Given the following information, complete the planned order releases and projected on-hand balances for component part X.
| 
 Part X  | 
 Week 1  | 
 Week 2  | 
 Week 3  | 
 Week 4  | 
 Week 5  | 
|
| 
 Gross Requirements  | 
 80  | 
 0  | 
 90  | 
 0  | 
 90  | 
|
| 
 Scheduled Receipts  | 
 60  | 
|||||
| 
 Projected Balance  | 
 120  | 
|||||
| 
 Planned Order Releases  | 
||||||
Q = 60, LT = 3 weeks, Safety Stock = 5
We have following information-
· Q = 60 means Planned Order Release could be in multiple of 60 only
· LT = 3 weeks, means lead time is 3 weeks so Planned Order Release should be 3 weeks before the requirements
· Safety Stock = 5 means the Projected Balance cannot go below 5 at any point of time
Now complete the planned order releases and projected on-hand balances for component part X -
| 
 Party X  | 
 Week 1  | 
 Week 2  | 
 Week 3  | 
 Week 4  | 
 Week5  | 
|
| 
 Gross requirement  | 
 80  | 
 0  | 
 90  | 
 0  | 
 90  | 
|
| 
 Scheduled receipts  | 
 60  | 
 0  | 
 0  | 
 0  | 
 0  | 
|
| 
 Projected Balance  | 
 120  | 
 100  | 
 100  | 
 10  | 
 10  | 
 40  | 
| 
 Planned Order Release  | 
 0  | 
 120  | 
 0  | 
 0  | 
 0  | 
Explanation:
Projected Balance for week 1 = Initial projected balance + scheduled receipts for week 1 – gross requirement for week 1
= 120 + 60 – 80 = 100
Projected Balance for week 2 = Projected balance for week 1 + scheduled receipts for week 2 – gross requirement for week 2
= 100 + 0 – 0 = 100
Projected Balance for week 3 = Projected balance for week 2 + scheduled receipts for week 3 – gross requirement for week 3
= 100 + 0 – 90 = 10
Projected Balance for week 4 = Projected balance for week 3 + scheduled receipts for week 4 – gross requirement for week 4
= 10 + 0 – 0 = 10
Projected Balance for week 5 = Projected balance for week 4 + scheduled receipts for week 5 – gross requirement for week 5 + Planned Order Release in week 2
= 10 + 0 – 90 + 120 = 40
For Planned Order Release; we can see in the above table that for week 5, if there is no receipts, the projected balance will be negative therefore there should be Planned Order Release 3 weeks before (in week 2). As the required quantity is more than 60 for week 5, therefore Planned Order Release will be 2 * 60 = 120 in week 2.