In: Finance
The Treasury bill rate is 5% and the market risk premium is 8%. |
Project | Beta | Internal Rate of Return, % |
P | 1.00 | 16 |
Q | 0 | 8 |
R | 2.00 | 22 |
S | 0.40 | 9 |
T | 1.90 | 20 |
a. |
What are the project costs of capital for new ventures with betas of .75 and 1.55? (Do not round intermediate calculations. Round your answers to 2 decimal places.) |
Beta | Cost of Capital |
0.75 | % |
1.55 | % |
b. |
Which of the following capital investments have positive NPVs? (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer.) |
|
Answer a.
If beta is 0.75:
Cost of Capital = Risk-free Rate + Beta * Market Risk
Premium
Cost of Capital = 5.00% + 0.75 * 8.00%
Cost of Capital = 11.00%
If beta is 1.55:
Cost of Capital = Risk-free Rate + Beta * Market Risk
Premium
Cost of Capital = 5.00% + 1.55 * 8.00%
Cost of Capital = 17.40%
Answer b.
Project P:
Cost of Capital = Risk-free Rate + Beta * Market Risk
Premium
Cost of Capital = 5.00% + 1.00 * 8.00%
Cost of Capital = 13.00%
IRR is higher than cost of capital, therefore, the NPV is positive.
Project Q:
Cost of Capital = Risk-free Rate + Beta * Market Risk
Premium
Cost of Capital = 5.00% + 0.00 * 8.00%
Cost of Capital = 5.00%
IRR is higher than cost of capital, therefore, the NPV is positive.
Project R:
Cost of Capital = Risk-free Rate + Beta * Market Risk
Premium
Cost of Capital = 5.00% + 2.00 * 8.00%
Cost of Capital = 21.00%
IRR is higher than cost of capital, therefore, the NPV is positive.
Project S:
Cost of Capital = Risk-free Rate + Beta * Market Risk
Premium
Cost of Capital = 5.00% + 0.40 * 8.00%
Cost of Capital = 8.20%
IRR is higher than cost of capital, therefore, the NPV is positive.
Project T:
Cost of Capital = Risk-free Rate + Beta * Market Risk
Premium
Cost of Capital = 5.00% + 1.90 * 8.00%
Cost of Capital = 20.20%
IRR is lower than cost of capital, therefore, the NPV is negative.