Question

In: Operations Management

A company wants to build a warehouse to serve three markets and has determined the markets...

A company wants to build a warehouse to serve three markets and has determined the markets and their relative locations as follows:

Market A- (10,20) Load 300

Market B- (20,15) Load 100

Market C- (15,25) Load 200

a.If the company has narrowed down the warehouse location to either market B or C, which location would be a better choice using load-distance score method, assuming rectilinear distance? b. If the company has decided to locate the facility at the center of gravity, what are the coordinates of the center of gravity? And what would be the load-distance score of this choice, assuming rectilinear distance?

Solutions

Expert Solution

If you liked the answer please give an Up-vote, this will be quite encouraging for me, thank you!


Related Solutions

a soap manufacturing company has three employees who work in a warehouse All of the warehouse...
a soap manufacturing company has three employees who work in a warehouse All of the warehouse workers are authorized to order inventory when it falls below order level.The workers complete a purchase order and mail it to supplier of their choice .The inventory is delivered directly to the warehouse .The workers send a memo to accounts payable reporting receipt of inventory accounts payable compares warehouse memo to suppliers invoice .Accounts payable prepares a memo which treasurer signs .discuss internal control...
A company wants to build a new factory. They know the cost to build the factory...
A company wants to build a new factory. They know the cost to build the factory and have forecasted the future cash flows from the plant. They want to do an NPV analysis but are not sure what rate to use. They come to you as a consultant to figure out their cost of capital. The information they have given you is: They just paid a dividend of $2.75. Their dividend growth rate is 4.8%. Their current stock price is...
Big Construction Company signs a contract on 1 July 2019, agreeing to build a warehouse for...
Big Construction Company signs a contract on 1 July 2019, agreeing to build a warehouse for Buyer Corporation Ltd at a fixed contract price of $10 million. Buyer Ltd will be in control of the asset throughout the construction process. Big Construction Company estimates that construction costs will be as follows: 2019 2.5 million 2020 $4 million 2021 $1.5 million The contract provides that Buyer Corporation Ltd will make payments on 31 December each year as follows: 2019 $2 million...
A   production   company   plans   to   build   a   new   warehouse   in   order   to   supply   its   new &nb
A   production   company   plans   to   build   a   new   warehouse   in   order   to   supply   its   new   sales   points.   On   the   basis   of   a   preliminary   analysis   of   the   problem,   it   has   been   decided   that   the   facility   should   accommodate   at   least   800   pallets   of   80×80   cm2   dimension.   The   pallets   will   be   stored   onto   conventional   racks   and   transported   by   means   of   reach   trucks.   Each   rack   has   four   shelves,   each   of   which   can   store   a   single   pallet.   Each   pallet   occupies   a   1.0×1.0   m2   area.   Racks  ...
2. At the end of 2018, Builders Inc. has one project underway to build a warehouse....
2. At the end of 2018, Builders Inc. has one project underway to build a warehouse. The project was begun in early 2017. The contract amount is $50,000,000 and the project is expected to be completed in late 2019. Data on this project are presented below: Costs incurred in 2017 $8,000,000 Billings in 2017 $6,000,000 Estimated cost to complete at 12/31/17 $32,000,000 Additional costs incurred in 2018 $19,000,000 Billings in 2018 $15,000,000 Estimated cost to complete at 12/31/18 $18,000,000 Required:...
For Pineapples How are products priced in the markets? Are they determined in central markets? Are...
For Pineapples How are products priced in the markets? Are they determined in central markets? Are contracts used? Please explain how the price can be affected by these factors.
The Nexus company wants to get a contract to build roads in Nigeria. It is the...
The Nexus company wants to get a contract to build roads in Nigeria. It is the standard business practice for companies to give payments and gifts to officials in Africa. Nexus could easily lose the contract to a competitor. Which of the following ethical theories is defined as a belief in time-and-place ethics and holds that ethical truths depend on the circumstances? a. Moral relativism theory b. Utilitarian ethical theory c. Deontological theory d. Casuist ethical theory
A company wants a $3 million loan for a warehouse expansion. The bank will finance 100%...
A company wants a $3 million loan for a warehouse expansion. The bank will finance 100% of the project with a 5 year balloon and a 20 year amortization. Give a loan structure for both a 5.00% and 5.25% fixed rate. (Specifically, I am looking for help concerning the 5 year balloon)
Quantum Logistics, Inc., a wholesale distributor, is considering the construction of a new warehouse to serve...
Quantum Logistics, Inc., a wholesale distributor, is considering the construction of a new warehouse to serve the southeastern geographic region near the Alabama–Georgia border. There are three cities being considered. After site visits and a budget analysis, the expected income and costs associated with locating in each of the cities have been determined. The life of the warehouse is expected to be 12 years and MARR is 15%/year. City Initial Cost Net Annual Income Lagrange $1,260,000 $480,000 Auburn $1,000,000 $410,000...
QUESTION 5. Company X wants to procure products from two different suppliers it has determined, but...
QUESTION 5. Company X wants to procure products from two different suppliers it has determined, but has doubted the quality of these suppliers' products. For this reason, he took random samples from both suppliers before placing their exact orders. He bought 50 products randomly from supplier A, and their average survival time was 153 hours and standard deviation was 10 hours. The average duration of 50 products bought from supplier B was 150 hours and the standard deviation was 5...