In: Operations Management
Problem 9-19 (Algorithmic)
The product development group at Landon Corporation has been working on a new computer software product that has the potential to capture a large market share. Through outside sources, Landon's management learned that a competitor is working to introduce a similar product. As a result, Landon's top management increased its pressure on the product development group. The group's leader turned to PERT/CPM as an aid to scheduling the activities remaining before the new product can be brought to the market. The project network is as follows:
The activity time estimates (in weeks) are as follows:
| Activity | Optimistic | Most Probable | Pessimistic | |||||||
| A | 2.0 | 4.0 | 6.0 | |||||||
| B | 4.0 | 4.5 | 8.0 | |||||||
| C | 3.0 | 5.0 | 7.0 | |||||||
| D | 1.0 | 3.0 | 5.0 | |||||||
| E | 6.0 | 11.0 | 16.0 | |||||||
| F | 6.5 | 8.5 | 13.5 | |||||||
| G | 3.5 | 6.0 | 8.5 | |||||||
| H | 4.0 | 6.0 | 14.0 | |||||||
| I | 1.0 | 2.5 | 7.0 | |||||||
| J | 4.0 | 5.0 | 6.0 | |||||||
| Activity | Expected Time | Variance | ||
| A | ||||
| B | ||||
| C | ||||
| D | ||||
| E | ||||
| F | ||||
| G | ||||
| H | ||||
| I | ||||
| J | ||||
| Earliest | Latest | Earliest | Latest | Critical | ||||||||
| Activity | Start | Start | Finish | Finish | Slack | Activity | ||||||
| A | No | |||||||||||
| B | Yes | |||||||||||
| C | No | |||||||||||
| D | No | |||||||||||
| E | Yes | |||||||||||
| F | No | |||||||||||
| G | No | |||||||||||
| H | Yes | |||||||||||
| I | No | |||||||||||
| J | Yes | |||||||||||
It is given that the critical path is B-E-H-J
Following may be noted :
Expected duration of an activity = ( Most probable duration + 4 x Pessimistic duration + Pessimistic duration)/6
Variance of an activity = ( Pessimistic duration – Most probable duration)^2/36
Refer below table which highlights data about calculated expected duration and variance of activities on critical path.
Expected duration of critical path = Sum of expected durations of B,E,H,J = 28
Variance of critical path = Sum of variances of B,E,H,J = 6.11
Therefore, Standard deviation of critical path = Square root ( variance ) = Square root ( 6.11) = 2.47
| 
 Activity  | 
 Optimistic  | 
 Most probable  | 
 Pessimistic  | 
 Expected duration  | 
 Variance  | 
| 
 B  | 
 4  | 
 4.5  | 
 8  | 
 5  | 
 0.44  | 
| 
 E  | 
 6  | 
 11  | 
 16  | 
 11  | 
 2.78  | 
| 
 H  | 
 4  | 
 6  | 
 14  | 
 7  | 
 2.78  | 
| 
 J  | 
 4  | 
 5  | 
 6  | 
 5  | 
 0.11  | 
| 
 Total:  | 
 28  | 
 6.11  | 
Let Z value of probability that project will be completed in 25 weeks = Z1
Therefore,
28 + 6.11.Z1 = 25
Or, 6.11.Z1 = - 3
Or, Z1 = - 3/6.11 = - 0.491
Corresponding probability for Z1 s derived from Z table = 0.3121
P( 25 weeks ) = 0.3121
Let Z value of probability that the project will be completed in 30 weeks = Z2
Therefore ,
28 + 6.11.Z2 = 30
Or, 6.11.Z2 = 2
Or, Z2 = 2/6.11 = 0.327 ( 0.33 rounded to 2 decimal places)
Corresponding probability for Z = 0.33 as derived from Z table is 0.6293
P( 30 weeks ) = 0.6293