Lulu Lemon Pants is planning on producing 40,000 pants in the year. Each pant requires 0.60 metres of material at $4 per metre and 0.15 hour of direct labour at $18 per hour. Overhead is applied at the rate of $8 per direct labour hour.

Calculate the following budgeted costs:

a) Total metres of direct materials required to produce 40,000 pants: Answer metres

b) Total direct material cost to produce 40,000 pants: $ Answer

c) Total direct labour hours required to produce 40,000 pants: Answer hours

d) Total direct labour cost to produce 40,000 pants: $ Answer

e) Total manufacturing overhead cost applied in the production of 40,000 pants: $ Answer

Now calculate the following standard costs per pants (per unit):

f) Direct material cost per t-shirt: $ Answer per pants

g) Direct labour cost per t-shirt: $ Answer per pants

h) Manufacturing overhead cost per t-shirt: $ Answer per pants

i) Standard cost of one unit of product: $ Answer per pants

Solutions

Expert Solution

Standard DATA for

40000

Pants

Quantity (SQ)

Rate (SR)

Standard Cost

[A]

[B]

[A x B]

Direct Material

( 0.60 metres x 40000 Pants)=24000 metres

$      4.00

$ 96,000.00

Direct labor

( 0.15 hours of direct labor x 40000 Pants)=6000 hours of direct labor

$    18.00

$    1,08,000.00

Variable Overhead

( 0.15 Hours x 40000 Pants)=6000 Hours

$      8.00

$       48,000.00

a) Total metres of direct materials required to produce 40,000 pants: 24000 metres

b) Total direct material cost to produce 40,000 pants: $96,000

c) Total direct labour hours required to produce 40,000 pants: 6000 hours

d) Total direct labour cost to produce 40,000 pants: $ 108,000

e) Total manufacturing overhead cost applied in the production of 40,000 pants:$ 48000

Total standard cost

Units

Cost per Unit

Material

$ 96,000.00

40000

$ 2.40

Direct labor

$ 1,08,000.00

40000

$ 2.70

Overheads

$      48,000.00

40000

$ 1.20

Total standard cost pet pant

$ 6.30

f) Direct material cost per t-shirt: $ 2.4 per pants

g) Direct labor cost per t-shirt: $ 2.7 per pants

h) Manufacturing overhead cost per t-shirt: $ 1.2 per pants

i) Standard cost of one unit of product: $ 6.3 per pants


Related Solutions

1. Griffith Company manufactures suitcases. The company is currently producing and selling 40,000 units per year...
1. Griffith Company manufactures suitcases. The company is currently producing and selling 40,000 units per year and it has the capacity to produce 42,000 units per year. The following information relates to current production: Sale price per unit $195 Costs per unit: Variable Manufacturing $80 Fixed Manufacturing $15 Variable Selling and Administrative $45 Fixed Selling and Administrative $10 Griffith is considering an order from a new customer for 2,000 suitcases at a total price of price of $250,000. Assume that...
A 5-year project requires equipment that costs $100,000. If undertaken, the shareholders will contribute $40,000 cash...
A 5-year project requires equipment that costs $100,000. If undertaken, the shareholders will contribute $40,000 cash and borrow $60,000 at 7% with an interest-only loan with a maturity of 5 years and annual interest payments. The equipment will be depreciated straight-line to zero over the 5-year life of the project. There will be a pre-tax salvage value of $10,000. There are no other start-up costs at year 0. During years 1 through 5, the firm will sell 50,000 units of...
A&Y Inc. considers a 7-year project that requires $500,000 of investment in new machinery and $40,000...
A&Y Inc. considers a 7-year project that requires $500,000 of investment in new machinery and $40,000 in NWC (that will stay constant for the entire life of the project). At the end of the project the equipment will be sold for a salvage value of $70,000. The cost of capital is 10%, the equipment belongs to a CCA class with d=40%, and the corporate tax rate is 30% Problem 20: Prof Reynolds was able to use his industry connections to...
1 Assume that a project has a starting cost of $300,000 in year 1. $40,000 each...
1 Assume that a project has a starting cost of $300,000 in year 1. $40,000 each year in Year 2, 3, and 4. Estimated benefits of the project are $0 in Year 1 and $ 120,000 each year in Year 2, 3, and 4. Use a discount rate of 7% and round the discount rate into two decimal points. Calculate the NPV for this project. calculate the project ROI.
A 10-year steel pipe-producing project requires $66 million in upfront investment (all in depreciable assets). The...
A 10-year steel pipe-producing project requires $66 million in upfront investment (all in depreciable assets). The expected price per pipe is $64 and the variable cost is $24 per widget. The fixed costs excluding depreciation are expected to be $14 million per year for ten years. The upfront investment will be depreciated on a straight line basis for the 10-year useful life of the project to $6 million book value. The expected salvage value of the assets is $14 million....
A 10-year steel pipe-producing project requires $66 million in upfront investment (all in depreciable assets). The...
A 10-year steel pipe-producing project requires $66 million in upfront investment (all in depreciable assets). The expected price per pipe is $64 and the variable cost is $24 per widget. The fixed costs excluding depreciation are expected to be $14 million per year for ten years. The upfront investment will be depreciated on a straight line basis for the 10-year useful life of the project to $6 million book value. The expected salvage value of the assets is $14 million....
E25-1 Parsons Company is planning to produce 2,000 units of product in 2017. Each unit requires...
E25-1 Parsons Company is planning to produce 2,000 units of product in 2017. Each unit requires 3 pounds of materials at $5 per pound and a half-hour of labor at $16 per hour. The overhead rate is 70% of direct labor. Instructions (a) Compute the budgeted amounts for 2017 for direct materials to be used, direct labor, and applied overhead. (b) Compute the standard cost of one unit of product. (c) What are the potential advantages to a corporation of...
Use the FV formula for each of the questions below. Alpha Motors offered a $40,000 per year job with a 3.5% guaranteed raise each year
Use the FV formula for each of the questions below. Alpha Motors offered a $40,000 per year job with a 3.5% guaranteed raise each year for the next 10 years, what will be your salary in 10 years?
A generator costs $150 and requires $80 in maintenance for each year of its 3 year...
A generator costs $150 and requires $80 in maintenance for each year of its 3 year life. After 3 years this generator will be replaced by a new one. The generator is straight-line depreciable to zero and has no salvage value. Assume a tax rate of 35 percent and a discount rate of 15 percent. What is the Operating Cash Flow (OCF) per year associated with the generator project?
A generator costs $150 and requires $80 in maintenance for each year of its 3 year...
A generator costs $150 and requires $80 in maintenance for each year of its 3 year life. After 3 years this generator will be replaced by a new one. The generator is straight-line depreciable to zero and has no salvage value. Assume a tax rate of 35 percent and a discount rate of 15 percent. What is the Equivalent Annual Cost (EAC) of the generator?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT