
| Work in process, June 30 | ||||
| Materials | $ 20,340 | |||
| Conversion costs | $ 7,232 | |||
| Total costs | $ 411,772 |