The standard cost of Product B manufactured by Pharrell Company includes 2.4 units of direct materials...

The standard cost of Product B manufactured by Pharrell Company includes 2.4 units of direct materials at $5.30 per unit. During June, 26,600 units of direct materials are purchased at a cost of $5.25 per unit, and 26,600 units of direct materials are used to produce 10,900 units of Product B.

(a)

Compute the total materials variance and the price and quantity variances.

Total materials variance $enter a dollar amount select an option                                                          FavorableUnfavorableNeither favorable nor unfavorable
Materials price variance $enter a dollar amount select an option                                                          UnfavorableFavorableNeither favorable nor unfavorable
Materials quantity variance $enter a dollar amount select an option                                                          FavorableUnfavorableNeither favorable nor unfavorable

Compute the total materials variance and the price and quantity variances, assuming the purchase price is $5.35 and the quantity purchased and used is 26,700 units.

Total materials variance $enter a dollar amount select an option                                                          UnfavorableFavorableNeither favorable nor unfavorable
Materials price variance $enter a dollar amount select an option                                                          UnfavorableFavorableNeither favorable nor unfavorable
Materials quantity variance $enter a dollar amount select an option                                                          Neither favorable nor unfavorableFavorableUnfavorable

Solutions

Expert Solution


Related Solutions

The standard cost of Product B manufactured by Pharrell Company includes 3.0 units of direct materials...
The standard cost of Product B manufactured by Pharrell Company includes 3.0 units of direct materials at $6.8 per unit. During June, 27,500 units of direct materials are purchased at a cost of $6.60 per unit, and 27,500 units of direct materials are used to produce 9,100 units of Product B. (a) Compute the total materials variance and the price and quantity variances. Total materials variance $enter a dollar amount select a type of the variance              ...
Exercise 11-5 The standard cost of Product B manufactured by Pharrell Company includes 2.6 units of...
Exercise 11-5 The standard cost of Product B manufactured by Pharrell Company includes 2.6 units of direct materials at $6.0 per unit. During June, 26,700 units of direct materials are purchased at a cost of $5.90 per unit, and 26,700 units of direct materials are used to produce 10,100 units of Product B. (a) Compute the total materials variance and the price and quantity variances. Total materials variance $ Materials price variance $ Materials quantity variance $ (b) Compute the...
The standard cost of product 777 includes 2.70 units of direct materials at $5.80 per unit....
The standard cost of product 777 includes 2.70 units of direct materials at $5.80 per unit. During August, the company bought 28,500 units of materials at $5.90 and used those materials to produce 10,800 units. Compute the total, price, and quantity variances for materials. Total materials variance $                                                           Neither favorable nor unfavorableFavorableUnfavorable Materials price variance $               ...
The standard cost of product 777 includes 2.40 units of direct materials at $6.80 per unit....
The standard cost of product 777 includes 2.40 units of direct materials at $6.80 per unit. During August, the company bought 29,300 units of materials at $7.05 and used those materials to produce 12,400 units. Compute the total, price, and quantity variances for materials. Total materials variance $                                                           FavorableNeither favorable nor unfavorableUnfavorable Materials price variance $               ...
Q 23 The standard cost for a product, product Z, includes the following direct materials costs...
Q 23 The standard cost for a product, product Z, includes the following direct materials costs GHS per unit Materials X 5 kilos at GHS8 per kilo 40 Material Y 3 kilos at GHS12 per kilo 36 76 The materials can be mixed in differing proportions Actual production during April was 1,250 units of Product Z, with the following GHS Material X 6,700kilos 51,400 Material Y 2,900kilos 39,500 90,900 Required: a) Calculate the direct materials price, mix and yield variances...
The standard cost for Product G3 includes 2 gallons of direct materials at $4 per gallon....
The standard cost for Product G3 includes 2 gallons of direct materials at $4 per gallon. During the current month, 11,200 gallons of direct materials were purchased for $45,920, and 11,200 gallons were used to produce 6,000 units of Product G3. The direct materials quantity variance for the current month is Group of answer choices $1,200 unfavorable $1,120 unfavorable $3,200 favorable $3,280 favorable
A manufactured product has the following information for June. Standard Actual Direct materials (5 lbs. @...
A manufactured product has the following information for June. Standard Actual Direct materials (5 lbs. @ $9 per lb.) 40,000 lbs. @ $9.20 per lb. Direct labor (3 hrs. @ $16 per hr.) 23,400 hrs. @ $16.60 per hr. Overhead (3 hrs. @ $13 per hr.) $ 315,100 Units manufactured 7,900 Compute the direct materials price variance and the direct materials quantity variance. Indicate whether each variance is favorable or unfavorable.
A manufactured product has the following information for June. Standard Actual Direct materials (5 lbs. @...
A manufactured product has the following information for June. Standard Actual Direct materials (5 lbs. @ $7 per lb.) 35,400 lbs. @ $7.20 per lb. Direct labor (2 hrs. @ $16 per hr.) 13,800 hrs. @ $16.50 per hr. Overhead (2 hrs. @ $13 per hr.) $ 188,500 Units manufactured 7,000 Exercise 23-8 Standard unit cost; total cost variance LO C2 (1) Compute the standard cost per unit.
A manufactured product has the following information for August. Standard Actual Direct materials 2 lbs. per...
A manufactured product has the following information for August. Standard Actual Direct materials 2 lbs. per unit @ $3.50 per lb. Direct labor 0.5 hours per unit @ $24 per hour Overhead $24 per direct labor hour Units manufactured 12,400 Total manufacturing costs $ 380,400 (1) Compute the standard cost per unit. (2) Compute the total budgeted cost for production in August. (3) Compute the total cost variance for August. (Indicate the effect of each variance by selecting for favorable,...
Standard Product Cost, Direct Materials Variance Condiments Company uses standards to control its materials costs. Assume...
Standard Product Cost, Direct Materials Variance Condiments Company uses standards to control its materials costs. Assume that a batch of ketchup (1,900 pounds) has the following standards: Standard Quantity Standard Price Whole tomatoes 3,200 lbs. $0.48 per lb. Vinegar 180 gal. 2.90 per gal. Corn syrup 15 gal. 10.70 per gal. Salt 72 lbs. 2.70 per lb. The actual materials in a batch may vary from the standard due to tomato characteristics. Assume that the actual quantities of materials for...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT