In: Accounting
1. Test Company derived the following cost function for the production of its product.
Cost = $16,000 + $10X, where x is the number of units.
Next month, Test Company expects to produce 4,000 units.
Determine the total cost per unit to produce 4,000 units.
Note: Give your answer using dollar signs and state your answer to the nearest cent.
Example: $12.34 or $12.00
2.
Next month, Test Company expects to produce 4,000 units.
Suppose production is less than expected so that Test Company only produces 3,500 units. Total cost will
a. |
Increase |
|
b. |
Decrease |
|
c. |
Remain unchanged |
|
d. |
A incorrect answer because Blackboard requires four choices |
3.
Next month, Test Company expects to produce 4,000 units.
Suppose production is less than expected so that Test Company only produces 3,500 units. Total variable cost will
Increase |
||
Decrease |
||
Remain unchanged |
||
An incorrect answer because Blackboard requires four choices |
4.
Next month, Test Company expects to produce 4,000 units.
Suppose production is less than expected so that Test Company only produces 3,500 units. Total fixed cost will
Increase |
||
Decrease |
||
Remain unchanged |
||
An incorrect answer because Blackboard requires four choices |
5.
Next month, Test Company expects to produce 4,000 units.
Suppose production is less than expected so that Test Company only produces 3,500 units. Variable cost per unit will
Increase |
||
Decrease |
||
Remain unchanged |
||
An incorrect answer because Blackboard requires four choices |
6.
Suppose production is less than expected so that Test Company only produces 3,500 units. Fixed cost per unit will
Increase |
||
Decrease |
||
Remain unchanged |
||
An incorrect answer because Blackboard requires four choices |
7.
Next month, Test Company expects to produce 4,000 units.
Suppose production is less than expected so that Test Company only produces 3,500 units. Total cost per unit will
Increase |
||
Decrease |
||
Remain unchanged |
||
An incorrect answer because Blackboard requires four choices |
1. Total cost = $56,000
2. b. Decreases
3. Decreases.
4. Remain Unchanged
5. Remain unchanged
6. Increase
7. Increase
Working notes